Companycom has several AS/400 servers in their IT infrastructure running V5R2 that they wish to consolidate. The customer wants to simplify their environment and install i5/OS on a p5 590 with 16 1.65GHz processors and 20 i5/OS partitions. The customer plans to use the Advanced Power Virtualization to share their storage, processors, and memory. What considerations and limitations should be reviewed with the customer before the purchase?()
第1题:
Companycom has a p690 and currently has eight LPARs. They have purchased a p5 590 and wish to migrate their eight LPARs to the new server. The LPARs are running either AIX 5.2 or AIX 5.3 with the current maintenance. What is the LEAST disruptive method for this activity?()
第2题:
A customer has a 32-core Power 770 with 4 AIX partitions and 2 IBM i partitions. They want to improve network availability and allow for concurrent maintenance. What will support the customer requirement at least cost?()
第3题:
Companycom has just purchased a p5 570 with AIX 5.3. The customer would like to add a training LPAR to the system, but no processors are available. All of the partitions are using dedicated resources. The test LPAR is using one processor and has a 90% CPU idle rate. What can be done to setup this training LPAR quickly without disabling their current environment?()
第4题:
A customer wants to expand their current storage environment, but has floor space for only two machine frames or two racks. Their environment consists of IBM SAN Volume Controllers and IBM DS4000 systems. The DS4000 systems are at end of lease. The customer wants the maximum number of disks possible in two frames. Which of the following solutions is best for this customer?()
第5题:
Companycom is considering a large partitioned p5 590 to consolidate several smaller systems in their data center. Due to the complexity of the consolidation, the customer is asking the technical support specialist to give them a report which shows pre order PCI adapter placement and validates them against IBM's recommendations. The concern is that the factory will not install the adapters in the appropriate slots as the customer pre-selected. What IBM tool is available to provide this?()
第6题:
Companycom wants to manage multiple partitions for a p5 590 server using Partition Load Manager (PLM). Some of the partitions are dedicated processors and some of them are shared processors. What information about PLM limitations should be expressed to the customer?()
第7题:
A customer is adding a new p5 machine to their environment. The machine will host several DB2 partitions running AIX 5.2. They currently have two SAN directors and an IBM ESS. The SAN design allows for concurrent maintenance. What is required on each partition to attach to the SAN?()
第8题:
Companycom wants to buy a new p5 570 running AIX 5.3. The applications require 4 processors and 8GB of memory. There is a requirement to have a Virtual IO Server. What is the smallest p5 570 that should be sold to this customer?()
第9题:
A minimum of two HBAs; the customer will need to download SDD
A minimum of four HBAs; the customer will need to download SDD
A minimum of two HBAs; the customer will need to configure MPIO
A minimum of four HBAs; the customer will need to configure MPIO
第10题:
APV, AIX5.2ML4
AIX5.3 or i5/OS
APV, i5/OS, AIX5.3
APV, AIX5.3 or SuSE9
第11题:
PowerVM Lx86
PowerVM Express Edition
PowerVM Standard Edition
PowerVM Enterprise Edition
第12题:
4 processors 8GB of memory
5 processors 8GB of memory
4 processors 10GB of memory
5 processors 10GB of memory
第13题:
A Customer has a functional server deployment solution that uses a combination of disk imaging and application pushing technology. They need to get a working Windows 2003 image for their new servers as soon as possible. What method can achieve this?()
第14题:
A current Sun Solaris customer has just purchased their first p5 590. During the Solution Assurance, the backup requirements were discussed. Which of the following should be recommended to the customer with regards to restoring rootvg?()
第15题:
An existing IBM customer has some iSeries servers in their environment. The customer is adding an x366 server with an RSA-II installed for their Microsoft Client/Server applications. The customer wants to consolidate the storage and centralize the backup of the iSeries and xSeries platforms. Which of the following will accomplish this?()
第16题:
A customer has 15 IBM x365 servers in a rack environment and is using IBM Director for systems management. They require the ability to restart any server independent of the operating system. Which of the following is the most cost-effective solution?()
第17题:
Companycom wants the application server LPAR to communicate with the database LPAR on a p5 590 without using network adapters. What does the customer need to install?()
第18题:
Companycom tells the technical sales specialist that recent announcements state that virtual lan in the datacenter is the best option. The customer wants to use interpartition communication to save on adapters and increase performance. The systems are going to have shared and dedicated processor partitions. Some of the partitions will be running AIX 5.2 and some will be running AIX 5.3. The second p5 590 will be running a mixture of AIX 5.3 and Linux partitions with 2.6 kernel. What limitations of vlan/interpartition communication should be discussed with this customer?()
第19题:
A Customer has a proprietary server deployment solution that uses a combination of disk imaging and application pushing technology. They need to get a working Windows 2003 image for their new servers as soon as possible for deployment with their provisioning system. Which of the following methods can achieve this?()
第20题:
During the Solution Assurance for a p5 590, Companycom states there is a plan to install OEM Emulex cards in the p5 590. The customer assumes there will be no problem with the plan since IBM resells the Emulex cards. What is the correct response for the customer?()
第21题:
Install Windows 2003 using the F6 supply Mass Storage Controller option
Replace Customer’s deployment solution with Tivoli Provisioning Manager for OS Deployment Director Edition
Deploy Customer’s existing image and use UXSPi to update IBM specific drivers
Use ServerGuide to install Windows 2003
第22题:
PowerVM supports shared servers compared to VSE
PowerVM supports shared processors and memory compared to VSE
PowerVM supports shared processors, memory and I/O compared to VSE
PowerVM supports DLPAR without a reboot and supports dedicated I/O compared to VSE
第23题:
The IBM CE will install the card
The card will not be supported by IBM
The AIX device driver should work fine
The customer is correct, there should be no problem