1
2
3
4
第1题:
A customer is planning on having a single Virtual I/O Server (VIOS) configuration in a Power 750. They haveselected a 4-port 1Gb Integrated Virtual Ethernet (IVE). There will be no other network cards installed in the system. One IVE logical port will be used in the VIO Server and will be used as the physicalport in a Shared Ethernet Adapter (SEA). What is the maximum number of IVE logical ports available to use inother LPARs?()
第2题:
Company.com wants to build two Dynamic Logical Partitions (DLPAR) on a p5-520. They have a requirement for communication between the two DLPARs. Which feature of virtualization will satisfy this requirement?()
第3题:
Which of the following would be the FIRST step to configure a Virtual I/O Server(VIOS)?()
第4题:
A customer is considering procuring HP servers with Virtual Server Environment (VSE) to consolidate servers and dynamically move resources between partitions. How can the technical sales representative position PowerVM as the solution to virtualize this server environment?()
第5题:
Which of the following steps should be done FIRST when deploying a Virtual I/O server on a p5-550, which will host three logical partitions: a NIM server and two application servers?()
第6题:
Companycom wants to use Virtual SCSI disks to boot multiple operating systems from the same disk. How will the volumes appear in the Virtual IO Server and how will the logical volumes appear in the partition?()
第7题:
Add the devices as virtual adapters to a VIO server first,then add the I/O drawer and create the shared ethernet adapters
Power down the partitions,run the diag a command when the system is brought back up and reconfigure the network cards
Use the rmdev command to remove the devices,shut down the partitions and move the cads,then run the cfgmgr command after reboot
Detach the network cards,run rmdev on the devices and then dynamically reassign theadapters to the partitions and reconfigure
第8题:
PowerVM supports shared servers compared to VSE
PowerVM supports shared processors and memory compared to VSE
PowerVM supports shared processors, memory and I/O compared to VSE
PowerVM supports DLPAR without a reboot and supports dedicated I/O compared to VSE
第9题:
Configure VIO Server Express Edition to control the tape library through one fibre channel card.Assign the library to the production partitions when needed.
Configure the IBM i partition to own the tape library.Use IBM i virtualization to host a virtual tape library connection to the AIX and Linux partition.Assign the library to the production partitions when needed.
Configure a fibre channel card for each partition, and a configure fibre switch.Connect the partitions and tape library to the switch.Zone the switch so all partitions can enable the tape when needed and disable the tape when finished.
Configure AIX to control the tape library through one fibre channel adapter.Use AIX virtualization to host a virtual tape library connection to the IBM i and Linux partitions.Assign the library to the production partitions when needed.
第10题:
Add memory to the database partition to improve response time.
Add additional Host Bus Adapters to the server to improve IO throughput.
Modify CPU allocations to favor the database partition.
Increase CPU allocations to the Virtual I/O Server.
第11题:
On the host server, install the MS Loopback adapter.
On the host server, enable the Multipath I/O feature.
On the virtual machine, install the MS Loopback adapter.
On the virtual machine, install Windows Server virtualization Guest Integration Components.
第12题:
The I/O workload needs of the client LPARs
The processing requirements of the client LPARs
The memory requirements of the client LPARs
The virtual Ethernet requirements between client LPARs
第13题:
The database on a p5-570 Micro-Partition has grown and backups are not meeting the Service Level Agreement. There are several partitions using the Virtual I/O Server to access the storage array. The database backup has high CPU utilization while the others have low CPU utilization. What adjustment can the technical specialist make to ensure that the Service Level Agreement is achieved?()
第14题:
A system is being planned with three production partitions, one each for an IBM i, AIX standard edition, and Power Linux applications. One fibre-channel attached TS3100 tape library will be shared between the partitions for backup. Which solution provides tape library sharing with minimum operator intervention?()
第15题:
A customer is debating whether to use Shared Ethernet versus Virtual Ethernet. Which of the following best describes a key difference between Shared and Virtual Ethernet?()
第16题:
What is the minimum number of CECs required to avoid single points of failure on a Power 570 server?()
第17题:
Company.com is adding a new I/O drawer to an existing p5-570 with four LPARs and wants to re-balance the network cards in the I/O drawers. What is the best way to accomplish this?()
第18题:
Allocate the HBA to a client partition.
Restart the Virtual I/O Server to detect the changes.
Install the device driver for the DS8000 in each of the four AIX partitions.
Allocate the HBA to the VIO server partition and install necessary drivers.
第19题:
Design the solution and present it confidently so the customer does not question it.
Design the solution and ensure the customer understands the unknowns with the new technology.
Explain to the customer that the VIO Server does not benefit them when doing server consolidation so it has not been configured.
Explain to the customer that the details surrounding the VIO Server have not been clearly defined so designing a solution is premature.
第20题:
Boot the HMC with the VIOS media.
Assign SAN-attached disks to the database partitions.
Create logical volumes for the VIOS on rootvg disks.
Identify the location of the internal SCSI disks for the VIOS.
第21题:
Shared Ethernet runs on POWER4 systems
Virtual Ethernet runs on POWER4 systems
Shared Ethernet requires a Virtual I/O server and Advanced Power Virtualization
Virtual Ethernet requires a Virtual I/O server and Advanced Power Virtualization
第22题:
Create and install the NIM server
Create and install the Virtual I/O Server
Create and install the application servers
Activate Advanced POWER Virtualization
第23题:
The Virtual SCSI disks are defined as logical volumes in the Virtual IO Server. The logical volumes appear as real devices (hdisks) in the client partitions.
The Virtual IO adapters are connected to a virtual host bridge. On the Virtual IO Server they are vdisks, on the client partition, the exported disks are visible as virtual disks.
The Virtual SCSI disks are represented in the ODM as a bus device whose parent is sysplanar0. Logical volumes will be assigned to the Virtual IO Server and virtual disks, vdisks, in the client partition.
The Virtual IO adapters are represented as adapter devices with the virtual host bridge as their parent. On the Virtual IO Server they are vdisks attached to vscsi, on the client partition the exported disks are visible as virtual disks.