单选题In the project management context,() includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing ex

题目
单选题
In the project management context,() includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.
A

Integration

B

Scope

C

Configuration

D

Requirement


相似考题
更多“单选题In the project management context,() includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing ex”相关问题
  • 第1题:

    ● The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75)

    (75)

    A. Project Scope Statement

    B. Project Management Plan

    C. Forecasts

    D. Project Charter


    正确答案:B

    试题(75)分析
      项目管理的过程开发计划,包括采取必要的定义,准备,集成和协调所有组成计划到    (75) 。
      A.项目范围说明书                    B.项目管理计划
      C.项目预测                          D.项目章程
    参考答案
      (75)B

  • 第2题:

    ()is the process of determining. documenting and managing stakeholder needs and requirements to meet project objectives

    A.Collecting requirements

    B.Defining requirements

    C.Creating WBS

    D.Requirements analysis


    正确答案:A

  • 第3题:

    The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.

    A.project charter

    B.project scope goal

    C.project budget

    D.project scope statement


    正确答案:C

  • 第4题:

    Project(69)Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

    A.Integration

    B.Scope

    C.Configuration

    D.Requirement


    正确答案:B
    解析:项目范围里管理包括为确保项目包含且仅只包含成功完成项目必需工作的所需过程。

  • 第5题:

    The inputs of developing project management plan do not include().

    A. project charter
    B. stakeholder management strategy
    C.project scope statement
    D.outputs from planning processes

    答案:B
    解析:
    制定项目管理计划的输入不包括(72)
    A.项目章程 B. 干系人管理策略
    C.项目范围说明书 D. 计划过程输出

  • 第6题:

    ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.

    A:Create scopE
    B:Project stakeholder management
    C:Project scope management
    D:Project cost management

    答案:C
    解析:

  • 第7题:

    The scope management plan is how the team will prepare the( )a document that includes descriptions of create the WBS,verify completion of the project deliverables,and control requests for changes to the project scope.

    A.project charter
    B.project scope goal
    C.project budget
    D.project scope statement

    答案:D
    解析:
    翻译:范围管理计划是团队如何准备项目范围说明文件,包括描述创建WBS,核实项目的可交付成果的完成,并为项目范围变更控制的要求。A.项目章程 B.项目范围目标C.项目预算 D.范围说明书

  • 第8题:

    ( )is the process of determining,documenting ,and managing stakeholder needs and requirements to meet project objectives.

    A.Collecting requirements
    B.Defining requirements
    C.Creating WBS
    D.Requirements analysis

    答案:A
    解析:
    翻译:收集需求是一个确定、记录、管理干系人需求以便满足项目需求的过程。A.收集需求 B.定义需求C.创建WBS D.需求分析

  • 第9题:

    The inputs of developing project management plan do not include()

    • A、project charter
    • B、stakeholder management strategy
    • C、project scope statement
    • D、outputs from planning processes

    正确答案:B

  • 第10题:

    Project()Management includes the processes required to ensure that theproj ect includes all the work required, and only the work required, to complete the project successfully.

    • A、Integration
    • B、Scope
    • C、Configuration
    • D、Requirement

    正确答案:B

  • 第11题:

    单选题
    Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
    A

    Integration

    B

    Scope

    C

    Configuration

    D

    Requirement


    正确答案: B
    解析: 暂无解析

  • 第12题:

    单选题
    Project()Management includes the processes required to ensure that theproj ect includes all the work required, and only the work required, to complete the project successfully.
    A

    Integration

    B

    Scope

    C

    Configuration

    D

    Requirement


    正确答案: B
    解析: 该题的关键词为"all the work required, only the work required",其语句结构为"Project()Management(主语)includes(谓语)the processes",含义为"项目什么管理包含过程",仅根据关键词便可判断出应该与项目范围管理紧密相关,在结合语句分析,应该选择项目范围管理,即Scope。

  • 第13题:

    The Develop Project Management Plan Process includes the actions necessary to define,prepare,integrate,and coordinate all constituent plans into a(75). A.Project Scope Statement B.Project Management Plan C.Forecasts D.Project Charter


    正确答案:B
    制定项目管理计划过程定义、准备、集成和协调所有的分计划,以形成项目管理计划 。

  • 第14题:

    The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75).

    A.Project Scope Statement

    B.Project Management Plan

    C.Forecasts

    D.Project Charter


    正确答案:B

  • 第15题:

    In the project management context,(68)includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.

    A.integration

    B.scope

    C.process

    D.charter


    正确答案:A
    解析:在项目管理语境中,“整体”包含了统一、合并、联接的特性,以及对于完成项目、成功满足顾客和其他干系人的需求及管理期望至关重要的整体行动。

  • 第16题:

    The Develop Project Management Plan Process includes the actions necessary to define, prepare,integrate, and coordinate all constituent plans into a ( )

    A. Project Scope Statement
    B.Project Management Plan
    C.Forecasts
    D.Project Charter

    答案:B
    解析:
    项目管理的过程开发计划,包括采取必要的定义,准备,集成和协调所有组成计划到(75)。

    A. 项目范围说明书 B. 项目管理计划

    C. 项目预测 D. 项目章程

  • 第17题:

    The inputs of developing project management plan do not include()

    A.project charter
    B.stakeholder management strategy
    C.project scope statement
    D.outputs from planning processes

    答案:B
    解析:
    制定项目管理计划的输入不包括:A.项目章程 B.利益相关者管理策略 C.项目范围描述 D.计划过程输出

  • 第18题:

    ( )is the process of determining,documenting ,and managing stakeholder needs and requirements to meet project objectives.

    A.Collecting requirements
    B.Defining requirements
    C.Creating WBS
    D.Requirements analysis

    答案:A
    解析:
    翻译:收集需求是一个确定、记录、管理干系人需求以便满足项目需求的过程。A.收集需求 B.定义需求C.创建WBS D.需求分析

  • 第19题:

    ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.

    A. Create scopE
    B. Project stakeholder management
    C. Project scope management
    D. Project cost management

    答案:C
    解析:

  • 第20题:

    Stakeholder management refers to managing communications to satisfy needs of, and resolve issues with, project stakeholders. The ( ) is useful responsible for stakeholder management.

    A.PMO
    B.CIO
    C.CCB
    D.PM

    答案:D
    解析:
    项目干系人管理是指为满足干系人的需要而与之沟通,并解决所发生的问题。通常,项目经理(PM)负责项目干系人管理。A.项目管理办公室 B.首席信息官 C.变更控制委员会 D.项目经理

  • 第21题:

    Stakeholder management refers to managing communications to satisfy needs of, and resolve issues with,project stakeholders. The ( ) is useful responsible for stakeholder management.

    • A、PMO
    • B、CIO
    • C、CCB
    • D、PM

    正确答案:D

  • 第22题:

    Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

    • A、Integration
    • B、Scope
    • C、Configuration
    • D、Requirement

    正确答案:D

  • 第23题:

    单选题
    In the project management context()includes characteristics of unification,consolidation, articulation, and integrative actions that are crucial to project completion,successfully meeting customer and other stakeholder requirements, and managing expectations.
    A

    integration

    B

    scope

    C

    process

    D

    charter


    正确答案: A
    解析: 该题的关键词为"unification、consolidation、articulation、integrativeactions",其语句结构为"(主语)includes(谓语)characteristics of unification,consolidation,articulation,andintegrativeactions",含义为"什么包括了统一、合并、沟通的特征以及集成活动",根据语句的含义容易识别为集成(或整体),对应的英文为Integration。

  • 第24题:

    单选题
    Stakeholder management refers to managing communications to satisfy needs of, and resolve issues with,project stakeholders. The ( ) is useful responsible for stakeholder management.
    A

    PMO

    B

    CIO

    C

    CCB

    D

    PM


    正确答案: C
    解析: 项目干系人管理是指为满足干系人的需要而与之沟通,并解决所发生的问题,通常,项目经理(PM)负责项目干系人管理。 A:项目管理办公室 B:首席信息官 C://变更控制委员会。 D://项目经理