estimating
defining
planning
sequencing
第1题:
The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.
A.estimating
B.defining
C.planning
D.sequencing
第2题:
● Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is following the process- Estimate Activity Durations.
(74)
A.Develop Schedule
B.Estimate Activity Resources
C.Define Activities
D.Sequence Activities
第3题:
Estimating activity durations uses information on activity scope of(74) , required resource types, estimated resource quantities, and resource calendars.
A.milestone
B.baseline
C.quality
D.work
第4题:
● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.
(71)
A.activity duration estimating, schedule developing, activity resource estimating
B . activity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.activity resource estimating, schedule developing, activity duration estimating
第5题:
Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.
A.Develop Schedule
B.Estimate Activity Resources
C.Define Activities
D.Sequence Activities
第6题:
is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships:(67), the initiation of the successor activity, depends upon the completion of the predecessor activity.(68), the initiation of the successor activity, depends upon the initiation of the predecessor activity.
A.PDM
B.CPM
C.PERT
D.AOA
第7题:
Estimating schedule activity costs involves developing an (74) of the cost of the resources needed to complete each schedule activity.
A.accuracy
B.approximation
C.specification
D.summary
第8题:
On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and (71) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.project planning
B.time estimating
C.cost estimating
D.schedule development
第9题:
第10题:
Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.
第11题:
Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.
第12题:
activity duration estimating, schedule developing, activity resource estimating
activity resource estimating, activity duration estimating, schedule development
schedule developing, activity resource estimating, activity duration estimating
activity resource estimating, schedule developing, activity duration estimating
第13题:
● (73) is one of the techniques used for estimating activity durations.
(73)
A.Analogous Estimating
B.Precedence Diagramming Method (PDM)
C.Dependency Determination
D.Schedule network Templates
第14题:
● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.time estimating
B.cost estimating
C.project planning
D.schedule development
第15题:
● Estimating activity durations uses information on activity scope of (74),required resource types, estimated resource quantities, and resource calendars.
(74)
A. milestone
B. baseline
C. quality
D. work

第16题:
______is one of the techniques used for estimating activity durations.
A.Analogous Estimating
B.Precedence Diagramming Method(PDM)
C.Dependency Determination
D.Schedule network Templates
第17题:
The process of(72)schedule activity durations uses information on schedule activity scope of work,required resource types,estimated resource quantities,and resource calendars with resource availabilities.
A.estimating
B.defining
C.planning
D.sequencing
第18题:
Estimating schedule activity costs involves developing an(69)of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estimates are generally expressed in units of(70)to facilitate comparisons both within and across projects.The(71 )describes the business need, justification, requirements, and current boundaries for the project. It provides important information about project requirements that is considered during cost estimating.
A.accuracy
B.approximation
C.specification
D.summary
第19题:
Estimating schedule activity costs involves developing an(4)of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in mostapplication areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estmates are generally expressed in units of(5)to facilitate comparisions both within and across projects. The(6)describes important information about project requirement that is considered during cost estimating.
A.accuracy
B.approxination
C.specification
D.summary
第20题:
第21题:
第22题:
On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
第23题:
(1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity. 空白(1)处填()
第24题:
activity
work
currency
time