单选题Company.com is running a p5-550 system with inactive processors. The system is managed using the Integrated Virtualization Manager. How would the system administrator activate two additional processors?()A Use the Advanced Systems Management Interface 

题目
单选题
Company.com is running a p5-550 system with inactive processors. The system is managed using the Integrated Virtualization Manager. How would the system administrator activate two additional processors?()
A

Use the Advanced Systems Management Interface to enter the Capacity on Demand Enablement code.

B

Use the Web-based System Manager Interface to enter the Capacity on Demand enablement code.

C

Use smitty or smit interface to enter the Capacity on Demand enablement code.

D

Use oem_setup_env on the Virtual I/O Server to enter the Capacity on Demand enablement code.


相似考题
更多“单选题Company.com is running a p5-550 system with inactive processors. The system is managed using the Integrated Virtualization Manager. How would the system administrator activate two additional processors?()A Use the Advanced Systems Management Interface ”相关问题
  • 第1题:

    Company.com is running a p5-550 system with inactive processors. The system is managed using the Integrated Virtualization Manager. How would the system administrator activate two additional processors?()

    • A、Use the Advanced Systems Management Interface to enter the Capacity on Demand Enablement code.
    • B、Use the Web-based System Manager Interface to enter the Capacity on Demand enablement code.
    • C、Use smitty or smit interface to enter the Capacity on Demand enablement code.
    • D、Use oem_setup_env on the Virtual I/O Server to enter the Capacity on Demand enablement code.

    正确答案:A

  • 第2题:

    A large shipping company that is standardized on Fibre Channel storage has just acquired a regional shipping company that is using an IBM XIV system. The large company would like to integrate the XIV system into the environment and manage all data through a single management interface. Which product should be suggested so that all data can be managed?()

    • A、IBM DS8700
    • B、IBM XIV GUI
    • C、IBM System Storage N7600
    • D、IBM SAN Volume Controller (SVC)

    正确答案:D

  • 第3题:

    Which of the following interfaces is required to implement Workload Partition Mobility? ()

    • A、 Workload Partitions Manager for AIX
    • B、 Hardware Management Console (HMC) GUI
    • C、 Integrated Virtualization Manager (IVM)
    • D、 Advanced System Management Interface (ASMI)

    正确答案:A

  • 第4题:

    Which of the following is a feature of Integrated Virtualization Manager (IVM)? ()

    • A、 It has a GUI interface for upgrading system firmware. 
    • B、 It creates and manages AIX/Linux and VIOS type LPARs. 
    • C、 It can be managed by the Hardware Management Console (HMC). 
    • D、 It supports Live Partition Mobility on POWER6 systems and above.

    正确答案:D

  • 第5题:

    System configurations on the HMC have been backed up correctly. After a restore, the partitions are defined with different characteristics than the running systems. What is the most probable cause of this problem?()

    • A、The LPAR Configuration backup is corrupt
    • B、The LPAR Configuration has been altered using DLPAR
    • C、The LPAR Configuration backup was performed on a different HMC
    • D、The LPAR Configuration has been altered through the Advanced System Management Interface (ASMI) on the server after the backup was performed

    正确答案:B

  • 第6题:

    单选题
    Company.com is running a p5-550 system with inactive processors. The system is managed using the Integrated Virtualization Manager. How would the system administrator activate two additional processors?()
    A

    Use the Advanced Systems Management Interface to enter the Capacity on Demand Enablement code.

    B

    Use the Web-based System Manager Interface to enter the Capacity on Demand enablement code.

    C

    Use smitty or smit interface to enter the Capacity on Demand enablement code.

    D

    Use oem_setup_env on the Virtual I/O Server to enter the Capacity on Demand enablement code.


    正确答案: B
    解析: 暂无解析

  • 第7题:

    单选题
    Your company has an Active Directory Domain Services (AD DS) domain. You virtualize applications by using Microsoft Application Virtualization (App-V). You are creating an application virtualization package. Which should you use?()
    A

    Microsoft Application Virtualization Sequencer

    B

    Microsoft Application Virtualization Desktop Client

    C

    Microsoft System Center Application Virtualization Streaming Server

    D

    Microsoft System Center Application Virtualization Management Server


    正确答案: B
    解析: 暂无解析

  • 第8题:

    单选题
    Which of the following interfaces is required to implement Workload Partition Mobility? ()
    A

     Workload Partitions Manager for AIX

    B

     Hardware Management Console (HMC) GUI

    C

     Integrated Virtualization Manager (IVM)

    D

     Advanced System Management Interface (ASMI)


    正确答案: C
    解析: 暂无解析

  • 第9题:

    单选题
    System configurations on the HMC have been backed up correctly. After a restore, the partitions are defined with different characteristics than the running systems. What is the most probable cause of this problem?()
    A

    The LPAR Configuration backup is corrupt

    B

    The LPAR Configuration has been altered using DLPAR

    C

    The LPAR Configuration backup was performed on a different HMC

    D

    The LPAR Configuration has been altered through the Advanced System Management Interface (ASMI) on the server after the backup was performed


    正确答案: C
    解析: 暂无解析

  • 第10题:

    单选题
    A system administrator for a business recovery service center needs to test disaster recovery strategies for their clients running Linux. Each client has a different system configuration. Each time a client comes in, the system configuration of the managed system must change. What is the best way to handle this using LPAR?()
    A

    Create a system profile. Reconfigure the managed system by activating and deactivating the system profiles. 

    B

    Create one partition profile for each client. Reconfigure the managed system by activating the partition profiles for that client. 

    C

    Dynamically move processors and memory as needed into each logical partition. Reconfigure the managed system by activating and deactivating partition profiles. 

    D

    Dynamically move processors and memory into each logical partition on the server if additional resources are needed. Reconfigure the managed system by activating and deactivating the system profiles.


    正确答案: D
    解析: 暂无解析

  • 第11题:

    单选题
    Company.com is running a p5-550 system with inactive processors. The system is managed using the Integrated Virtualization Manager. How would the system administrator activate two additional processors?()
    A

    Use the Advanced Systems Management Interface to enter the Capacity on Demand Enablement code.

    B

    Use the Web-based System Manager Interface to enter the Capacity on Demand enablement code.

    C

    Use smitty or smit interface to enter the Capacity on Demand enablement code.

    D

    Use oem_setup_env on the Virtual I/O Server to enter the Capacity on Demand enablement code.


    正确答案: D
    解析: 暂无解析

  • 第12题:

    单选题
    A customer would like to implement an IBM System Storage DS8000 solution. A Capacity Magic study has determined that 500 drives of 450 GB are required to meet the customer’s capacity requirements. Limited space is available for additional systems in the data center.  Which solution  best meets the customer’s requirements()
    A

    DS8800 system with three frames

    B

    DS8800 system with one frame

    C

    DS8700 system with two frames

    D

    DS8800 system with two frames


    正确答案: B
    解析: 暂无解析

  • 第13题:

    A system administrator for a business recovery service center needs to test disaster recovery strategies for their clients running Linux. Each client has a different system configuration. Each time a client comes in, the system configuration of the managed system must change. What is the best way to handle this using LPAR?()

    • A、Create a system profile. Reconfigure the managed system by activating and deactivating the system profiles. 
    • B、Create one partition profile for each client. Reconfigure the managed system by activating the partition profiles for that client. 
    • C、Dynamically move processors and memory as needed into each logical partition. Reconfigure the managed system by activating and deactivating partition profiles. 
    • D、Dynamically move processors and memory into each logical partition on the server if additional resources are needed. Reconfigure the managed system by activating and deactivating the system profiles.

    正确答案:B

  • 第14题:

    A customer needs a system supporting four partitions, each with the following requirements: ? 0.6 1.65GHz processors ? 2GB memory ? AIX 5.2 They also need the ability to grow the system in the future.  Which pSeries system would be positioned best to meet this customer’s requirements?()

    • A、p5-550 with the Advanced POWER Virtualization feature and AIX 5.2
    • B、p5-550 with the POWER5 processor technology and AIX 5.2
    • C、p5-570 with the Advanced POWER Virtualization feature and AIX 5.3
    • D、p5-570 with the POWER5 processor technology and AIX 5.2

    正确答案:D

  • 第15题:

    A POWER6 595 LPAR has two dedicated processors. The LPAR is active and running AIX 6.1. What must be done to donate any unusedprocessing capacity to the shared processor pool?()

    • A、In the HMC Properties, select the options to allow processor sharing when the partition is inactive and active.
    • B、In the LPAR Properties, select the options to allow processor sharing when the partition is inactive and active.
    • C、In the LPAR Profile Properties, select the options to allow processor sharing when the partition is inactive and active.
    • D、In the 595 Managed System Properties, select the options to allow processor sharing when partitions are inactive and active.

    正确答案:C

  • 第16题:

    Company.com is ordering a new p5-570 and planning for the option of using Capacity on  Demand to activate additional resources in the future. Which of the following is a prerequisite to support the addition of CPUs or memory without an outage?()

    • A、Use Micro-Partitioning
    • B、Configure a Virtual I/O Server
    • C、Configure dynamic logical partitions
    • D、Activate Advanced POWER Virtualization

    正确答案:C

  • 第17题:

    Your company has an Active Directory Domain Services (AD DS) domain. You virtualize applications by using Microsoft Application Virtualization (App - V). You are creating an application virtualization package. Which sh ould you use?()

    • A、Microsoft Application Virtualization Sequencer
    • B、Microsoft Application Virtualization Desktop Client
    • C、Microsoft System Center Application Virtualization Streaming Server
    • D、Microsoft System Center Application Virtualization Management Server

    正确答案:A

  • 第18题:

    单选题
    Which of the following can deploy system plans generated by the IBM System Planning Tool (SPT)?()
    A

     The Hardware Management Console (HMC) and Integrated Virtualization Manager (IVM).

    B

     The Hardware Management Console (HMC) and Advanced System Manager Interface (ASMI).

    C

     Integrated Virtualization Manager (IVM) and Advanced System Manager Interface (ASMI).

    D

     Integrated Virtualization Manager (IVM) and BladeCenter Advanced Management Module (AMM).


    正确答案: D
    解析: 暂无解析

  • 第19题:

    单选题
    A large shipping company that is standardized on Fibre Channel storage has just acquired a regional shipping company that is using an IBM XIV system. The large company would like to integrate the XIV system into the environment and manage all data through a single management interface. Which product should be suggested so that all data can be managed?()
    A

    IBM DS8700

    B

    IBM XIV GUI

    C

    IBM System Storage N7600

    D

    IBM SAN Volume Controller (SVC)


    正确答案: D
    解析: 暂无解析

  • 第20题:

    单选题
    A user is reporting that access to a file server is much slower than it has been. The system administrator completes a test of the server using a system monitoring tool and compares it to the previously taken baseline. The comparison shows that there are no significant changes in the use of system resources. Which of the following actions should be taken to resolve this user problem?()
    A

    Add additional RAM to the user PC

    B

    Troubleshoot the user PC

    C

    Add additional RAM to the server

    D

    Add additional hard drive space to the server


    正确答案: C
    解析: 暂无解析

  • 第21题:

    单选题
    A customer has two Power 770 systems with 4 enclosures each.  Thirty two cores and 1TB of memory are activated on each system.  Each system has 3 database partitions and each partition has 10 cores and 300GB of memory.   Which solution will provide automated recovery of unplanned outages at least cost?()
    A

    Purchase PowerVM Enterprise Edition.Use System Director to automate Live Partition Mobility to recover from partition failure

    B

    Create additional shared processor partitions as standby nodes.Use PowerHA SystemMirror to activate and use CoD resources when a failover occurs

    C

    Purchase an additional 32-core Power 750 with PowerHA SystemMirror Standard Edition.Use the new system as standby node with the XD component of PowerHA

    D

    Purchase an additional Power 770 system.Locate production and standby database partitions on each system.Use DB2 pureScale to provide automated partition monitoring and failover


    正确答案: C
    解析: 暂无解析

  • 第22题:

    单选题
    Which of the following is a feature of Integrated Virtualization Manager (IVM)? ()
    A

     It has a GUI interface for upgrading system firmware. 

    B

     It creates and manages AIX/Linux and VIOS type LPARs. 

    C

     It can be managed by the Hardware Management Console (HMC). 

    D

     It supports Live Partition Mobility on POWER6 systems and above.


    正确答案: A
    解析: 暂无解析

  • 第23题:

    单选题
    A customer has an entry level Power System that is currently partitioned and managed by a Hardware Management Console (HMC). For operational reasons, it must be disconnected from the HMC and configured as a new development system.  How should the customer proceed to implement PowerVM Express and Integrated Virtualization Manager (IVM) on this Power System? ()
    A

     Install a VIO server as an additional partition and DLPAR the resources from the existing partition to the VIO server.

    B

     Create a service partition and install a VIO server. This will automatically move resources to the VIO server on reboot of the managed system.

    C

     Delete all the existing LPARs, create a new LPAR and assign all the system resources to this LPAR and then install the VIO server on this LPAR.

    D

     Reset the machine to Manufacturing Default Configuration and install the VIO server on the resulting partition created, which will own all system resources.


    正确答案: D
    解析: 暂无解析

  • 第24题:

    单选题
    A POWER6 595 LPAR has two dedicated processors. The LPAR is active and running AIX 6.1. What must be done to donate any unusedprocessing capacity to the shared processor pool?()
    A

    In the HMC Properties, select the options to allow processor sharing when the partition is inactive and active.

    B

    In the LPAR Properties, select the options to allow processor sharing when the partition is inactive and active.

    C

    In the LPAR Profile Properties, select the options to allow processor sharing when the partition is inactive and active.

    D

    In the 595 Managed System Properties, select the options to allow processor sharing when partitions are inactive and active.


    正确答案: D
    解析: 暂无解析