Managing risk and documenting them is very important in project planning process.You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the(73) .A.pro

题目
Managing risk and documenting them is very important in project planning process.You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the(73) .

A.project management plan
B.project baseline
C.riskresponse plan
D.risk baseline

相似考题
参考答案和解析
答案:A
解析:
风险管理和记录它们是非常重要的在项目规划过程。在过程定义关键风险中,包括约束和假设,应对计划和对突发事件的处理。这些细节将被包含在项目管理计划中。
更多“Managing risk and documenting them is very important in project planning process.You are in the process of defining key risks, including constraints and assumptions, and planned responses and conting”相关问题
  • 第1题:

    ●(71)assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame. and risk tolerance of the project constraints of cost, schedule, scope, and quality.

    (71)

    A. Quantitative Risk Analysis

    B. Qualitative Risk Analysis

    C. Enterprise Environmental Factors

    D. Risk Management Plan


    正确答案:B

  • 第2题:

    The project()is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteria

    A.work performance information

    B.scope statement

    C.change requests

    D.process analysis


    正确答案:B

  • 第3题:

    Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses


    正确答案:A
    风险管理并不能使得项目经理及其团队在项目的规划过程中避免大多数的风险。

  • 第4题:

    ●Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the (73).

    (73)A. project management plan

    B. project baseline

    C. risk response plan

    D. risk baseline


    正确答案:A

  • 第5题:

    ()is the process of determining. documenting and managing stakeholder needs and requirements to meet project objectives

    A.Collecting requirements

    B.Defining requirements

    C.Creating WBS

    D.Requirements analysis


    正确答案:A

  • 第6题:

    Risk management allows the project manager and the project team not to (71).

    A.eliminate most risks during the planning phase of the project

    B.identify project risks

    C.identify impacts of various risks

    D.plan suitable responses


    正确答案:A

  • 第7题:

    The______process ascertains which risks have the potential Of affecting the proect and documenting the risks' characteristics.

    A.Risk Identification

    B.Quantitative Risk Analysis

    C.Qualitative Risk Analysis

    D.Risk Monitoring and Control


    正确答案:A
    解析:项目风险管理主要包括风险管理计划编制、风险识别、定性风险分析、定量风险分析、风险应对计划编制和风险监控。其中,风险识别过程是确定哪些风险可能会对项目产生影响,并将这些风险的特征形成文档。选项A是风险识别,选项B是定量风险分析,选项C是定性风险分析,选项D是风险监控。

  • 第8题:

    Risk management allows the project manager and the project team not to()

    A.eliminate most risks during the planning phase of the project
    B.identify project risks
    C.identify impacts of various risks
    D.plan suitable responses

    答案:A
    解析:
    下面不属于风险管理中项目经理和项目团队职责的是(71)。A.排除大部分项目执行中的风险B.风险识别C.风险分析D.妥善处理

  • 第9题:

    ( )is the process of determining,documenting ,and managing stakeholder needs and requirements to meet project objectives.

    A.Collecting requirements
    B.Defining requirements
    C.Creating WBS
    D.Requirements analysis

    答案:A
    解析:
    翻译:收集需求是一个确定、记录、管理干系人需求以便满足项目需求的过程。A.收集需求 B.定义需求C.创建WBS D.需求分析

  • 第10题:

    The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.

    • A、work performance information
    • B、scope statement
    • C、changerequests
    • D、process analysis

    正确答案:B

  • 第11题:

    ()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.

    • A、Quantitative Risk Analysis
    • B、Qualitative Risk Analysis
    • C、Enterprise Environmental Factors
    • D、Risk Management Plan

    正确答案:B

  • 第12题:

    单选题
    ()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.
    A

    Quantitative Risk Analysis

    B

    Qualitative Risk Analysis

    C

    Enterprise Environmental Factors

    D

    Risk Management Plan


    正确答案: B
    解析: 参考答案:B

  • 第13题:

    ● Risk management allows the project manager and the project team not to(71).

    (71)

    A.eliminate most risks during the planning phase of the project

    B.identify project risks

    C.identify impacts of various risks

    D.plan suitable responses


    正确答案:A

    试题(71)分析
      下面不属于风险管理中项目经理和项目团队职责的是  (71)  。
      A.排除大部分项目执行中的风险        B.风险识别
      C.风险分析                          D.妥善处理
    参考答案
    (71)A

  • 第14题:

    ______assesses the priority of identified ri sks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame. and risk tolerance of the project constraints of cost,schedule,scope,and quality.

    A.Quantitative Risk Analysis

    B.Qualitative Risk Analysis

    C.Enterprise Environmental Factors

    D.Risk Management Plan


    正确答案:B
    解析:定性风险分析利用风险发生概率、风险一旦发生对项目产生的影响以及其他因素(如时间框架和项目制约条件,即成本、进度、范围、质量的风险承受度水平),对已识别风险进行优先级的评估。
    选项A是定量风险分析,选项B是定性风险分析,选项C是企业环境因素,选项D是风险管理计划。故B是正确的。

  • 第15题:

    The( )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring and Control


    正确答案:A
    风险识别(RiskIdentification)是确定何种风险可能会对项目产生影响,并将这些风险的特征形成文档。

  • 第16题:

    The project(73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.

    A.work performance information

    B.scope statement

    C.change requests

    D.process analysis


    正确答案:B
    解析:项目范围说明书是制订质量计划的—项关键输入,这是因为它记载了项目的主要可交付成果以及用于确定重要项目干系人需求的项目目标、限值和验收标准。

  • 第17题:

    Since risk is associated with most projects,the best course of action is to ( )

    A.cover all project risks by buying appropriate insurance

    B.ignore the risks,since nothing can be done about them and move forward with the project in an expeditious manner

    C.avoid project with clear and present risk

    D.identify various risks and implement actions to mitigate their potential impact


    正确答案:D
    识别所有风险,潜在应对措施。

  • 第18题:

    ()is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluating risk process effectiveness throughout the project.

    A.Identity risks

    B.Control risks

    C.Plan risk responses

    D.Plan risk management


    正确答案:B

  • 第19题:

    ()is the process of identifying individual project risks as well as source of overall project risk,and documenting their characteristics.

    A.identify risks
    B.monitor risks
    C.implement risks responses
    D.plan risk management

    答案:A
    解析:
    翻译:()是识别单个项目风险以及整个项目风险的来源,并记录其特征的过程。
    A.识别风险
    B.监控风险
    C.实施风险应对措施
    D.计划风险管理
    识别风险是识别单个项目风险以及整个项目风险的来源,并记录其特征的过程。

  • 第20题:

    ( )is the process of determining,documenting ,and managing stakeholder needs and requirements to meet project objectives.

    A.Collecting requirements
    B.Defining requirements
    C.Creating WBS
    D.Requirements analysis

    答案:A
    解析:
    翻译:收集需求是一个确定、记录、管理干系人需求以便满足项目需求的过程。A.收集需求 B.定义需求C.创建WBS D.需求分析

  • 第21题:

    The ( ) process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.

    A.Risk Identification
    B.Quantitative Risk Analysis
    C.Qualitative Risk Analysis
    D.Risk Monitoring anD.Control

    答案:A
    解析:
    项目风险管理主要包括风险管理计划编制、风险识别、定性风险分析、定量风险分析、风险应对计划编制和风险监控。其中,风险识别过程是确定哪些风险可能会对项目产生影响,并将这些风险的特征形成文档。
    A.风险识别 B.定量风险分析 C.定性风险分析 D.风险检测与控制

  • 第22题:

    The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.

    • A、Riskldentification
    • B、Quantitative Risk Analysis
    • C、Qualitative Risk Analysis
    • D、Risk Monitoring and Control

    正确答案:A

  • 第23题:

    单选题
    The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.
    A

    Riskldentification

    B

    Quantitative Risk Analysis

    C

    Qualitative Risk Analysis

    D

    Risk Monitoring and Control


    正确答案: A
    解析: 该题的关键词为"ascertains、documenting the risks' characteristics",其语句结构为"The()_process(主语)ascertains(谓语)which risks have the potential of affecting the project and documenting the risks' characteristics",含义为"什么过程确定那些可能影响项目的风险并记录这些风险特征",根据风险管理知识领域,识别并记录风险是风险识别子过程的主要任务,所以选择A