更多“The()process analyzes the effect of risk events and assigns a numerical rating to those risks.()A.Risk Identification B.Quantitative Risk AnalysisC.Qualitative Risk Analysis D.Risk Monitoring and Control”相关问题
  • 第1题:

    Sensitivity analysis can be used in risk analysis to:

    A Substitute for uncertainty analysis in risk quantification

    B estimate the level of risk aversion adopted by management

    C estimate the effect of change of one project variable on the overall project

    D A and B

    E All of the above.


    正确答案:C

  • 第2题:

    15 Total project risk can be defined as:

    A. the sum of the probabilities of project risks events times the sum of consequences of those risks

    B. the sum of the products of each project risk event times its consequences

    C. the sum of the consequences of all project risk events

    D. the sum of the probabilities of all project risk events

    E. 1 - the sum of the probabilities of all project risk events


    正确答案:B

  • 第3题:

    186 Risk management requires an understanding that _____ .

    A. the degree of greatest uncertainty occurs in the Conceptual Phase of the Life Cycle.

    B. risk identification must be directly aligned with the Work Breakdown Structure.

    C. it is merely advanced preparation for possible adverse future events.

    D. it does not imply complete control of events

    E. All of the above


    正确答案:E

  • 第4题:

    108 Risk mitigation is the process of _____ .

    A. transferring risk to another party.

    B. reducing uncertainty on the project

    C. identifying all possible risk events

    D. monitoring status and making adjustments

    E. All of the above


    正确答案:B

  • 第5题:

    Workarounds are determined during which risk management process? (75).

    A. Risk identification

    B. Quantitative risk analysis

    C. Plan risk responses

    D. Risk monitoring and control


    正确答案:D
    权变措施是在风险管理过程中的(75)过程确定的?。A.风险识别B.风险定量分析C.规划风险应对D.风险监测和控制

  • 第6题:

    setting redundant components in subsystem to handle with the risks brought by the defaultsof original components,what kind of risk response strategy is this?()

    A.risk avoidance

    B.risk acceptance

    C.risk mitigation

    D.contingency plan


    正确答案:C
    设置冗余组件的子系统处理的原始成分的违约带来的风险,这是一种什么样的风险应对策略?()A、风险规避B、风险接受C、风险减轻D、应急计划

  • 第7题:

    ()is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluating risk process effectiveness throughout the project.

    A.Identity risks

    B.Control risks

    C.Plan risk responses

    D.Plan risk management


    正确答案:B

  • 第8题:

    The(75)process analyzes the effect of risk events and assigns a numerical rating to those risks.

    A.Risk Identification

    B.Quantitative Risk Analysis

    C.Qualitative Risk Analysis

    D.Risk Monitoring and Control


    正确答案:B
    解析:定量风险分析过程分析风险事件的影响并对这些风险赋予一个数值化的评价。

  • 第9题:

    ( ) Assesses the priority of identified risks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame and risk tolerance of the project constraints of cost,schedule,scope,and quality.

    A.Quantitative Risk Analysis
    B.Qualitative Risk Analysis
    C.Enterprise Environmental Factors
    D.Risk Management Plan

    答案:B
    解析:
    翻译:(71)利用风险发生概率、风险一旦发生对项目产生的影响以及其他因素(如时间框架和项目制约条件,即成本、进度、范围、质量的风险承受度水平),对已识别风险进行优先级的评估。A.定量风险分析 B.定性风险分析 C.企业环境因素 D.风险管理计划

  • 第10题:

    The()process analyzes the effect of risk events and assigns a numerical rating to those risks.

    • A、Riskldentification
    • B、Quantitative RiskAnalysis
    • C、Qualitative RiskAnalysis
    • D、Risk Monitoring and Control

    正确答案:B

  • 第11题:

    单选题
    The()process analyzes the effect of risk events and assigns a numerical rating to those risks.
    A

    Riskldentification

    B

    Quantitative RiskAnalysis

    C

    Qualitative RiskAnalysis

    D

    Risk Monitoring and Control


    正确答案: B
    解析: 该题的关键词为"analyzes the effect of risk, numerical rating",其语句结构为"The()一process(主语)analyzes(谓语)the effect of risk events(宾语)and assigns(并列谓语)anumerical rating to those risks(并列宾语)",含义为"什么过程分析风险事件的后果,并且为这些风险指定数值级别",容易判断题目描述的是量化风险分析的特点,应该选择选项B。

  • 第12题:

    单选题
    The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.
    A

    Riskldentification

    B

    Quantitative Risk Analysis

    C

    Qualitative Risk Analysis

    D

    Risk Monitoring and Control


    正确答案: C
    解析: 该题的关键词为"ascertains、documenting the risks' characteristics",其语句结构为"The()_process(主语)ascertains(谓语)which risks have the potential of affecting the project and documenting the risks' characteristics",含义为"什么过程确定那些可能影响项目的风险并记录这些风险特征",根据风险管理知识领域,识别并记录风险是风险识别子过程的主要任务,所以选择A

  • 第13题:

    Total project risk can be defined as:

    A the sum of the probabilities of project risks events times the sum of consequences of those risks

    B the sum of the products of each project risk event times its consequences

    C the sum of the consequences of all project risk events

    D the sum of the probabilities of all project risk events

    E 1 - the sum of the probabilities of all project risk events.


    正确答案:B

  • 第14题:

    157 Sensitivity analysis can be used in risk analysis to:

    A. Substitute for uncertainty analysis in risk quantification

    B. estimate the level of risk aversion adopted by management

    C. estimate the effect of change of one project variable on the overall project

    D. A and B

    E. All of the above


    正确答案:C

  • 第15题:

    26 Risk mitigation is the process of _____ .

    A. transferring risk to another party.

    B. reducing uncertainty on the project

    C. identifying all possible risk events

    D. monitoring status and making adjustments

    E. All of the above.


    正确答案:B

  • 第16题:

    The( )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring and Control


    正确答案:A
    风险识别(RiskIdentification)是确定何种风险可能会对项目产生影响,并将这些风险的特征形成文档。

  • 第17题:

    Setting redundant components in subsystem to handle with the risks brought by the defaults of original components, what kind of risk response strategy is this ? ( 75 ).

    A.Risk avoidance

    B.Risk acceptance

    C.Risk mitigation

    D.Contingency plan


    正确答案:C

  • 第18题:

    The (72) process analyzes the effect of risk events and assigns a numerical rating to those risks.

    A.Quantitative Risk Analysis

    B.Risk Identification

    C.Qualitative Risk Analysis

    D.Risk Monitoring and Control


    正确答案:A

  • 第19题:

    The______process ascertains which risks have the potential Of affecting the proect and documenting the risks' characteristics.

    A.Risk Identification

    B.Quantitative Risk Analysis

    C.Qualitative Risk Analysis

    D.Risk Monitoring and Control


    正确答案:A
    解析:项目风险管理主要包括风险管理计划编制、风险识别、定性风险分析、定量风险分析、风险应对计划编制和风险监控。其中,风险识别过程是确定哪些风险可能会对项目产生影响,并将这些风险的特征形成文档。选项A是风险识别,选项B是定量风险分析,选项C是定性风险分析,选项D是风险监控。

  • 第20题:

    The ( ) process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.

    A.Risk Identification
    B.Quantitative Risk Analysis
    C.Qualitative Risk Analysis
    D.Risk Monitoring anD.Control

    答案:A
    解析:
    项目风险管理主要包括风险管理计划编制、风险识别、定性风险分析、定量风险分析、风险应对计划编制和风险监控。其中,风险识别过程是确定哪些风险可能会对项目产生影响,并将这些风险的特征形成文档。
    A.风险识别 B.定量风险分析 C.定性风险分析 D.风险检测与控制

  • 第21题:

    The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.

    • A、Riskldentification
    • B、Quantitative Risk Analysis
    • C、Qualitative Risk Analysis
    • D、Risk Monitoring and Control

    正确答案:A

  • 第22题:

    The()process analyzes the effect of risk events and assigns a numerical rating to those risks.

    • A、Risk Identification
    • B、Quantitative Risk Analysis
    • C、Qualitative Risk Analysis
    • D、Risk Monitoring and Control

    正确答案:B

  • 第23题:

    单选题
    The()process analyzes the effect of risk events and assigns a numerical rating to those risks.
    A

    Risk Identification

    B

    Quantitative Risk Analysis

    C

    Qualitative Risk Analysis

    D

    Risk Monitoring and Control


    正确答案: C
    解析: 暂无解析