vmstat and iostat data from the older machines
The number of CPUs that were installed in the original machines
Data from Workload Estimator (WLE) and IBM Performance Management (PM)
Performance data that is collected from the new system after it has been put into production
第1题:
A customer has ten RS/6000 Model M80, two pSeries 690 Model 681, five POWER5 510 and two POWER6 560 machines installed and running commercial applications. They want to do a server consolidation study in order to replace the existing systems with POWER7 systems. What performance metric is recommended when evaluating the replacement system?()
第2题:
Companycom is currently using a p690 and has just ordered a p5 590. They prefer to run in full system partition mode, since their application will utilize all the resources in the machine, and they don't want the overhead of an LPAR. What is the best response to the customer about the POWER5 capabilities?()
第3题:
A customer plans to consolidate several systems onto POWER7. Their immediate requirement is to have a single Power 770, and they will buy a second Power 770 at a later stage. They want to keep their existing three POWER5 570s and three POWER6 520s which are all managed by an HMC (7310-CR3). Which of these statements is true and would minimize the cost?()
第4题:
A customer has a new Power 720 with PowerVM Standard Edition. They plan to migrate their single-partition POWER5 550 to the new Power 720. How can the customer migrate from the POWER5 550 to the Power 720 with minimal effort and down time?()
第5题:
The customer has an older storage array and is looking to migrate data that currently exists onover 100 73 GB FC drives to a new IBM System Storage DS5020. The customer states that theyhave only 3 TB of data and wants to consolidate on to fewer higher capacity drives. There are sixapplication servers running multiple applications and operating systems utilizing the storagesystem. What would be the next step to accurately identify the new storage configuration?()
第6题:
A new p5 customer has just installed a partitioned p5-550 alongside some older POWER4 servers. The pSeries technical specialist has received a call to say that the existing HMC (7315) cannot connect to the new server. How can the specialist help the customer?()
第7题:
e-Config
System Planning Tool (SPT)
IBM Workload Estimator (WLE)
IBM Performance Monitor (PM)
第8题:
vmstat and iostat data from the older machines
The number of CPUs that were installed in the original machines
Data from Workload Estimator (WLE) and IBM Performance Management (PM)
Performance data that is collected from the new system after it has been put into production
第9题:
Explain to the customer that they need an additional HMC for the POWER5 system.
Obtain a PO from the customer to purchase additional serial connections to the HMC.
Obtain a PO from the customer to purchase additional Ethernet connections to the HMC.
Explain to the customer that they need a firmware update on the HMC to support both POWER4 and POWER5.
第10题:
vmstat and iostat data from the older machines
The number of CPUs that were installed in the original machines
Data from Workload Estimator (WLE) and IBM Performance Management (PM)
Performance data that is collected from the new system after it has been put into production
第11题:
Perform Live Partition Mobility between the two systems.
Move the boot disks from the old system to the new system.
Use Tivoli Storage Manager to back up the POWER5 550 and restore on the Power 720.
Upgrade AIX to the latest level on the POWER5 550 and clone using the mksysb command.
第12题:
initiate a Disk Magic study
initiate a Capacity Magic study
runiometer on the current environment
utilize the IBM Disk capacity planner toolkit
第13题:
A customer has a POWER6 520 system with 6 partitions. They plan to upgrade their system and need to determine the current hardware configuration of the partitions before making any upgrade decisions. What is needed to read the exported system plan and design the new system?()
第14题:
A customer has 5 older POWER5 systems and they want to consolidate them onto a POWER6 system. What information is important to analyze when deciding how to design the new machine using the System Planning Tool?()
第15题:
A customer has a key application running in a logical partition on a POWER5 system. The customer wants the ability to run the application with minimal down time using Live Partition Mobility. Which of the following is the minimum PowerVM edition and hardware configuration that will support the customer requirement?()
第16题:
A customer plans to order several new pSeries systems and is concerned that the additional heat load may overwhelm the current air-handling system. How might the pSeries technical specialist aid the customer in addressing their concern?()
第17题:
A customer’s data center has all POWER4+ systems, and they plan to add three new p5-570 systems. They will be purchasing a new 7310-CR2 HMC to support the POWER5 systems. What is a key requirement that they need to plan for with the new HMC?()
第18题:
LPAR Validation Tool (LVT)
Personal Systems Configurator (PSC)
IBM Configuration for eBusiness (eConfig)
Advanced System Management Interface (ASMI)
第19题:
All the machines can be connected to the existing HMC, as long as it is updated to code level 7.7.1 or later
The Power 770 requires an HMC (7042-CR5 or later), so they must buy one. All of the systems can be managed by this new HMC
They should buy a new HMC for the Power 770 system, and leave the POWER5 and POWER6 based systems connected to the existing one
The Power 770 requires an HMC, so they should connect the Power 770 to the HMC and convert the POWER5 and POWER6 based servers to IVM
第20题:
IBM CPW
IBM rPerf
SPECint_rate2006
IDEAS International RPE2
第21题:
Direct the customer to the Installation Guide for each system to identify the power requirements.
Direct the customer to engage their site personnel to ensure the proper power connectors are provided to support the systems.
Direct the customer to the Site and Hardware Planning Information and review the system requirements for each new pSeries system.
Direct the customer to the Site and Hardware Planning Information to confirm that enough space is available in the rack to allow for proper airflow.
第22题:
PowerVM Standard Edition on POWER6 hardware
PowerVM Standard Edition with POWER5 hardware
PowerVM Enterprise Edition with POWER6 hardware
PowerVM Enterprise Edition with POWER5 hardware
第23题:
IBM eConfig
IBM Performance Monitor
IBM Workload Estimator (WLE)
IBM System Planning Tool (SPT)
第24题:
A desk, as it not rack mountable
Ethernet connections to the POWER5 systems
Serial connections to the POWER5 systems
USB connections for the keyboard and mouse