( ) is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.A.Quality assurance(QA) B.Quality planning C.Quality control(QC) D.Quality costs

题目
( ) is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.

A.Quality assurance(QA)
B.Quality planning
C.Quality control(QC)
D.Quality costs

相似考题
参考答案和解析
答案:A
解析:
质量计划是质量管理的一部分,致力于制定质量目标,并规定必要的运行过程和相关资源以实现项目质量目标。
质量控制就是项目团队的管理人员采取有效措施,监督项目的具体实施结果,判断它们是否符合项目有关的质量标准,并消除产生不良结果原因的途径。
质量成本是指为满足质量要求所付出的主要成本。
质量保证是通过对质量计划的系统实施,确保项目需要的相关过程达到预期要求的质量活动。选项A是质量保证(QA),选项B是质量计划,选项C是质量控制(QC),选项D是质量成本。因此应选择A。
更多“( ) is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.”相关问题
  • 第1题:

    Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.

    A.Project

    B.project management team

    C.performingorganization

    D.customer


    参考答案:C

    该题的关键词为"determine quality policies,objectives and responsibilities",其语句结构为"Project Quality Management processes(主语)include(谓语)all the activities of the (宾语)that determine quality policies,objectives and responsibilities(定语从句)",含义为"项目质量管理过程包括决定质量政策、质量目标以及质量责任的什么的所有活动",根据项目质量管理知识,只有组织才可以决定项目的质量政策,因而此处选择选项C。

  • 第2题:

    ● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.

    t

    A.Integration

    B.Scope

    C.Configuration

    D.Requiremen


    正确答案:B

  • 第3题:

    ______is the application of planned,systematic quality activities to ensure that the project will employ all processes needed to meet requirements.

    A.euality assurance(QA)

    B.Quality planning

    C.Quality control(QC)

    D.Quality costs


    正确答案:A
    解析:质量计划是质量管理的一部分,致力于制定质量目标,并规定必要的运行过程和相关资源以实现项目质量目标。
      质量控制就是项目团队的管理人员采取有效措施,监督项目的具体实施结果,判断它们是否符合项目有关的质量标准,并消除产生不良结果原因的途径。
      质量成本是指为满足质量要求所付出的主要成本。
      质量保证是通过对质量计划的系统实施,确保项目需要的相关过程达到预期要求的质量活动。选项A是质量保证(QA),选项B是质量计划,选项C是质量控制(QC),选项D是质量成本。因此应选择A。

  • 第4题:

    ● ()is the application ion of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.()A. Quality assurance (QA) B. Quality planningC. Quality control (QC) D. Quality costs


    正确答案:A
    质量保证是一项有计划的、系统的质量活动,以确保项目的所有过程达到并符合要求。

  • 第5题:

    ● Plan Quality is the process of identifying quality requirements and standards for the project and product, and documenting how the project will demonstrate compliance.(75) is a method that analyze all the costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirement, and failing to meet requirements.

    (75)

    A.Cost-Benefit analysis

    B.Control charts

    C.Quality function deployment

    D.Cost of quality analysis


    正确答案:D
    试题(75)分析
     质量分析成本Cost of quality analysis是对产品或服务进行需求一致性分析所产生的成本;
     成本效益分析Cost-Benefit analysi是通过比较项目的全部成本和效益来评估项目价值的一种方法;
     控制图Control charts是项目质量控制方法;
     质量功能展开Quality function deployment是把顾客或市场的要求转化为设计要求、零部件特性、工艺要求、生产要求的多层次演绎分析方法
     因此,因此选D
    参考答案
    (75)D

  • 第6题:

    Plan Quality is the process of identifying quality requirements and standards for the project and product and documenting how the project will demonstrate compliance ______ is a method that analyze all the costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirement and failing to meet requirements.

    A.Cost-Benefit analysis

    B.Control charts

    C.Quality function deployment

    D.Cost of quality analysis


    正确答案:D

  • 第7题:

    ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.

    A:Create scopE
    B:Project stakeholder management
    C:Project scope management
    D:Project cost management

    答案:C
    解析:

  • 第8题:

    ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.

    A. Create scopE
    B. Project stakeholder management
    C. Project scope management
    D. Project cost management

    答案:C
    解析:

  • 第9题:

    Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.

    • A、Project
    • B、project management team
    • C、performingorganization
    • D、customer

    正确答案:C

  • 第10题:

    Project()Management includes the processes required to ensure that theproj ect includes all the work required, and only the work required, to complete the project successfully.

    • A、Integration
    • B、Scope
    • C、Configuration
    • D、Requirement

    正确答案:B

  • 第11题:

    单选题
    Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.
    A

    Project

    B

    project management team

    C

    performingorganization

    D

    customer


    正确答案: B
    解析: 该题的关键词为"determine quality policies,objectives and responsibilities",其语句结构为"Project Quality Management processes(主语)include(谓语)all the activities of the (宾语)that determine quality policies,objectives and responsibilities(定语从句)",含义为"项目质量管理过程包括决定质量政策、质量目标以及质量责任的什么的所有活动",根据项目质量管理知识,只有组织才可以决定项目的质量政策,因而此处选择选项C。

  • 第12题:

    单选题
    Quality planning tools are often used to help plan effective quality management activities.( ) is one of such tools,which involves company actual or planned project practices to those or other projects to generate ideas for improvementand to provide a basis by which to measure performance.
    A

    Benchmarking

    B

    Quality metric

    C

    Quality checklist

    D

    Brainstorming


    正确答案: C
    解析: 参考答案:A

  • 第13题:

    ● (73)is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.

    (73)

    A. Quality assurance (QA)

    B. Quality planning

    C. Quality control (QC)

    D. Quality costs


    正确答案:A

  • 第14题:

    ●Quality planning tools are often used to help plan effective quality management activities.(71) is one of such tools, which involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance.

    (71)A. Benchmarking

    B. Quality metric

    C. Quality checklist

    D. Brainstorming


    正确答案:A

  • 第15题:

    Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.

    A.Developing project charter

    B.Developing project management plan

    C.Analyzing project risks

    D.Monitoring and controlling project


    正确答案:C

  • 第16题:

    Project Quality Management processes include all the activities of the (75) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.

    A.performing organization

    B.project management team

    C.project

    D.customer


    正确答案:A

  • 第17题:

    Project (24) Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

    A.Integration

    B.Scope

    C.Configuration

    D.Requirement


    正确答案:B
    解析:项目范围管理包括为确保项目包含且仅包含成功完成项目必需工作的所需过程。

  • 第18题:

    ()is the application of planned,systematic quality activities to ensure thatthe project will employ all processes needed to meet requirements.

    A.Quality assurance(QA)
    B.Quality planning
    C.Quality control(QC)
    D.Quality costs

    答案:A
    解析:
    质量计划是质量管理的一部分,致力于制定质量目标,并规定必要的运行过程和相关资源以实现项目质量目标。质量控制就是项目团队的管理人员采取有效措施,监督项目的具体实施结果,判断它们是否符合项目有关的质量标准,并消除产生不良结果原因的途径。质量成本是指为满足质量要求所付出的主要成本。质量保证是通过对质量计划的系统实施,确保项目需要的相关过程达到预期要求的质量活动。选项 A 是质量保证(QA),选项B 是质量计划,选项 C 是质量控制(QC),选项 D 是质量成本。因此应选择 A。

  • 第19题:

    ()is the application of planned,systematic.quality activities to ensure that the project will employ all processes to meet requirements.

    A.Quality assurance
    B.Quality planning
    C.Quality control
    D.Quality cost

    答案:A
    解析:
    翻译:
    ()是计划的应用于系统的质量活动,确保该项目将采用所有流程来满足需求。
    A.质量保证B..质量计划C.质量控制D..质量成本

  • 第20题:

    Quality planning tools are often used to help plan effective quality management activities.( ) is one of such tools,which involves company actual or planned project practices to those or other projects to generate ideas for improvementand to provide a basis by which to measure performance.

    • A、Benchmarking
    • B、Quality metric
    • C、Quality checklist
    • D、Brainstorming

    正确答案:A

  • 第21题:

    Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.

    • A、Benchmarking
    • B、Quality metric
    • C、Quality checklist
    • D、Brainstornung

    正确答案:A

  • 第22题:

    Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

    • A、Integration
    • B、Scope
    • C、Configuration
    • D、Requirement

    正确答案:D

  • 第23题:

    单选题
    Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.
    A

    Benchmarking

    B

    Quality metric

    C

    Quality checklist

    D

    Brainstornung


    正确答案: C
    解析: 暂无解析