第1题:
109 Problems can occur in properly defining a project because:
A. Project goals may not be agreeable to all parties
B. The plan was "too loose," thus allowing priorities to change
C. Low turnover of project personnel
D. Too much communication between the client and project personnel
E. The project objectives were quantified
第2题:
139 The project charter is a document designed to tell _____ exactly what the project entails.
A. The project manager
B. The project office
C. The project team
D. The project sponsor
E. Anyone associated with the project
第3题:
● Interfacing with the customer after project go-ahead is the responsibility of:
A Project sponsor
B Project team
C Project manager
D Functional manager
E All of the above are possible, based upon the size and complexity of the project
第4题:
● Problems can occur in properly defining a project because:
A Project goals may not be agreeable to all parties
B The plan was "too loose," thus allowing priorities to change
C Low turnover of project personnel
D Too much communication between the client and project personnel
E The project objectives were quantified
第5题:
The(70)provides the project manager with the authority to apply organizational resources to project activities.
A.project management plan
B.contract
C.project human resource plan
D.project charter
第6题:
The( )provides the project manager with the authority to apply organizational resources to project activities。
A.project management plan
B.project charter
C.project human resource plan
D.project stakeholders
第7题:
JOHN: It seems that the new project in Nanjing will be even better than your current project....
BOB: ___1__That is really an exciting project, and I hope our plan will be approved by the board.
JOHN: Good luck! But unfortunately, from what I’ve seen so far, ___2__the Jinan project does not seem to __3___. Is there any problem I can help with
BOB: Don’t worry! Please believe me that ___4__and I’ll get it back on track soon.
JOHN: I’m sure you can straighten things out. Well,___5__, Bob.
A. everything is under control
B. keep up the good work
C. You got it!
D. I must mention that
E. be up to your usual standard
第8题:
第9题:
第10题:
第11题:
The()provides the project manager with the authority to apply organizational resources to project activities.
第12题:
Your workgroup’s project is critical and there is no time for rebuilding the Windows 2000 Professional desktops in case of disaster. Your company has not yet established automated system replacement that Windows 2000 can provide. What is your most comprehensive option for disaster recovery at this time?()
第13题:
123 The scope baseline/project charter is prepared by the:
A. Project manager
B. Project manager and project office
C. Project manager, project office and functional team
D. Project manager, project office, functional team and project sponsor
E. Project manager, project sponsor and customer/user
第14题:
(A)arranged to
(B) arranged of
(C) arranged in
(D) arranged with
正确答案:D
解答参考:D词组搭配arrange for sb to do sth安排sb做sth【译文】他们安排由最好的医生来给她做手术。
第15题:
● The scope baseline/project charter is prepared by the:
A Project manager
B Project manager and project office
C Project manager, project office and functional team
D Project manager, project office, functional team and project sponsor
E Project manager, project sponsor and customer/user
第16题:
● The project life-cycle can be described as(72).
(72)
A.project concept, project planning, project execution, and project close-out
B.project planning, work authorization, and project reporting
C.project planning, project control, project definition, WBS development, and project termination
D.project concept, project execution, and project reporting
第17题:
are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.
A.Controls
B.Baselines
C.Project stakeholders
D.Project managers
第18题:
Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.
A.Developing project charter
B.Developing project management plan
C.Analyzing project risks
D.Monitoring and controlling project
第19题:
The (73) provides the project manager with the authority to apply organizational resources to project activities.
A.project management plan
B.project charter
C.project human resource plan
D.project stakeholders
第20题:
第21题:
第22题:
() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.
第23题:
With everything arranged properly, the project is surely to () smoothly as planned, step by step.
第24题:
Obtain buy-in and feedback from the customer.
First ask the client executive if financing has been arranged.
Plan the installation and rollout schedule before ordering.
Confirm that any additional requirements are handled by others.