第1题:
156 Expectancy theory as applied to project management implies that:
A. The team will work the hardest on those goals that are clearly explained by the project manager
B. The more rewards that the project manager provides, the better the performance of the team
C. Team members will work hardest for those project goals that also bring satisfaction to personal goals
D. Employees will work hardest for those project goals which are accompanied by high levels of authority for the individual team members E. None of the above
第2题:
A.disappoint
B.disappointing
C.disappointed
D.to disappoint
第3题:
The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned
第4题:
I had a sandwich before I played tennis, __ I'm very hungry now.
A. but
B. and
C. so
第5题:
There are two main approaches to the study of English words namely()
A、descriptive and prescriptive
B、synchronic and diachronic
C、spoken and written
D、competence and performance
第6题:
The earned value technique is a commonlyused method of performance measurement. It integrates project scope, cost, andschedule measures to help the project management team assess projectperformance.If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, itmeans that (74).
A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
第7题:
Where events have rendered performance of the contract illegal either by English law or by the law of the country in which performance was to have taken place,the Charterer will ______ from the liability to provide a cargo.
A.be provided
B.be excused
C.be supplied
D.be replied
第8题:
第9题:
Your company network has 500 client computers that run Windows 7. Your team consists of 20 desktop support technicians. Two technicians troubleshoot a hardware-related performance issue on a computer. The technicians obtain different results by using their own User Defined Data Collector Sets. You need to create a standardized Data Collector Set on a network share that is accessible to your team. What should you create?()
第10题:
disappoint
disappointing
disappointed
to disappoint
第11题:
In 1912, Thorpe went back to finish his college education.
Thorpe won two gold medals in the 1912 Olympic Games.
Thorpe once played on a baseball team for money.
In 1950, Thorpe was named the greatest American football player.
第12题:
both Spanish and English
both Spanish and French
both English and Italian
both Spanish and German
第13题:
50 Which of the following is least likely to be used in explaining to a team member why you consider his/her performance substandard?
A. Project office memo
B. counseling session
C. project team meeting
D. formal letter
E. individual conversation
第14题:
●To ensure the project team provides the functionality the customerexpects in a new piece of software, the project manager ask the customer forsign-off on the design criteria. These documents are(75).
(75) A. technical specifications
B. performance specifications
C. product descriptions
D. quality assurance
第15题:
SUCCESSFUL TEAM WORK AND TEAM BUILDING Team building skills are critical for your effectiveness as a manager or entrepreneur. And even if you are not in a management or leadership role yet, better understanding of team work can make you a more effective employee and give you an extra edge in your corporate office. Team building success is when your team can accomplish something much bigger and work more effectively than a group of the same individuals working on their own. There are two critical factors in building a high performance team. The first factor in team effectiveness is the diversity of skills and personalities. It means people use their strengths in full, but can compensate for each other's weaknesses. Or, different personality types balance and complement each other. The other critical element of team work success is that all the team efforts are directed towards the same clear goals, the team goals. This relies heavily on good communication in the team and harmony in member relationships. In real life, team work success rarely happens by itself if there are no focused team building efforts or activities. There is simply too much room for problems. For example, different personalities may build up conflicts. Or even worse, some people with similar personalities may start fighting for authority and dominance in certain areas of expertise. Even if the team goals are clear and accepted by everyone, there may be no team commitment to the group goals, or no consensus on the means of achieving those goals. There may be a lack of trust and openness which may block the critical communication and lead to loss of coordination in the individual efforts. This is why every team needs a good leader who is able to deal with all team work issues.
1. Team building skills are not so critical if you are only an employee.()
2. To form. a high performance team, you need many important factors.()
3. A good team should have a diversity of personalities.()
4. Team work success is quite common in practice.()
5. To solve all the problems, you need a capable leader.()
第16题:
A、They play a big role in team spirit.
B、The number of fans watching the game will help increase or reduce the team spirit.
C、Fans give money to support their team.
D、Fans pray for their team.
第17题:
● The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.
(74)A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
第18题:
Your company network has 500 client computers that run Windows 7. Your team consists of 20 desktop support technicians. Two technicians troubleshoot a hardware-related performance issue on a computer. The technicians obtain different results by using their own User Defined Data Collector Sets. You need to create a standardized Data Collector Set on a network share that is accessible to your team. What should you create?()
A.Event Trace Data Collector Set
B.Performance Counter Data Collector Set
C.Performance Counter Alert Data Collector Set
D.System Configuration Information Data Collector Set
第19题:
第20题:
第21题:
provides timely help to every member.
exerts positive influence on team members’ performance.
is a self-motivated person.
doesn’t expect too much accomplishment from members.
第22题:
have known what to do before the game.
have offered tacos to the Churchill team.
not have felt so inferior to the whites.
have played better basketball with his friends.
第23题:
the learning level
practical activities
learning strategies
habits of thinking
第24题:
be provided
be excused
be supplied
be replied