()is the process of determining. documenting and managing stakeholder needs and requirements to meet project objectivesA.Collecting requirementsB.Defining requirementsC.Creating WBSD.Requirements analysis

题目

()is the process of determining. documenting and managing stakeholder needs and requirements to meet project objectives

A.Collecting requirements

B.Defining requirements

C.Creating WBS

D.Requirements analysis


相似考题
更多“()is the process of determining. documenting and managing stakeholder needs and requi ”相关问题
  • 第1题:

    Rateyourlevelofproficiencywithconfiguring,managing,andtroubleshootingaccesstoresources,suchasfiles,folders,offlinefiles,sharedfolders,andlocalandnetworkprinters.()

    A.VeryHigh

    B.High

    C.Moderate

    D.Low

    E.VeryLow


    参考答案:A

  • 第2题:

    Configuration management is focused on the specification of both the deliverables and the processes;while( )is focused on identifying,documenting,and approving or rejecting changes to the project documents,deliverables,or baselines.

    A.cost management
    B.change management
    C.configuration management
    D.capacity management

    答案:B
    解析:

  • 第3题:

    ( )is the process of determining,documenting ,and managing stakeholder needs and requirements to meet project objectives.

    A.Collecting requirements
    B.Defining requirements
    C.Creating WBS
    D.Requirements analysis

    答案:A
    解析:
    翻译:收集需求是一个确定、记录、管理干系人需求以便满足项目需求的过程。A.收集需求 B.定义需求C.创建WBS D.需求分析

  • 第4题:

    Mother hasn’t much money and it is only by good__________that she is able to buy all we need.

    A.manages

    B.manage

    C.management

    D.managing


    正确答案:C
    句意虽然指“管理”,在介词by后作宾语,故选择其名词形式。

  • 第5题:

    Because administering the whole company,he sometimes has to work around the clock.

    A:.adjusting
    B:evaluating
    C:engaging
    D:managing

    答案:D
    解析:
    题干意为“因为要管理整个公司,他有时不得不夜以继日地工作。” 句中划线词意为“管理,执行”。D项managing意为“管理,经营,处理”;例句:I feel confi- dent of his ability to manage the business here.我相信他能搞好这里的经营。A项意为“调整,使适合”;B项意为“评估”;C项意为“从事,雇用,使参加”;故选D。

  • 第6题:

    Requirements management is the process of (73) ,analyzing,tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholders.

    A.communicating
    B.collecting
    C.filing
    D.documenting

    答案:D
    解析:
    需求管理是针对需求进行(过程记录),分析,跟踪,优先考虑,控制变更并与相关干系人沟通的过程。