Your project is behind schedule due to conflict between team members. Having resolved the conflict,to get the project back on schedule,you should consider ( ) . A.crashing the scheduleB.performing resource leveling C.conducting reverse resource allocation

题目
Your project is behind schedule due to conflict between team members. Having resolved the conflict,to get the project back on schedule,you should consider ( ) .

A.crashing the schedule
B.performing resource leveling
C.conducting reverse resource allocation scheduling
D.utilizing the critical chair resources

相似考题
更多“Your project is behind schedule due to conflict between team members. Having resolved the conflict,to get the project back on schedule,you should consider ( ) .”相关问题
  • 第1题:

    11 When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.

    A. Reduce features and/or functionality

    B Increase risk.

    C. Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)

    D. All of the above.

    E. A and B only


    正确答案:D

  • 第2题:

    96 A negative cost variance and positive schedule variance means:

    A. The project is under budget and ahead of schedule

    B. The project is over budget and behind schedule

    C. The project is over budget and ahead of schedule

    D. The project will be overrun but ahead of schedule at completion


    正确答案:C

  • 第3题:

    ● The Work Breakdown Structure (WBS) is the basis for communicating:

    A Project scope, cost control, schedule, quality

    B Project objectives, dependencies, plan, cost control

    C Project scope, schedule, staffing, cost control

    D Project scope, quality, schedule, dependencies

    E Project budget, schedule, risk factors, work assignments.


    正确答案:A

  • 第4题:

    ● You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as (74) .

    (74)

    A.Ahead of schedule

    B.Behind schedule

    C.On schedule

    D.Having not enough information provided


    正确答案:B

  • 第5题:

    ● The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to (73) .

    (73)

    A. measure, delay, record, distribute, analyze, and direct

    B. plan, schedule, monitor, control, report, and forecast

    C. promote, highlight, monitor, control, forecast, and report

    D. emphasize, visualize, analyze, conceptualize, report, and record


    正确答案:B

  • 第6题:

    Your project is behind schedule due to conflict between team members. Having resolved the conflict, to get the project back on schedule, you should consider __(74)__.

    A.crashing the schedule

    B.performing resource leveling

    C.conducting reverse resource allocation scheduling

    D.utilizing the critical chair resources


    正确答案:D
    你的项目由于团队成员之间的冲突而导致进度滞后了,为了解决这种冲突,让项目回到计划进度上来,你应该考虑的是利用临界(应急)资源。

  • 第7题:

    Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and ( )

    A.fast tracking

    B.what-if scenario analysis

    C.resource leveling

    D.critical chain method


    正确答案:A

  • 第8题:

    Earned value management(EVM)integrates the scope baseline with the()baseline,along with schedule baseline,to form the performance,which helps the project management team assess and measure project performance and progress.

    A.qulity
    B.risk
    C.change
    D.cost

    答案:D
    解析:
    本题翻译:
    挣值管理(EVM)将范围基线与()基线以及进度基线结合起来,形成绩效基线,帮助项目管理团队评估和衡量项目绩效和进度。
    A.质量B.风险C.变更D.成本
    其实此题只需要知道两个英文词就可以做出题,第一个就是EVM,挣值管理,属于成本管理里面用到的工具与技术,那此题答案就出来了,成本的英文就是D选项。所以英文题不需要会翻译所有的单词,记住题眼也是可以答题的,所以日常复习中,背几个英文单词,也很有帮助。
    题干多读几遍,有个印象,也是一个知识点。

  • 第9题:

    The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()

    • A、Data flow model
    • B、The project critical path
    • C、Resource loading chart
    • D、WBS (Work Breakdown Structure)

    正确答案:B

  • 第10题:

    You work as a network exchange administrator at company.com.the company.com network currently consists of a single active directory forest containing a single domain named company.com.the company.com organization makes use of microsoft exchange server 2010 as their messaging solution.thecompany.com organization currently makes use of a computer named -ex01.during the course of the business week you receive instruction from company.com to configure a retention period of 30 days for all deleted message items whilst ensuring that each item which passes the retention period are removed between 3:00 and 5:00 on a daily basis. What should you do?()

    • A、you should consider having the maintenance schedule of king database changed for the retention and removal of message items.
    • B、you should consider having the messaging record management (mrm) schedule for-ex01 changed for the retention and removal of message items.
    • C、you should consider having the set-retention policy cmdlet run to schedule the retention and removal of message items.
    • D、you should consider having the start-managed folder assistant cmdlet run to schedule the retention and removal of message items.

    正确答案:A

  • 第11题:

    单选题
    You work as a network Exchange administrator at Company.com.The Company.com network currently consists of a single Active Directory forest containing a single domain named Company.com.The Company.com organization makes use of Microsoft Exchange Server 2010 as their messaging solution.During the course of the day a network user named Mia Hamm reports that certain meetings are missing from her calendar.Company.com requested that you recover the missing calendar items for Mia Hamm whilst ensuring your solution recovers the missing items automatically.What should you do?()
    A

    You should consider having the Set-MailboxCalendarConfiguration cmdlet run.

    B

    You should consider having the schedule set for the Calendar Repair Assistant (CRA).

    C

    You should consider having a Sharing policy created and configured.

    D

    You should consider having the schedule set for the Managed Folder Assistant.


    正确答案: B
    解析: 暂无解析

  • 第12题:

    单选题
    You work as a network exchange administrator at company.com.the company.com network currently consists of a single active directory forest containing a single domain named company.com.the company.com organization makes use of microsoft exchange server 2010 as their messaging solution.thecompany.com organization currently makes use of a computer named -ex01.during the course of the business week you receive instruction from company.com to configure a retention period of 30 days for all deleted message items whilst ensuring that each item which passes the retention period are removed between 3:00 and 5:00 on a daily basis. What should you do?()
    A

    you should consider having the maintenance schedule of king database changed for the retention and removal of message items.

    B

    you should consider having the messaging record management (mrm) schedule for-ex01 changed for the retention and removal of message items.

    C

    you should consider having the set-retention policy cmdlet run to schedule the retention and removal of message items.

    D

    you should consider having the start-managed folder assistant cmdlet run to schedule the retention and removal of message items.


    正确答案: B
    解析: 暂无解析

  • 第13题:

    131 The project team form. of organization confers both advantages and disadvantages. Disadvantages of the project form. include:

    A. Conflict in authority between project manager and functional managers

    B. Dual allegiance on part of team members

    C. Complex prioritization of resources

    D. Loss of developed procedures on project dissolution

    E. All of the above


    正确答案:E

  • 第14题:

    13 The project team form. of organization confers both advantages and disadvantages. Disadvantages of the project form. include:

    A. Conflict in authority between project manager and functional managers

    B. Dual allegiance on part of team members "

    C. Complex prioritization of resources

    D. Loss of developed procedures on project dissolution

    E. All of the above


    正确答案:E

  • 第15题:

    The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned


    正确答案:C
    挣值管理(EVM)是一种常用的绩效测量方法。它综合考虑项目范围、进度与成本指标,帮助项目管理团队评估项目绩效。如果某个项目的成本绩效指数(CPI=EV/AC)值小于1.0,则说明已完成的工作的成本超支(the cost overrun for work completed)。

  • 第16题:

    You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week perio.As of today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as (74) .

    A.Ahead of schedule

    B.Behind schedule

    C.On schedule

    D.Having not enough information provided


    正确答案:B
    你是一个项目经理。你目前负责的项目预算是50万元,工期是6周。到目前为止,你已经花费了26万工程款,完成了预算中28万的工作量。根据你之前制定的进度计划,到目前为止,你应该花费30万元工程款。根据这些描述,你的工程目前____________。

  • 第17题:

    ● Your project is behind schedule due to conflict between team members. Having resolved the conflict, to get the project back on schedule, you should consider __(74)__.

    (74)A.crashing the schedule

    B.performing resource leveling

    C.conducting reverse resource allocation scheduling

    D.utilizing the critical chair resources


    正确答案:D
    你的项目由于团队成员之间的冲突而导致进度滞后了,为了解决这种冲突,让项目回到计划进度上来,你应该考虑的是利用临界(应急)资源。

  • 第18题:

    In project time management processes,( )involves identifying and documenting the relationships between project activities.

    A.activity definition

    B.activity sequencing

    C.schedule control

    D.Schedule development


    正确答案:B

  • 第19题:

    The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such , the schedule is used by the project management team to()

    A.Measure, delay, record, distribute, analyze, and direct
    B.Plan, schedule, monitor, control, report, and forecast
    C.Promote, highlight, monitor, control, forecast, and report
    D.Emphasize, visualize, analyze, conceptualize, report and record

    答案:B
    解析:
    项目进度计划不只是一个列出项目规定活动的时间表,而且还是一个用于决策的工具。如:进度计划可以被项目管理团队用来(73)。A.检测,延时,记录,分发,分析和直接B.计划,日程安排,监督,控制,报告和预测C.提升,亮点,监视,控制,预测和报告D.重点化,可视化,分析,概念化,报告和记录

  • 第20题:

    Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().

    • A、crashing the schedule
    • B、performing resource leveling
    • C、conducting reverse resource allocation scheduling
    • D、utilizing the critical chain resources

    正确答案:A

  • 第21题:

    You work as a network Exchange administrator at Company.com.The Company.com network currently consists of a single Active Directory forest containing a single domain named Company.com.The Company.com organization makes use of Microsoft Exchange Server 2010 as their messaging solution.During the course of the day a network user named Mia Hamm reports that certain meetings are missing from her calendar.Company.com requested that you recover the missing calendar items for Mia Hamm whilst ensuring your solution recovers the missing items automatically.What should you do?()

    • A、You should consider having the Set-MailboxCalendarConfiguration cmdlet run.
    • B、You should consider having the schedule set for the Calendar Repair Assistant (CRA).
    • C、You should consider having a Sharing policy created and configured.
    • D、You should consider having the schedule set for the Managed Folder Assistant.

    正确答案:B

  • 第22题:

    You work as a network Exchange administrator at Company.com.The Company.com network currently consists of a single Active Directory forest containing a single domain named Company.com.The Company.com organization makes use of Microsoft Exchange Server 2010 as their messaging solution.During the course of the business week you receive instruction from Company.com to ensure that all the network users are able to automatically schedule the use of a projector.What should you do?()

    • A、You should consider having the schedule for the Managed Folder Assistant modified.
    • B、You should consider having the properties of the Calendar managed default folder modified.
    • C、You should consider having a new Sharing policy created.
    • D、You should consider having an equipment mailbox created.

    正确答案:D

  • 第23题:

    单选题
    You work as a network Exchange administrator at Company.com.The Company.com network currently consists of a single Active Directory forest containing a single domain named Company.com.The Company.com organization makes use of Microsoft Exchange Server 2010 as their messaging solution.During the course of the business week you receive instruction from Company.com to ensure that all the network users are able to automatically schedule the use of a projector.What should you do?()
    A

    You should consider having the schedule for the Managed Folder Assistant modified.

    B

    You should consider having the properties of the Calendar managed default folder modified.

    C

    You should consider having a new Sharing policy created.

    D

    You should consider having an equipment mailbox created.


    正确答案: C
    解析: 暂无解析