第1题:
● Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress.
(74)
A.scope statement
B.activity list
C.project charter
D.project schedule
第2题:
Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress. A.scope statement B.activity list C.project charter D.project schedule
第3题:
On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and (71) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.project planning
B.time estimating
C.cost estimating
D.schedule development
第4题:
Estimating activity durations uses information on activity scope of (74), required resource types, estimated resource quantities, and resource calendars.
(74)
A. milestone
B. baseline
C. quality
D. work
第5题:
第6题:
第7题:
第8题:
Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.
第9题:
Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.
第10题:
The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.
第11题:
activity duration estimating, schedule developing, activity resource estimating
activity resource estimating, activity duration estimating, schedule development
schedule developing, activity resource estimating, activity duration estimating
activity resource estimating, schedule developing, activity duration estimating
第12题:
milestone
baseline
quality
work
第13题:
The process of(72)schedule activity durations uses information on schedule activity scope of work,required resource types,estimated resource quantities,and resource calendars with resource availabilities.
A.estimating
B.defining
C.planning
D.sequencing
第14题:
The process of (74) schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.
A.defining
B.estimating
C.planning
D.sequencing
第15题:
On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and(70)are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.time estimating
B.cost estimating
C.project planning
D.schedule development
第16题:
第17题:
第18题:
第19题:
第20题:
On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
第21题:
The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.
第22题:
time estimating
cost estimating
project planning
schedule development
第23题:
estimating
defining
planning
sequencing
第24题:
estimating
defining
planning
sequencing