第1题:
Setting redundant components in subsystem to handle with the risks brought by the defaults of original components, what kind of risk response strategy is this ? ( 75 ).
A.Risk avoidance
B.Risk acceptance
C.Risk mitigation
D.Contingency plan
第2题:
In object-oriented(51), objects can be viewed as reusable components, and once the programmer has developed a(52)of these components, he can(53)the amount of new coding required. But(52)a(54)is no simple task because the integrity of the Original software design is critical. Reusability can be a mixed blessing for user, too, as a programmer has to be able to find the object he needs. But if(55)is your aim, reusability is worth the risk.
A.programming
B.creating
C.indisposing
D.library
E.maximize
第3题:
Microsoffs COM is a software(66)that allows applications to be built from binary software components. COM defines a binary standard for function calling between components, a way for components to dynamically discover the interfaces implemented by other components, and a mechanism to identify components and their interfaces uniquely.OLE is a compound(67)standard developed by Microsoft. OLE makes it possible to create(68)with one application and link or embed them in a second application. Embedded objects retain their original format and(69)to the application that created them. Support for OLE is built into the Windows and MacOS Operating Systems. A(70)compound document standard developed mainly by Apple and IBM is called OpenDoc.
A.architecture
B.protocol
C.procedure
D.structure
第4题:
Refer to the exhibit. What are three of the basic components of a VoIP network?()
第5题:
setting redundant components in subsystem to handle with the risks brought by the defaults of original components,what kind of risk response strategy is this?()
第6题:
Which four are components of the Cisco collaboration Architecture strategy?()
第7题:
Which of the following is a management strategy of iDataPlex?()
第8题:
To enhance the availability of an application running under HACMP, a decision was made to use The application monitoring facility. The application consists of several components and can take several minutes to initialize. The components use socket communication and can be initialized in any order as long as it is a serial order. The customer’s concern is that if the application stop and start scripts are used during application monitoring recovery,it may take an extraordinary length of time to reset all of the application components. What can be done to ensure the best recover time?()
第9题:
WCS
WLSE
WLC
WDS
LWAPP
第10题:
Challenge
Exploit
Avoid
Enhance
第11题:
software voice applications
multipoint control unit (MCU)
gatekeeper
call agent
interactive voice response (IVR) systems
softphones
第12题:
WCS
WLSE
Location Appliance
WDS
WLSE-Express
第13题:
setting redundant components in subsystem to handle with the risks brought by the defaultsof original components,what kind of risk response strategy is this?()
A.risk avoidance
B.risk acceptance
C.risk mitigation
D.contingency plan
第14题:
()is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluating risk process effectiveness throughout the project.
A.Identity risks
B.Control risks
C.Plan risk responses
D.Plan risk management
第15题:
第16题:
What are the components of the JTAPI Subsystem?()
第17题:
What are three components of a scheduler?()
第18题:
What components are required to support the collaborative workspace feature?()
第19题:
What is the primary purpose of the Technical and Delivery Assessment (TDA)?()
第20题:
risk avoidance
risk acceptance
risk mitigation
contingency plan
第21题:
Any one component can be eliminated to extinguish a fire
Any two components must be eliminated to properly extinguish a fire
Any three components must be eliminated to properly extinguish a fire
Ali four components must be eliminated to extinguish any fire
第22题:
interoperability
clod computing
intercompany communications
dedicated networking
video
enterprise social networking
covergence protocols
第23题:
provider
CTI ports
call control groups
CMT Dialog Control Group
trigger
RM provider