单选题The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.A estimatingB definingC planningD sequencing

题目
单选题
The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.
A

estimating

B

defining

C

planning

D

sequencing


相似考题
参考答案和解析
正确答案: B
解析: 暂无解析
更多“单选题The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.A estimatingB definingC planningD sequencing”相关问题
  • 第1题:

    ● Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress.

    (74)

    A.scope statement

    B.activity list

    C.project charter

    D.project schedule


    正确答案:D

    试题(74)分析
      计划进展需要对持续时间和资源的评估和修改创建一个被核准的  (74)  ,它可以作为基线,有助于跟踪进展。
      A.范围说明        B.活动列表        C.项目章程        D.项目计划
    参考答案
    (74)D

  • 第2题:

    Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress. A.scope statement B.activity list C.project charter D.project schedule


    正确答案:D
    制定进度表可能要求对历时估算与资源估算进行审查与修改,以便进度表在批准之后能够当做跟踪项目绩效的基准使用。

  • 第3题:

    On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and (71) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

    A.project planning

    B.time estimating

    C.cost estimating

    D.schedule development


    正确答案:D

  • 第4题:

    Estimating activity durations uses information on activity scope of (74), required resource types, estimated resource quantities, and resource calendars.

    (74)

    A. milestone

    B. baseline

    C. quality

    D. work


    正确答案:D

  • 第5题:

    Schedule development can require the review and revision of duration estimates and resource estimates to create an approved () that can serve as a baseline to track progress.

    A.scope statement
    B.activity list
    C.project charter
    D.project schedule

    答案:D
    解析:
    计划进展需要对持续时间和资源的评估和修改创建一个被核准的(74),它可以作为基线,有助于跟踪进展。A.范围说明B.活动列表C.项目章程 D.项目计划

  • 第6题:

    Before a project schedule can be created,the schedule maker should have a ( ) ,an effort estimate for each task,and a resource list with availability for each resource.

    A.work breakdown structure
    B.baseline
    C.software requirements specification
    D.plan

    答案:A
    解析:
    翻译:在项目进度计划制定前,制定者应该有一份工作分解结构,一份针对每个任务的工作量估算,以及可用资源列表。A.工作分解结构 B.基线 C.软件需求说明书 D.计划

  • 第7题:

    Estimating activity
    durations uses information on activity scope of ( ) , required resource types, estimated
    resource quantities, and resource calendars.

    A.milestone
    B. baseline
    C.quality
    D. work

    答案:D
    解析:

  • 第8题:

    Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.

    • A、milestone
    • B、baseline
    • C、quality
    • D、work

    正确答案:D

  • 第9题:

    Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

    • A、activity duration estimating, schedule developing, activity resource estimating
    • B、activity resource estimating, activity duration estimating, schedule development
    • C、schedule developing, activity resource estimating, activity duration estimating
    • D、activity resource estimating, schedule developing, activity duration estimating

    正确答案:B

  • 第10题:

    The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

    • A、estimating
    • B、defining
    • C、planning
    • D、sequencing

    正确答案:D

  • 第11题:

    单选题
    Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.
    A

    activity duration estimating, schedule developing, activity resource estimating

    B

    activity resource estimating, activity duration estimating, schedule development

    C

    schedule developing, activity resource estimating, activity duration estimating

    D

    activity resource estimating, schedule developing, activity duration estimating


    正确答案: A
    解析: 暂无解析

  • 第12题:

    单选题
    Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.
    A

    milestone

    B

    baseline

    C

    quality

    D

    work


    正确答案: B
    解析: 该题的关键词为"required resource types、estimated resource quantities、 resource calendars",其语句结构为"Estimating activity durations(主语)uses(谓语)information on activity scope of_____(宾语)",含义为"估算活动工期应用什么活动范围的信息",结合前面的关键词,此处应该识别出估算活动工期对应的输入项,因而选择工作范围,选择选项D。

  • 第13题:

    The process of(72)schedule activity durations uses information on schedule activity scope of work,required resource types,estimated resource quantities,and resource calendars with resource availabilities.

    A.estimating

    B.defining

    C.planning

    D.sequencing


    正确答案:A
    解析:估算活动历时的过程会用到活动工作范围、所需资源类型、估计的资源数量以及建立在资源可用性上的资源日历等信息。

  • 第14题:

    The process of (74) schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

    A.defining

    B.estimating

    C.planning

    D.sequencing


    正确答案:B

  • 第15题:

    On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and(70)are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

    A.time estimating

    B.cost estimating

    C.project planning

    D.schedule development


    正确答案:D
    解析:在某些项目,特别是在范围较小的项目中,活动排序、活动资源估算、活动历时估算和进度制定连接得如此紧密,以至于它们被视为可以由一个人在相对较短的时间内执行的单独过程。

  • 第16题:

    Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress.

    A.scope statement
    B.activity list
    C.project charter
    D.project schedule

    答案:D
    解析:
    计划进展需要对持续时间和资源的评估和修改创建一个被核准的(74),它可以作为基线,有助于跟踪进展。

    A. 范围说明 B. 活动列表 C. 项目章程 D. 项目计划

  • 第17题:

    Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order.

    A.activity duration estimating, schedule developing, activity resource estimating
    B.activity resource estimating, activity duration estimating, schedule development
    C.schedule developing, activity resource estimating, activity duration estimating
    D.activity resource estimating, schedule developing, activity duration estimating

    答案:B
    解析:
    项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来,合理分配工作量,利用进度安排的有效分析方法来严格监视项目的进展情况,以使得项目的进度不致被拖延。项目时间管理过程包括:活动定义、活动排序、活动的资源估算、活动历时估算、制订进度计划及进度控制6个步骤。以上6个步骤具有先后顺序,因此选择“活动的资源估算”、“活动历时估算”、制订进度计划,所以选B。(71) A.活动历时估算 制订进度计划 活动的资源估算 B.活动的资源估算 活动历史估算 制订进度计划 C.制订进度计划 活动的资源估算 活动历时估算 D.活动的资源估算 制订进度计划 活动历时估算

  • 第18题:

    Many useful tools and techniques are used in developing schedule. ( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource.

    A.PERT
    B.Resource levelling
    C.Schedule compression
    D.Critical chain methoD.

    答案:D
    解析:
    PERT方法能协调整个计划的各道工序,通过描绘出项目包含的各种活动的先后次序,标明每项活动的时间或相关的成本,合理安排人力、物力、时间、资金,加速计划的完成。A. PERT B. 资源平衡C. 进度压缩 D. 关键链法

  • 第19题:

    Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order.

    A.activity duration estimating, schedule developing, activity resource estimating
    B.activity resource estimating, activity duration estimating, schedule development
    C.schedule developing, activity resource estimating, activity duration estimating
    D.activity resource estimating, schedule developing, activity duration estimating

    答案:B
    解析:
    项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来,合理分配工作量,利用进度安排的有效分析方法来严格监视项目的进展情况,以使得项目的进度不致被拖延。项目时间管理过程包括:活动定义、活动排序、活动的资源估算、活动历时估算、制订进度计划及进度控制6个步骤。以上6个步骤具有先后顺序,因此选择“活动的资源估算”、“活动历时估算”、制订进度计划,所以选B。A. 活动历时估算 制订进度计划 活动的资源估算B. 活动的资源估算 活动历史估算 制订进度计划C. 制订进度计划 活动的资源估算 活动历时估算D. 活动的资源估算 制订进度计划 活动历时估算

  • 第20题:

    On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

    • A、time estimating
    • B、cost estimating
    • C、project planning
    • D、schedule development

    正确答案:C

  • 第21题:

    The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.

    • A、estimating
    • B、defining
    • C、planning
    • D、sequencing

    正确答案:A

  • 第22题:

    单选题
    On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
    A

    time estimating

    B

    cost estimating

    C

    project planning

    D

    schedule development


    正确答案: A
    解析: 暂无解析

  • 第23题:

    单选题
    The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.
    A

    estimating

    B

    defining

    C

    planning

    D

    sequencing


    正确答案: A
    解析: 该题的关键词为"schedule activity durations",其语句结构为"The process(主语)of()schedule activity durations uses(谓语)information",语句的含义为"(?)进度活动持续时间的过程使用信息",结合选项,此处应该选择动词,所以观察对进度活动持续时间采取什么行为会应用到各种信息(information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities),只有在估算进度活动持续时间时才会使用这些信息得到活动的工期,其他选项容易排除,因而选项A符合题意要求。

  • 第24题:

    单选题
    The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.
    A

    estimating

    B

    defining

    C

    planning

    D

    sequencing


    正确答案: A
    解析: 暂无解析