单选题During the implement phase, systems acceptance testing does which of the following for the customer? Select exactly 1 answer(s) from the following:()。A installation, configuration, and testing, as well as the commissioning of tools and processes in acc

题目
单选题
During the implement phase, systems acceptance testing does which of the following for the customer? Select exactly 1 answer(s) from the following:()。
A

installation, configuration, and testing, as well as the commissioning of tools and processes in accordance with the operations implementation plan

B

provision of information regarding customer-specified design requirements and configuration

C

the migration of network services from an existing state to a future state in accordance with the migration plan

D

the provision of an objective means of measuring system operability and functionality


相似考题
更多“During the implement phase, systems acceptance testing does ”相关问题
  • 第1题:

    Many of the activities performed during the preliminary investigation are still being conducted in( ), but in much greater depth than before. During this phase, the analyst must become fully aware of the ( )and must develop enough knowledge about the (3) and the existing systems to enable an effective solution to be proposed and implemented. Besides the ( )for process and data of current system, the deliverable from this phase also includes the ( )for the proposed system.

    (3)应选( )。


    A. harD.ware environment
    B. testing environment
    C. software environment
    D.. business environment


    答案:D
    解析:
    本题考查的是初步调研的相关知识,这个考点可以做个了解。经常考初步调研阶段的许多活动在分析阶段仍然要继续,而且会比以前更深入许多。在分析阶段,分析师必须要完全清楚最终蓝图并且掌握充分的业务环境和目前系统的商业环境,以使一个有效的解决方案被提出并且执行。除了当前系统的过程和数据的逻辑模型,这一阶段的产出物还包括建议系统的正式需求定义。73、A、硬件环境,B、测试环境,C、软件环境,D、商业环境

  • 第2题:

    The purpose of the systems analysis phase is to build a logical model of the new system.The first step is(71),where you investigate business processes and document what the new system must do to satisfy users. This step continues the investigation that began during the(72). You use the fact-finding results to build business models,data and process models,and object models. The deliverable for the systems analysis phase is the(73),which describes management and user requirements,costs and benefits,and outlines alternative development strategies.The purpose of the systems design phase is to create a physical model that will satisfy all documented requirements for the system. During the systems design phase,you need to determine the(74),which programmers will use to transform the logical design into program modules and code. The deliverable for this phase is the(75),which is presented to management and users for review and approval.

    A.application architecture
    B.system datA.model
    C.system process model
    D.implement environment

    答案:C
    解析:
    翻译:系统分析阶段的目的是建立新系统的逻辑模型,第一步就是进行(71),调查业务流程并记录新系统必须做哪些以满足用户需求。这一步是(72)的延续,可以使用调查结果构建业务模型,数据和流程模型以及对象模型。系统分析阶段的可交付成果是(73),它描述了管理和用户要求,成本和收益,还有可替代的方案。系统设计阶段的目的是创建一个能够满足系统所有需求文件要求的物理模型。 在系统设计阶段,需要确定(74),程序员通过系统过程模型把逻辑设计转换为程序模块和代码。该阶段的可交付成果是(75),提交给管理层和用户审查和批准。(74) A.应用程序架构描述B.系统数据模型C.系统过程模型 D.实施环境参考答案:(74)C

  • 第3题:

    During this phase,the analyst must must develop enough knowledge about the ( )and the existing systems to enable an effective solution to be proposed and implemented.

    A.hardware environment
    B.testing environment
    C.software environment
    D.business environment

    答案:D
    解析:
    在这个分析阶段,系统分析师一定要充分掌握关于业务环境和现行系统的知识,以提交和实施一个有效的解决方案。
    A.硬件环境 B.测试环境 C.软件环境 D.业务环境

  • 第4题:

    Which phase includes testing operational processes and procedures in accordance with the Cisco Unified Communications operations plan()

    • A、Operate
    • B、Design
    • C、Deploy
    • D、Implement

    正确答案:D

  • 第5题:

    During the implement phase, systems acceptance testing provides which two of the following services for the customer()

    • A、It installs, configures, and verifies monitoring tools and processes in accordance with the operations implementation.
    • B、It verifies that the Cisco Unified Communications solutions is ready for production.
    • C、It verifies that the Cisco Unified Communications solution meets their business and technical requirements.
    • D、It executes and verifies the migration plan by migrating network services from an existing state to a future state.
    • E、It provides automated tools for measuring system performance under load.

    正确答案:B,E

  • 第6题:

    Which service component in the implement phase is typically performed prior to the handover of a wireless solution to the customer’s operations organization?()

    • A、systems integration
    • B、skill assessment
    • C、systems acceptance testing
    • D、wireless check 
    • E、project close out

    正确答案:C

  • 第7题:

    Which implement phase service component describes the activities to install and test your Cisco Unified Communications solution in a nonproduction lab environment()

    • A、Proof of Concept
    • B、Acceptance Testing
    • C、Staging
    • D、Lab Testing

    正确答案:C

  • 第8题:

    Which service component in the implement phase is typically performed prior to the handover of a wirelesssolution to the customer’s operations organization?()

    • A、Systems Integration
    • B、Systems Acceptance Testing
    • C、Skill Assessment
    • D、Project Close Out
    • E、Wireless Check

    正确答案:A

  • 第9题:

    多选题
    Which two service components are performed during the wireless implement phase?()
    A

    project planning

    B

    configuration management

    C

    wireless readiness assessment

    D

    systems acceptance testing

    E

    site readiness specification


    正确答案: D,C
    解析: 暂无解析

  • 第10题:

    单选题
    Which of the following wireless service components occur in the implement phase?()
    A

    project kickoff,staging,systems acceptance testing,ongoing support handoff meeting

    B

    wlan change management,security administration,technology assessment,operations plan

    C

    security assessment,operations assessment,supplier management

    D

    operations readiness assessment,systems requirements validation,planning project kickoff,service assurance


    正确答案: B
    解析: 暂无解析

  • 第11题:

    单选题
    Which implement phase service component describes the activities to install and test your Cisco Unified Communications solution in a nonproduction lab environment()
    A

    Proof of Concept

    B

    Acceptance Testing

    C

    Staging

    D

    Lab Testing


    正确答案: C
    解析: 暂无解析

  • 第12题:

    多选题
    During the implement phase, systems acceptance testing provides which two of the following services for the customer()
    A

    It installs, configures, and verifies monitoring tools and processes in accordance with the operations implementation.

    B

    It verifies that the Cisco Unified Communications solutions is ready for production.

    C

    It verifies that the Cisco Unified Communications solution meets their business and technical requirements.

    D

    It executes and verifies the migration plan by migrating network services from an existing state to a future state.

    E

    It provides automated tools for measuring system performance under load.


    正确答案: C,B
    解析: 暂无解析

  • 第13题:

    The purpose of the systems analysis phase is to build a logical model of the new system.The first step is(71),where you investigate business processes and document what the new system must do to satisfy users. This step continues the investigation that began during the(72). You use the fact-finding results to build business models,data and process models,and object models. The deliverable for the systems analysis phase is the(73),which describes management and user requirements,costs and benefits,and outlines alternative development strategies.The purpose of the systems design phase is to create a physical model that will satisfy all documented requirements for the system. During the systems design phase,you need to determine the(74),which programmers will use to transform the logical design into program modules and code. The deliverable for this phase is the(75),which is presented to management and users for review and approval.

    A.systems planning phase
    B.systems modeling phase
    C.systems analysis phase
    D.systems design phase

    答案:A
    解析:
    翻译:系统分析阶段的目的是建立新系统的逻辑模型,第一步就是进行(71),调查业务流程并记录新系统必须做哪些以满足用户需求。这一步是(72)的延续,可以使用调查结果构建业务模型,数据和流程模型以及对象模型。系统分析阶段的可交付成果是(73),它描述了管理和用户要求,成本和收益,还有可替代的方案。系统设计阶段的目的是创建一个能够满足系统所有需求文件要求的物理模型。 在系统设计阶段,需要确定(74),程序员通过系统过程模型把逻辑设计转换为程序模块和代码。该阶段的可交付成果是(75),提交给管理层和用户审查和批准。(72) A.系统计划阶段B.系统建模阶段C.系统分析阶段 D.系统设计阶段
    参考答案:(72)A

  • 第14题:

    During this phase, the analyst must become fully aware of the ____ and must develop enough knowledge about the __请作答该选项__ and the existing systems to enable an effective solution to be proposed and implementeD.

    A.hardware environment
    B.testing environment
    C.software environment
    D.business environment

    答案:D
    解析:

  • 第15题:

    Which service component in the implement phase is typically performed prior to the handover of awireless solution to the customer’s operations organization?()

    • A、Systems Integration
    • B、Skill Assessment
    • C、Systems Acceptance Testing
    • D、Wireless Check
    • E、Project Close Out

    正确答案:C

  • 第16题:

    During the implement phase, systems acceptance testing does which of the following for the customer? Select exactly 1 answer(s) from the following:()。

    • A、installation, configuration, and testing, as well as the commissioning of tools and processes in accordance with the operations implementation plan
    • B、provision of information regarding customer-specified design requirements and configuration
    • C、the migration of network services from an existing state to a future state in accordance with the migration plan
    • D、the provision of an objective means of measuring system operability and functionality

    正确答案:D

  • 第17题:

    Which two service components are performed during the wireless implement phase?()

    • A、project planning
    • B、configuration management
    • C、wireless readiness assessment
    • D、systems acceptance testing
    • E、site readiness specification

    正确答案:A,D

  • 第18题:

    Which three of these service components are in the design phase?()

    • A、Account Qualification and Planning
    • B、Detailed Design Development
    • C、Staff Training
    • D、Systems Acceptance Test Plan Development
    • E、Staging Plan Development
    • F、Site Readiness Assessment

    正确答案:B,D,E

  • 第19题:

    There are six phases of the Cisco Lifecycle Services framework. During which of the following phases would the Acceptance Testing be developed and documented?()

    • A、Operate
    • B、Design
    • C、Implement
    • D、Prepare

    正确答案:B

  • 第20题:

    单选题
    Which service component in the implement phase is typically performed prior to the handover of a wirelesssolution to the customer’s operations organization?()
    A

    Systems Integration

    B

    Systems Acceptance Testing

    C

    Skill Assessment

    D

    Project Close Out

    E

    Wireless Check


    正确答案: B
    解析: 暂无解析

  • 第21题:

    单选题
    In which phase is a systems acceptance test plan developed and documented?()
    A

    Implement

    B

    Design

    C

    Prepare

    D

    Operate


    正确答案: A
    解析: 暂无解析

  • 第22题:

    单选题
    Which service component in the implement phase is typically performed prior to the handover of a wireless solution to the customer’s operations organization?()
    A

    systems integration

    B

    skill assessment

    C

    systems acceptance testing

    D

    wireless check 

    E

    project close out


    正确答案: D
    解析: 暂无解析

  • 第23题:

    单选题
    Which service component in the implement phase is typically performed prior to the handover of awireless solution to the customer’s operations organization?()
    A

    Systems Integration

    B

    Skill Assessment

    C

    Systems Acceptance Testing

    D

    Wireless Check

    E

    Project Close Out


    正确答案: D