A negative cost variance and positive schedule variance means:
A The project is under budget and ahead of schedule
B The project is over budget and behind schedule
C The project is over budget and ahead of schedule
D The project will be overrun but ahead of schedule at completion
第1题:
You have summarized the project and note that , hours have been scheduled, , hours have been earned and , hours paid. The correct conclusion is:
A.The project is operating at a favorable cost efficiency ratio.
B.the project is spending more than planned
C.the project is behind schedule
D.the project is ahead of schedule
E.B and C
第2题:
During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:
A . The project will be completed late.
B . The critical path has been lengthened.
C . the costs are being overrun.
D . Overtime will be required to maintain the original critical path.
E . None of the above.
第3题:
163 During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:
A. The project will be completed late.
B. The critical path has been lengthened.
C. the costs are being overrun.
D. Overtime will be required to maintain the original critical path.
E. None of the above.
第4题:
39 You have summarized the project and note that 28,000 hours have been scheduled, 25,000 hours have been earned and 26,000 hours paid. The correct conclusion is:
A. The project is operating at a favorable cost efficiency ratio.
B. the project is spending more than planned
C. the project is behind schedule
D. the project is ahead of schedule
E. B and C
第5题:
72 Project trade-offs vary between
A. risk, cost and schedule.
B. direct cost, indirect cost, and resource availability
C. quality, schedule and time
D. cost, quality and schedule
E. contract terms, scope and budget
第6题:
● The most common non-behavioral reason for projects being completed behind schedule and over budget is:
A Selecting the wrong person as the project manager
B Selecting the wrong person as the sponsor
C Accepting a high-risk project
D Ill-defined requirements
E All of the above
第7题:
The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned
第8题:
● The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.
(74)A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
第9题:
In project management,a ( ) is a list of a project’s milestones,activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource allocation,budget and duration, linked by dependencies and scheduled events.
A.schedule
B.WBS
C.SOW
D.charter
第10题:
第11题:
第12题:
You are working on the cost budget for one project. Which of the following is true()
第13题:
When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.
A . Reduce features and/or functionality
B . Increase risk.
C . Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)
D . All of the above.
E . A and B only
第14题:
11 When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.
A. Reduce features and/or functionality
B Increase risk.
C. Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)
D. All of the above.
E. A and B only
第15题:
38 The most common non-behavioral reason for projects being completed behind schedule and over budget is:
A. Selecting the wrong person as the project manager
B. Selecting the wrong person as the sponsor
C. Accepting a high-risk project
D. Ill-defined requirements
E. All of the above
第16题:
69 The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.
A. budget, schedule
B. quality requirements, schedule
C. size, type of industry
D. nature, size
E. project manager, sponsor
第17题:
96 A negative cost variance and positive schedule variance means:
A. The project is under budget and ahead of schedule
B. The project is over budget and behind schedule
C. The project is over budget and ahead of schedule
D. The project will be overrun but ahead of schedule at completion
第18题:
● The Work Breakdown Structure (WBS) is the basis for communicating:
A Project scope, cost control, schedule, quality
B Project objectives, dependencies, plan, cost control
C Project scope, schedule, staffing, cost control
D Project scope, quality, schedule, dependencies
E Project budget, schedule, risk factors, work assignments.
第19题:
● You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as (74) .
(74)
A.Ahead of schedule
B.Behind schedule
C.On schedule
D.Having not enough information provided
第20题:
The earned value technique is a commonlyused method of performance measurement. It integrates project scope, cost, andschedule measures to help the project management team assess projectperformance.If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, itmeans that (74).
A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
第21题:
In project management , a (1) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (2) ,budget and duration, linked by dependencies and scheduled events.
A.schedule
B.activity
C.plan
D.contractor@@@SXB@@@A.finding
B.balance
C.allocation
D.distribution
第22题:
第23题:
In project management , a (73) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (74) ,budget and duration, linked by dependencies and scheduled events.