单选题A customer is concerned about rising power costs, and the limited space they have left in the computer room. They have been doing some research into virtualization and would like to know if they should pursue this solution. Which of the following archi

题目
单选题
A customer is concerned about rising power costs, and the limited space they have left in the computer room. They have been doing some research into virtualization and would like to know if they should pursue this solution. Which of the following architectural features should be discussed with them?()
A

x3650 M3 servers and racks

B

x3550 M3 servers, VMware and racks

C

BladeCenter, blades and VMware

D

x3620 M3 servers and VMware


相似考题

4.Do you have any idea what you would like to be and do after graduation? A lot of people don′! begin thinking about careers until they reach junior or senior year, which, in my opinion, is too late. When people are trying to decide what they want to do, it helps to know something they love. Ever since I was little, I′ve always been doing someone′s hair, make-up or nails, starting with Barbie dolls and progressing to humans. Over the years my family has really inspired me to do this and now I fix friends′ and family members′ hair for weddings, dances and other big events. I have been thinking about what I would like to do for a career since middle school. I did some research and discovered that I might really enjoy being a cosmetologist, so I went to my hair stylist and asked her lots of questions about what it takes to reach her level and what she would recommend I do. I considered her advice and then did more research. I used Aveda′ s website to get information on the Aveda Institute and what type of credit (贷款) I would need from high school to apply. I found their institute has three parts: theoretical knowledge, practical experience, and professional business-building skills. For the past few years, I have been looking at Aveda in more and more detail. This school not only offers cosmetology, but also massage therapy. I grew up in Minnesota (美国中北部的一个州), so I plan to apply to the institute in Minneapolis that several people have highly recommended. It helps students become "future industry leaders in hair care, skin care, makeup and total body wellness". It is affordable and everyone there is friendly and understanding. Having done the groundwork and thinking about what I′d like to do after high school, I know that I will definitely pursue my dream of becoming a cosmetologist. We know from the text that a cosmetologist is ___________.A.a chemist working at college B.a person who works in the institute C.a doctor in a hospital D.a person doing all types of body care for people

更多“单选题A customer is concerned about rising power costs, and the limited space they have left in the computer room. They have been doing some research into virtualization and would like to know if they should pursue this solution. Which of the following archi”相关问题
  • 第1题:

    A customer would like to have the ability to permanently activate processor and memory resources as their workload increases. Which of the following supports the customer requirement?()

    • A、Reserve Capacity on Demand
    • B、Utility Capacity on Demand
    • C、Capacity Upgrade on Demand
    • D、Uncapped Capacity on Demand

    正确答案:C

  • 第2题:

    Which of the following is a sign that a computer has been infected by a worm?()

    • A、Screensaver changed on its own
    • B、Unauthorized outgoing emails being sent
    • C、Desktop background changed on its own
    • D、Left and right mouse buttons have been flipped

    正确答案:B

  • 第3题:

    You have successfully sold and installed your customer’s System x solution. Sometimes, the overall succeed of a sale depends on how well you have trained your customer to support their new hardware. Please consider the following tools. Which one would be the best for protectively determining a server outage, and contacting the system administrator about the outage?()

    • A、CDAT
    • B、Configuration and Options Guide (COG)
    • C、Physical Alarm Sounding in Data Center
    • D、IBM Systems Director

    正确答案:D

  • 第4题:

    A customer is concerned about rising power costs, and the limited space they have left in the computer room. They have been doing some research into virtualization and would like to know if they should pursue this solution.Which of the following architectural features should be discussed with them?()

    • A、x3650 M3 servers and racks 
    • B、x3550 M3 servers, VMware and racks 
    • C、BladeCenter, blades and VMware 
    • D、x3620 M3 servers and VMware 

    正确答案:C

  • 第5题:

    A customer is concerned about increasing storage capacity costs in their NAS storageinfrastructure. Which IBM technology would directly address this concern?()

    • A、 Easy Tier 
    • B、 Real-time Compression Appliance 
    • C、 FlashCopy Space Efficient (SE) 
    • D、 ProtecTIER deduplication

    正确答案:B

  • 第6题:

    A new customer wants to install a Power 750 in a warehouse location that has no local staff to support it. They are concerned about hardware support and would like to have the system notify IBM service if there is an issue.Which actions will address the customer concern?()

    • A、Enable automatic problem reporting from smit
    • B、Use IVM to enable console mirroring to IBM Remote Support.
    • C、Use the HMC to enable reporting through Electronic Service Agent.
    • D、Enable Automatic Problem Reporting in ASMI using he embedded modem on the FSP.

    正确答案:C

  • 第7题:

    单选题
    A customer is looking at an Oracle eBusiness solution. They would like to know what hardware they will need for the solution. They have some preliminary information from Oracle, including hardware requirements and specifics for their environment. Which of the following should be done next?()
    A

    Configure a 2 node x3950 X5 

    B

    Customer needs a System p server to support Oracle applications 

    C

    Download the Oracle eBusiness sizing questionnaire from IBM, fill out with customer and submit to IBM for System x sizing 

    D

    Configure a system that meets the minimum requirements


    正确答案: B
    解析: 暂无解析

  • 第8题:

    单选题
    A customer has an existing high availability SAN environment with CLARiiON, which has been stable for 16 months. They have recently experienced several outages with their current storage systems. They need to purchase additional storage and have asked about tier 1 storage. They are concerned with connecting their existing storage and servers without trouble. Which resource should be consulted while developing the solution options?()
    A

    Disk Magic

    B

    TPC for Data

    C

    CLARiiON Procedure Generator

    D

    System Storage Interoperability Center


    正确答案: C
    解析: 暂无解析

  • 第9题:

    单选题
    A customer is concerned about increasing storage capacity costs in their NAS storageinfrastructure. Which IBM technology would directly address this concern?()
    A

     Easy Tier 

    B

     Real-time Compression Appliance 

    C

     FlashCopy Space Efficient (SE) 

    D

     ProtecTIER deduplication


    正确答案: B
    解析: 暂无解析

  • 第10题:

    单选题
    A network technician is concerned about the environmental effects of power consumption and heat from network resources Limited space is also a concern. Which of the following technologies should be implemented?()
    A

    Circuit switching

    B

    Network address translation

    C

    Power over Ethernet

    D

    Virtual servers


    正确答案: B
    解析: 暂无解析

  • 第11题:

    单选题
    A customer is concerned about rising power costs, and the limited space they have left in the computer room. They have been doing some research into virtualization and would like to know if they should pursue this solution.Which of the following architectural features should be discussed with them?()
    A

    x3650 M3 servers and racks 

    B

    x3550 M3 servers, VMware and racks 

    C

    BladeCenter, blades and VMware 

    D

    x3620 M3 servers and VMware 


    正确答案: D
    解析: 暂无解析

  • 第12题:

    单选题
    A customer is very concerned about maintaining a competitive advantage through the use of state-of-the-art technology.  Assuming all solutions meet the customer’s technical requirements, which solution should the IBM team propose to maximize customer satisfaction?()
    A

    p690 with Dynamic LPAR

    B

    Grid of SP switch-attached p5-550s

    C

    p690 with Advanced POWER Virtualization

    D

    p5-570 with Advanced POWER Virtualization


    正确答案: C
    解析: 暂无解析

  • 第13题:

    A manufacturing customer has liminted space remaining in their data center and is concerned about rising power costs. The customer applications require very large amounts of memory. They want server redundancy and no downtime. Which of the following architectural features should be discussed with them?()

    • A、iDataPlex with vSphere
    • B、Four x3550 M3 servers,vSphere and racks
    • C、BladeCenter, HX5 blades and vSphere
    • D、One x3950 X5 servers andvSphere

    正确答案:C

  • 第14题:

    A customer is very concerned about maintaining a competitive advantage through the use of state-of-the-art technology.  Assuming all solutions meet the customer’s technical requirements, which solution should the IBM team propose to maximize customer satisfaction?()

    • A、p690 with Dynamic LPAR
    • B、Grid of SP switch-attached p5-550s
    • C、p690 with Advanced POWER Virtualization
    • D、p5-570 with Advanced POWER Virtualization

    正确答案:D

  • 第15题:

    A customer has been working with your company to purchase an iDataPlex cluster. They have a configuration from IBM and are getting ready to place an order. Which should be done of the following?()

    • A、A solution sizing questionnaire
    • B、Verify the customer has the proper racks
    • C、A Technical Delivery Assessment
    • D、Verify the customer has enough cooling in the computer room

    正确答案:C

  • 第16题:

    A customer is looking at an Oracle eBusiness solution. They would like to know what hardware they will need for the solution. They have some preliminary information from Oracle, including hardware requirements and specifics for their environment. Which of the following should be done next?()

    • A、Configure a 2 node x3950 X5 
    • B、Customer needs a System p server to support Oracle applications 
    • C、Download the Oracle eBusiness sizing questionnaire from IBM, fill out with customer and submit to IBM for System x sizing 
    • D、Configure a system that meets the minimum requirements

    正确答案:C

  • 第17题:

    A customer is looking at an Oracle E-Business solution. They would like to know what hardware they will need for the solution. They have some preliminary information from Oracle, including hardware requirements and specifics for their environment. Which of the following should be done next?()

    • A、Select the Server Proven configuration for Oracle E-Business
    • B、UseeConfig to configure a Power server with AIX to support Oracle E-Business applications
    • C、Download the Oracle E-Business sizing questionnaire from IBM, fill out with customer and submit to IBM for System x sizing
    • D、Use SSCT to configure a system that meets the minimum requirements specified by Oracle E-Business

    正确答案:C

  • 第18题:

    单选题
    A customer is looking at an Oracle E-Business solution. They would like to know what hardware they will need for the solution. They have some preliminary information from Oracle, including hardware requirements and specifics for their environment. Which of the following should be done next?()
    A

    Select the Server Proven configuration for Oracle E-Business

    B

    UseeConfig to configure a Power server with AIX to support Oracle E-Business applications

    C

    Download the Oracle E-Business sizing questionnaire from IBM, fill out with customer and submit to IBM for System x sizing

    D

    Use SSCT to configure a system that meets the minimum requirements specified by Oracle E-Business


    正确答案: A
    解析: 暂无解析

  • 第19题:

    单选题
    A new customer wants to install a Power 750 in a warehouse location that has no local staff to support it. They are concerned about hardware support and would like to have the system notify IBM service if there is an issue.Which actions will address the customer concern?()
    A

    Enable automatic problem reporting from smit

    B

    Use IVM to enable console mirroring to IBM Remote Support.

    C

    Use the HMC to enable reporting through Electronic Service Agent.

    D

    Enable Automatic Problem Reporting in ASMI using he embedded modem on the FSP.


    正确答案: A
    解析: 暂无解析

  • 第20题:

    单选题
    A customer would like to have the ability to permanently activate processor and memory resources as their workload increases. Which of the following supports the customer requirement?()
    A

    Reserve Capacity on Demand

    B

    Utility Capacity on Demand

    C

    Capacity Upgrade on Demand

    D

    Uncapped Capacity on Demand


    正确答案: C
    解析: 暂无解析

  • 第21题:

    单选题
    You have successfully sold and installed your customer’s System x solution. Sometimes, the overall succeed of a sale depends on how well you have trained your customer to support their new hardware. Please consider the following tools. Which one would be the best for protectively determining a server outage, and contacting the system administrator about the outage?()
    A

    CDAT

    B

    Configuration and Options Guide (COG)

    C

    Physical Alarm Sounding in Data Center

    D

    IBM Systems Director


    正确答案: A
    解析: 暂无解析

  • 第22题:

    单选题
    A manufacturing customer has liminted space remaining in their data center and is concerned about rising power costs. The customer applications require very large amounts of memory. They want server redundancy and no downtime. Which of the following architectural features should be discussed with them?()
    A

    iDataPlex with vSphere

    B

    Four x3550 M3 servers,vSphere and racks

    C

    BladeCenter, HX5 blades and vSphere

    D

    One x3950 X5 servers andvSphere


    正确答案: C
    解析: 暂无解析

  • 第23题:

    单选题
    A customer has been working with your company to purchase an iDataPlex cluster. They have a configuration from IBM and are getting ready to place an order. Which should be done of the following?()
    A

    A solution sizing questionnaire

    B

    Verify the customer has the proper racks

    C

    A Technical Delivery Assessment

    D

    Verify the customer has enough cooling in the computer room


    正确答案: C
    解析: 暂无解析

  • 第24题:

    单选题
    A customer is concerned about rising power costs, and the limited space they have left in the computer room. They have been doing some research into virtualization and would like to know if they should pursue this solution. Which of the following architectural features should be discussed with them?()
    A

    x3650 M3 servers and racks

    B

    x3550 M3 servers, VMware and racks

    C

    BladeCenter, blades and VMware

    D

    x3620 M3 servers and VMware


    正确答案: C
    解析: 暂无解析