130 The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.A. Conceptual, charter

题目

130 The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.

A. Conceptual, charter/baseline.

B. Conceptual, master schedule.

C. Development, charter/baseline.

D. Development, master schedule.

E. Development, masterplan


相似考题
更多“130 The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.A. Conceptual, charter”相关问题
  • 第1题:

    The process of choosing/documenting the best approach to achieve the project objectives is part of:

    A.The scope baseline.

    B.Scope authorization

    C.Scope definition

    D.Scope planning.

    E.All of the above.


    正确答案:D
    D

  • 第2题:

    Of the following, who has the ultimate responsibility for meeting project quality objectives?

    A . Project Engineer

    B . Project Manager

    C . Functional Manager

    D . Quality Assurance Manager

    E . Project Owner


    正确答案:B

  • 第3题:

    78 The process of choosing/documenting the best approach to achieve the project objectives is part of: A. The scope baseline.

    B. Scope authorization

    C. Scope definition

    D. Scope planning.

    E. All of the above.


    正确答案:D

  • 第4题:

    85 The purpose of project Risk Management is to:

    A. Identify those factors that will adversely impact project objectives.

    B. Assess the impact of adverse project factors.

    C. Assess the probability of adverse project factors.

    D. A and C

    E. All of the above


    正确答案:E

  • 第5题:

    120 The Work Breakdown Structure (WBS) is the basis for communicating:

    A. Project scope, cost control, schedule, quality

    B. Project objectives, dependencies, plan, cost control

    C. Project scope, schedule, staffing, cost control

    D. Project scope, quality, schedule, dependencies

    E. Project budget, schedule, risk factors, work assignments


    正确答案:A

  • 第6题:

    193 Creation of project objectives:

    A. allows for data collection and analysis and progress reporting against which standards of performance can be measured.

    B. is accomplished by selection of measurable variables against which performance can be judged. C. is required before funding of the project by the project sponsor.

    D. all of the above.

    E. A and B only


    正确答案:E

  • 第7题:

    109 Problems can occur in properly defining a project because:

    A. Project goals may not be agreeable to all parties

    B. The plan was "too loose," thus allowing priorities to change

    C. Low turnover of project personnel

    D. Too much communication between the client and project personnel

    E. The project objectives were quantified


    正确答案:A

  • 第8题:

    160 The process of choosing/documenting the best approach to achieve the project objectives is part of:

    A. The scope baseline.

    B. Scope authorization

    C. Scope definition

    D. Scope planning.

    E. All of the above


    正确答案:D

  • 第9题:

    ● In preparing a good project definition, experienced project managers will:

    A Concentrate mainly on the end product rather than costs or benefits. These come later.

    B Realize that only the "tip of the iceberg" may be showing. As a project manager, you must get beneath it.

    C Understand that a project definition/plan is a dynamic rather than static tool, and thus subject to change.

    D Try to convert objectives into quantifiable terms.

    E All of the above


    正确答案:E

  • 第10题:

    ● The project charter:

    A Expresses upper management commitment to the project.

    B Provides that authority by which the project will be run.

    C Establishes that organizational structure with the project.

    D Specifies overall objectives and timeframe. of the project.

    E All of the above.


    正确答案:E

  • 第11题:

    The( )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.

    A、project scope statement

    B、work package

    C、WBS

    D、project scope plan


    参考答案:C

  • 第12题:

    Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.

    • A、Project
    • B、project management team
    • C、performingorganization
    • D、customer

    正确答案:C

  • 第13题:

    The quality objectives are approved in the conceptual stage of the project by the:

    A . Project Engineer

    B . Project Manager

    C . Functional Manager

    D . Quality Assurance Manager

    E . Project Owner


    正确答案:E

  • 第14题:

    The purpose of project Risk Management is to:

    A Identify those factors that will adversely impact project objectives.

    B Assess the impact of adverse project factors.

    C Assess the probability of adverse project factors.

    D A and C

    E All of the above.


    正确答案:E

  • 第15题:

    35 The project charter:

    A. Expresses upper management commitment to the project.

    B. Provides that authority by which the project will be run.

    C. Establishes that organizational structure with the project.

    D. Specifies overall objectives and timeframe. of the project.

    E. All of the above


    正确答案:E

  • 第16题:

    112 Of the following, who has the ultimate responsibility for meeting project quality objectives?

    A. Project Engineer

    B. Project Manager

    C. Functional Manager

    D. Quality Assurance Manager

    E. Project Owner


    正确答案:B

  • 第17题:

    121 The quality objectives are approved in the conceptual stage of the project by the:

    A. Project Engineer

    B. Project Manager

    C. Functional Manager

    D. Quality Assurance Manager

    E. Project Owner


    正确答案:E

  • 第18题:

    97 In preparing a good project definition, experienced project managers will:

    A. Concentrate mainly on the end product rather than costs or benefits. These come later.

    B. Realize that only the "tip of the iceberg" may be showing. As a project manager, you must get beneath it.

    C. Understand that a project definition/plan is a dynamic rather than static tool, and thus subject to change.

    D. Try to convert objectives into quantifiable terms.

    E. All of the above


    正确答案:E

  • 第19题:

    12 The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.

    A. Conceptual, charter/baseline.

    B. Conceptual, master schedule.

    C. Development, charter/baseline.

    D. Development, master schedule.

    E. Development, masterplan


    正确答案:A

  • 第20题:

    ● Problems can occur in properly defining a project because:

    A Project goals may not be agreeable to all parties

    B The plan was "too loose," thus allowing priorities to change

    C Low turnover of project personnel

    D Too much communication between the client and project personnel

    E The project objectives were quantified


    正确答案:A

  • 第21题:

    ● The Work Breakdown Structure (WBS) is the basis for communicating:

    A Project scope, cost control, schedule, quality

    B Project objectives, dependencies, plan, cost control

    C Project scope, schedule, staffing, cost control

    D Project scope, quality, schedule, dependencies

    E Project budget, schedule, risk factors, work assignments.


    正确答案:A

  • 第22题:

    ● The process of choosing/documenting the best approach to achieve the project objectives is part of:

    A The scope baseline.

    B Scope authorization

    C Scope definition

    D Scope planning.

    E All of the above.


    正确答案:D

  • 第23题:

    The()is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.

    A.Project scope statement
    B.Work package
    C.WBS
    D.Project scope plan

    答案:C
    解析:
    ()是项目团队为完成项目目标和创建所需可交付成果而执行的整个工作范围的分层分解。
    A.项目范围说明书B.工作包C.WBS?D.项目范围计划