单选题The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.A estimatingB definingC planningD sequencing

题目
单选题
The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.
A

estimating

B

defining

C

planning

D

sequencing


相似考题
参考答案和解析
正确答案: A
解析: 该题的关键词为"schedule activity durations",其语句结构为"The process(主语)of()schedule activity durations uses(谓语)information",语句的含义为"(?)进度活动持续时间的过程使用信息",结合选项,此处应该选择动词,所以观察对进度活动持续时间采取什么行为会应用到各种信息(information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities),只有在估算进度活动持续时间时才会使用这些信息得到活动的工期,其他选项容易排除,因而选项A符合题意要求。
更多“The process of()schedule activity durations uses information”相关问题
  • 第1题:

    The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

    A.estimating

    B.defining

    C.planning

    D.sequencing


    参考答案:D

  • 第2题:

    ● Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is following the process- Estimate Activity Durations.

    (74)

    A.Develop Schedule

    B.Estimate Activity Resources

    C.Define Activities

    D.Sequence Activities


    正确答案:A
    试题(74)分析
        项目进度管理包含多个项目实效管理过程,这些过程相互影响,其中紧接活动历时估算的过程是答案A计划编制。
    参考答案
        (74)A

  • 第3题:

    Estimating activity durations uses information on activity scope of(74) , required resource types, estimated resource quantities, and resource calendars.

    A.milestone

    B.baseline

    C.quality

    D.work


    正确答案:D
    解析:估算活动历时使用的信息包括活动的工作范围、所需资源类型、估算的资源数量,以及资源日历。

  • 第4题:

    ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

    (71)

    A.activity duration estimating, schedule developing, activity resource estimating

    B . activity resource estimating, activity duration estimating, schedule development

    C.schedule developing, activity resource estimating, activity duration estimating

    D.activity resource estimating, schedule developing, activity duration estimating


    正确答案:B
    试题(71)分析
     项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来,合理分配工作量,利用进度安排的有效分析方法来严格监视项目的进展情况,以使得项目的进度不致被拖延。
     项目时间管理过程包括:活动定义、活动排序、活动的资源估算、活动历史估算、制定进度计划及进度控制六个步骤。
     以上六个步骤具有先后顺序,因此选择“活动的资源估算”activity resource estimating、“活动历史估算”activity duration estimating、制定进度计划schedule                 development,所以选B。
    参考答案
    (71)B

  • 第5题:

    Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.

    A.Develop Schedule

    B.Estimate Activity Resources

    C.Define Activities

    D.Sequence Activities


    正确答案:A
    解析:项目进度管理包含多个项目实效管理过程,这些过程相互影响,其中紧接活动历时估算的过程是答案A计划编制。

  • 第6题:

    is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships:(67), the initiation of the successor activity, depends upon the completion of the predecessor activity.(68), the initiation of the successor activity, depends upon the initiation of the predecessor activity.

    A.PDM

    B.CPM

    C.PERT

    D.AOA


    正确答案:A
    解析:PDM是以一种方块或矩形(或称为节点)来表示活动,并将它们用表示依存关系的箭线连接起来,以构建项目进度网络图的方法。这种方法包括了下列依存或前导关系:完成—开始(F-S),后续活动的开始依赖于前置活动的完成。开始-开始(S-S),后续活动的开始依赖于前置活动的启动。

  • 第7题:

    Estimating schedule activity costs involves developing an (74) of the cost of the resources needed to complete each schedule activity.

    A.accuracy

    B.approximation

    C.specification

    D.summary


    正确答案:B

  • 第8题:

    On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and (71) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

    A.project planning

    B.time estimating

    C.cost estimating

    D.schedule development


    正确答案:D

  • 第9题:

    Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order.

    A.activity duration estimating, schedule developing, activity resource estimating
    B.activity resource estimating, activity duration estimating, schedule development
    C.schedule developing, activity resource estimating, activity duration estimating
    D.activity resource estimating, schedule developing, activity duration estimating

    答案:B
    解析:
    项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来,合理分配工作量,利用进度安排的有效分析方法来严格监视项目的进展情况,以使得项目的进度不致被拖延。项目时间管理过程包括:活动定义、活动排序、活动的资源估算、活动历时估算、制订进度计划及进度控制6个步骤。以上6个步骤具有先后顺序,因此选择“活动的资源估算”、“活动历时估算”、制订进度计划,所以选B。(71) A.活动历时估算 制订进度计划 活动的资源估算 B.活动的资源估算 活动历史估算 制订进度计划 C.制订进度计划 活动的资源估算 活动历时估算 D.活动的资源估算 制订进度计划 活动历时估算

  • 第10题:

    Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.

    • A、milestone
    • B、baseline
    • C、quality
    • D、work

    正确答案:D

  • 第11题:

    Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

    • A、activity duration estimating, schedule developing, activity resource estimating
    • B、activity resource estimating, activity duration estimating, schedule development
    • C、schedule developing, activity resource estimating, activity duration estimating
    • D、activity resource estimating, schedule developing, activity duration estimating

    正确答案:B

  • 第12题:

    单选题
    Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.
    A

    activity duration estimating, schedule developing, activity resource estimating

    B

    activity resource estimating, activity duration estimating, schedule development

    C

    schedule developing, activity resource estimating, activity duration estimating

    D

    activity resource estimating, schedule developing, activity duration estimating


    正确答案: A
    解析: 暂无解析

  • 第13题:

    ● (73) is one of the techniques used for estimating activity durations.

    (73)

    A.Analogous Estimating

    B.Precedence Diagramming Method (PDM)

    C.Dependency Determination

    D.Schedule network Templates


    正确答案:A
    试题(73)分析
        下列用于活动历时估算的技术是答案A类比估算法。
    参考答案
        (73)A

  • 第14题:

    ● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

    A.time estimating

    B.cost estimating

    C.project planning

    D.schedule development


    正确答案:D

  • 第15题:

    ● Estimating activity durations uses information on activity scope of (74),required resource types, estimated resource quantities, and resource calendars.

    (74)

    A. milestone

    B. baseline

    C. quality

    D. work


    正确答案:D


     

     

  • 第16题:

    ______is one of the techniques used for estimating activity durations.

    A.Analogous Estimating

    B.Precedence Diagramming Method(PDM)

    C.Dependency Determination

    D.Schedule network Templates


    正确答案:A
    解析:下列用于活动历时估算的技术是答案A类比估算法。

  • 第17题:

    The process of(72)schedule activity durations uses information on schedule activity scope of work,required resource types,estimated resource quantities,and resource calendars with resource availabilities.

    A.estimating

    B.defining

    C.planning

    D.sequencing


    正确答案:A
    解析:估算活动历时的过程会用到活动工作范围、所需资源类型、估计的资源数量以及建立在资源可用性上的资源日历等信息。

  • 第18题:

    Estimating schedule activity costs involves developing an(69)of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estimates are generally expressed in units of(70)to facilitate comparisons both within and across projects.The(71 )describes the business need, justification, requirements, and current boundaries for the project. It provides important information about project requirements that is considered during cost estimating.

    A.accuracy

    B.approximation

    C.specification

    D.summary


    正确答案:B
    解析:估算计划活动的成本涉及估算完成每项计划活动所需资源的近似成本。成本估算包括识别和考虑各种成本计算方案。例如,在大多数的应用领域,普遍在设计阶段多做些额外工作以降低执行阶段和产品运行时的潜在成本。成本估算过程考虑预期的成本节省是否能够弥补额外设计工作的成本。成本估算一般以货币单位表示,以利于在项目内和项目间进行比较。项目范围说明书描述了项目的商业要求、理由、需求和当前边界。它提供了关于在成本估算时必须考虑的项目需求的重要信息。

  • 第19题:

    Estimating schedule activity costs involves developing an(4)of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in mostapplication areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estmates are generally expressed in units of(5)to facilitate comparisions both within and across projects. The(6)describes important information about project requirement that is considered during cost estimating.

    A.accuracy

    B.approxination

    C.specification

    D.summary


    正确答案:B

  • 第20题:

    PDM is a method of constructing a project schedule network diagram that uses boxesor rectangles, referred to as nodes, to represent activities and connects them with arrows thatshow the dependencies.This method includes following types of dependencies or precedence relationships:F-S, the initiation of the successor activity, depends upon the completion of thepredecessor activity.() , the initiation of the successor activity, depends upon the initiation of thepredecessor activity.

    A.F-S
    B.F-F
    C.S-F
    D.S-S

    答案:D
    解析:
    PDM是以一种方块或矩形(或称为节点)来表示活动,并将它们用表示依存关系的剪线链接起来,以构建项目进度网络图的方法。这种方法包括了下列依存或前导关系:完成---开始(F-S),后续活动的开始依赖于前置活动的完成。开始---开始(S-S),后续活动的开始依赖于前置活动的启动。

  • 第21题:

    Estimating activity
    durations uses information on activity scope of ( ) , required resource types, estimated
    resource quantities, and resource calendars.

    A.milestone
    B. baseline
    C.quality
    D. work

    答案:D
    解析:

  • 第22题:

    On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

    • A、time estimating
    • B、cost estimating
    • C、project planning
    • D、schedule development

    正确答案:C

  • 第23题:

    (1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity. 空白(1)处填()

    • A、PDM
    • B、CPM
    • C、PERT
    • D、AOA

    正确答案:A

  • 第24题:

    单选题
    Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating. 空白(2)处填()
    A

    activity

    B

    work

    C

    currency

    D

    time


    正确答案: C
    解析: 阅读试题可知,整段文章讨论的内容集中于"Costestimating",分析问题(1)的语句结构为"estimatingscheduleactivitycosts(主语)involves(谓语)developingan(1)ofthecostoftheresources"。接下来使用排除法,如果对于"estimatingscheduleactivitycosts"的特定内容不了解,似乎哪个选项也可以,注意"thelresourcesneededtocompleteeachscheduleactivity",既然每项活动所需的资源都需考虑,那就只能选择答案summary,summary在此处解释为"汇总"。分析问题(2)对应的语句,"costestimates(主语)aregenerallyexpressed(谓语)inunitsof(2)tofacilitatecomparisonsbothwithinandacrossprojects",结合选项,此句的含义为"成本估算(结果)通常以作为单位",故而只能选择C,Currency的含义为"货币"、"通货",考生即使不熟悉这个单词,也能轻易排除其他三个选项。问题(3)对应的语句,"the(3)(主语)describes(谓语)importantinformationaboutprojectrequirementthatisconsideredduringcostestimating",所以该句的含义即"描述了成本估算时应考虑的项目需求"。显而易见,选项C和D容易排除,但选择"Projectscopestatement"还是"Scopeofwork"?Scopeofwork(工作说明书)是合同中的附件,用于说明合同的工作范围(此时项目尚未建立),因而选择选项A。