milestone
baseline
quality
work
第1题:
● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.time estimating
B.cost estimating
C.project planning
D.schedule development
第2题:
● Estimating activity durations uses information on activity scope of (74),required resource types, estimated resource quantities, and resource calendars.
(74)
A. milestone
B. baseline
C. quality
D. work

第3题:
● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.
(71)
A.activity duration estimating, schedule developing, activity resource estimating
B . activity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.activity resource estimating, schedule developing, activity duration estimating
第4题:
Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.
A.Develop Schedule
B.Estimate Activity Resources
C.Define Activities
D.Sequence Activities
第5题:
Estimating schedule activity costs involves developing an (74) of the cost of the resources needed to complete each schedule activity.
A.accuracy
B.approximation
C.specification
D.summary
第6题:
On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and (71) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.project planning
B.time estimating
C.cost estimating
D.schedule development
第7题:
第8题:
第9题:
第10题:
Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.
第11题:
Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.
第12题:
activity duration estimating, schedule developing, activity resource estimating
activity resource estimating, activity duration estimating, schedule development
schedule developing, activity resource estimating, activity duration estimating
activity resource estimating, schedule developing, activity duration estimating
第13题:
Estimating activity durations uses information on activity scope of(74) , required resource types, estimated resource quantities, and resource calendars.
A.milestone
B.baseline
C.quality
D.work
第14题:
Estimate activity durations is the processof estimating the number of work periods to complete indivities with estimatedresources . the tools and technques is not including().
A.expert judgment
B.analogous estimating
C.requiremen tstraceability matrix
D.three-point estimating
第15题:
______is one of the techniques used for estimating activity durations.
A.Analogous Estimating
B.Precedence Diagramming Method(PDM)
C.Dependency Determination
D.Schedule network Templates
第16题:
The process of(72)schedule activity durations uses information on schedule activity scope of work,required resource types,estimated resource quantities,and resource calendars with resource availabilities.
A.estimating
B.defining
C.planning
D.sequencing
第17题:
Estimating schedule activity costs involves developing an(4)of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in mostapplication areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estmates are generally expressed in units of(5)to facilitate comparisions both within and across projects. The(6)describes important information about project requirement that is considered during cost estimating.
A.accuracy
B.approxination
C.specification
D.summary
第18题:
( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.
A.Parametric
B.Analogous
C.Three-point
D.Expert judgment
第19题:
第20题:
第21题:
第22题:
(1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity. 空白(3)处填()
第23题:
time estimating
cost estimating
project planning
schedule development
第24题:
activity
work
currency
time