单选题Companycom wants to reduce the number of copper, Ethernet adapters on their 4 way p5 570 running AIX 5.3 used in each of the four LPARs. Companycom has one database LPAR, two application LPARs, and one web LPAR. Only the Web LPAR needs to communicate w

题目
单选题
Companycom wants to reduce the number of copper, Ethernet adapters on their 4 way p5 570 running AIX 5.3 used in each of the four LPARs. Companycom has one database LPAR, two application LPARs, and one web LPAR. Only the Web LPAR needs to communicate with the outside world. What is the minimum number of Ethernet adapters that should be provided to ensure redundancy and no single point of failure?()
A

One single port Ethernet adapter

B

Four dual port Ethernet adapters

C

Two single port Ethernet adapters

D

Eight single port Ethernet adapters


相似考题
更多“单选题Companycom wants to reduce the number of copper, Ethernet adapters on their 4 way p5 570 running AIX 5.3 used in each of the four LPARs. Companycom has one database LPAR, two application LPARs, and one web LPAR. Only the Web LPAR needs to communicate w”相关问题
  • 第1题:

    Companycom is about to purchase a POWER5 Enterprise server which requires two Ethernet ports and two disks for each of the four LPARs. It has been configured and validated using the IBM eConfig tool. Which of the following is very important to verify in addition to the eConfig validation?()

    • A、Total number of SCSI adapters
    • B、Total number of Ethernet adapters
    • C、Total number of Ethernet adapters and number of SCSI paths per LPAR
    • D、Total number of SCSI paths available and total number of SCSI adapters

    正确答案:C

  • 第2题:

    Companycom is installing a p5 595 with AIX 5.3. The DLPAR option for the resources cannot be selected on the HMC menus. However, the daemons are running on both the HMC and LPARs. Which of the following is a prerequisite for DLPAR functionality?()

    • A、The resources must be unallocated in an LPAR
    • B、The microcode on the pSeries must be current
    • C、All network adapters on the LPAR must be defined
    • D、Network connectivity and name resolution capability between HMC and LPARs

    正确答案:D

  • 第3题:

    A p5 570 customer is currently running AIX 5.3. The customer now wants to add Virtual Ethernet to two of the LPARs. This will enable the application tier can communicate to the database tier without using an external Ethernet card. What is the best way to accomplish this task?()

    • A、Create a VIO server
    • B、Modify the LPAR profiles to add a Virtual Ethernet adapter
    • C、Buy the Advanced Power Virtualization feature and enter a authorization code at the HMC
    • D、Buy the Advanced Power Virtualization feature and enter a authorization code at the service  processor menu

    正确答案:B

  • 第4题:

    Companycom has just installed a p5 595 with four uncapped LPARs in a shared processor pool. The system and profile settings are still in their default states. One of the LPARs has an application that is consuming all of the available shared processor resources. Users of this application are complaining about response time. Which of the following changes to the slow LPAR would improve response time?()

    • A、Enable SMT
    • B、Reduce the weight
    • C、Renice the process
    • D、Increase the weight

    正确答案:D

  • 第5题:

    Companycom is considering a partitioned solution with one of the LPARs utilizing 12 CPUs. Multiple applications will be loaded on this large LPAR. However, the customer wants to ensure some tasks will have higher priority access to the CPU and memory resources. Which of the following solutions would best satisfy the requirement?()

    • A、Loadleveler
    • B、AIX Workload Manager
    • C、Partition Load Manager
    • D、Tivoli Provisioning Manager

    正确答案:B

  • 第6题:

    单选题
    Companycom is about to purchase a POWER5 Enterprise server which requires two Ethernet ports and two disks for each of the four LPARs. It has been configured and validated using the IBM eConfig tool. Which of the following is very important to verify in addition to the eConfig validation?()
    A

    Total number of SCSI adapters

    B

    Total number of Ethernet adapters

    C

    Total number of Ethernet adapters and number of SCSI paths per LPAR

    D

    Total number of SCSI paths available and total number of SCSI adapters


    正确答案: A
    解析: 暂无解析

  • 第7题:

    单选题
    Companycom has a p5 595 running 12 LPARs. They are interested in high bandwidth, secure communication between two of the LPARs within the p5 595 server. They do not have any unused Ethernet adapters. Which of the following recommendations will best meet this requirement?()
    A

    Utilize the integrated 10/100/1000 network interface

    B

    Implement Virtual Ethernet to enable inter-partition communication

    C

    Implement shared Ethernet with the Ethernet adapters utilized in the other LPARs

    D

    Implement a Point to Point protocol serial communication between the p5 595 serial ports


    正确答案: A
    解析: 暂无解析

  • 第8题:

    单选题
    Companycom is installing a p5 595 with AIX 5.3. The DLPAR option for the resources cannot be selected on the HMC menus. However, the daemons are running on both the HMC and LPARs. Which of the following is a prerequisite for DLPAR functionality?()
    A

    The resources must be unallocated in an LPAR

    B

    The microcode on the pSeries must be current

    C

    All network adapters on the LPAR must be defined

    D

    Network connectivity and name resolution capability between HMC and LPARs


    正确答案: D
    解析: 暂无解析

  • 第9题:

    单选题
    A user has an application server LPAR with a physical Ethernet adapter. They want to have a database LPAR also connected to the application LPAR via virtual Ethernet. Their security policies require a firewall between the application LPAR and database LPAR. Which of the following virtual Ethernet configurations satisfies the customer’s requirements?()
    A

    The application server,firewall,and database server on the same VLAN

    B

    The application server and firewall on one VLAN,and the database server on a second VLAN

    C

    The application server on one VLAN,and the database server and firewall on a second VLAN

    D

    The application server and firewall on one VLAN,and the firewall and database server on a second VLAN


    正确答案: D
    解析: 暂无解析

  • 第10题:

    单选题
    Companycom wants to reduce the number of copper, Ethernet adapters on their 4 way p5 570 running AIX 5.3 used in each of the four LPARs. Companycom has one database LPAR, two application LPARs, and one web LPAR. Only the Web LPAR needs to communicate with the outside world. What is the minimum number of Ethernet adapters that should be provided to ensure redundancy and no single point of failure?()
    A

    One single port Ethernet adapter

    B

    Four dual port Ethernet adapters

    C

    Two single port Ethernet adapters

    D

    Eight single port Ethernet adapters


    正确答案: B
    解析: 暂无解析

  • 第11题:

    单选题
    Companycom is buying an application solution that bases its software licensing on the number of CPUs per machine. They will be running two instances of this application and will require 8 CPUs each. A second application is priced based on CPUs per LPAR as well as the class of machine. That application will require 8 CPUs. What is the best hardware to propose to keep the software cost low?()
    A

    A 24 way p5 595 with 3 LPARs

    B

    A 24 way p5 595 with 2 LPARs

    C

    One p5 570s 16 way and one p5 570 8 way

    D

    One p5 595 12 way active and 12 way inactive, and one p5 570 8 way


    正确答案: A
    解析: 暂无解析

  • 第12题:

    单选题
    Companycom has just installed a p5 595 with four uncapped LPARs in a shared processor pool. The system and profile settings are still in their default states. One of the LPARs has an application that is consuming all of the available shared processor resources. Users of this application are complaining about response time. Which of the following changes to the slow LPAR would improve response time?()
    A

    Enable SMT

    B

    Reduce the weight

    C

    Renice the process

    D

    Increase the weight


    正确答案: B
    解析: 暂无解析

  • 第13题:

    Companycom has just purchased a p5 570 with AIX 5.3. The customer would like to add a training LPAR to the system, but no processors are available. All of the partitions are using dedicated resources. The test LPAR is using one processor and has a 90% CPU idle rate. What can be done to setup this training LPAR quickly without disabling their current environment?()

    • A、Use AIX 5.3 which supports micro-partitioning for both the test and training LPARS
    • B、Use DLPAR to move resources from the test LPAR to training when training is active
    • C、Install Partition Load Manager to share resources between the test and training environments
    • D、Install Advanced Power Virtualization and then use micro-partitioning for both the test and  training LPARs

    正确答案:D

  • 第14题:

    A customer has an 8-way p5-570 with eight internal disk drives and AIX 5.2.  Which of the following must be added, if anything, to the configuration to support four LPARs, assuming each LPAR requires twodisk drives?()

    • A、7311-D20 drawer with four disks
    • B、Upgrade to AIX 5.3
    • C、Fiber adapters to attach to SAN
    • D、Nothing

    正确答案:D

  • 第15题:

    A customer is planning to buy a two enclosure Power 770, and will implement 4 LPARs with the following requirements:Each LPAR must have a private, dedicated connection to the network.The adapter for this network connection must be hot-swappable.The customer wants to minimize the number of I/O slots used. Which of the following fulfills the customer requirements?()

    • A、Two dual-port PCIe adapters
    • B、A four-port PCIe Ethernet adapter
    • C、Four separate PCIe Ethernet adapters
    • D、Two embedded Integrated Virtual Ethernet adapters (IVE)

    正确答案:C

  • 第16题:

    Companycom wants the application server LPAR to communicate with the database LPAR on a p5 590 without using network adapters. What does the customer need to install?()

    • A、VIO Server
    • B、AIX 5.2 ML4
    • C、Shared Ethernet Adapter
    • D、AIX 5.3 with Advanced Power Virtualization

    正确答案:D

  • 第17题:

    Companycom is planning a p5 595 running AIX 5L 5.3 LPARs. They would like to design the system using physical resources with maximum resource efficiency. One LPAR requires a peak load of 30 processors during the week with a low of 1 processor required on the weekend. The other LPAR requires only a single processor most of the time, but needs at least 24 processors at the beginning of the weekend to finish its weekly processing in the window allocated. Which of the following solutions is most appropriate to continuously maximize resource use for these two LPARs?()

    • A、Dynamic LPAR
    • B、Workload Manager
    • C、Partition Load Manager
    • D、Shared Processor Pools

    正确答案:C

  • 第18题:

    单选题
    A p5 570 customer is currently running AIX 5.3. The customer now wants to add Virtual Ethernet to two of the LPARs. This will enable the application tier can communicate to the database tier without using an external Ethernet card. What is the best way to accomplish this task?()
    A

    Create a VIO server

    B

    Modify the LPAR profiles to add a Virtual Ethernet adapter

    C

    Buy the Advanced Power Virtualization feature and enter a authorization code at the HMC

    D

    Buy the Advanced Power Virtualization feature and enter a authorization code at the service  processor menu


    正确答案: C
    解析: 暂无解析

  • 第19题:

    单选题
    Companycom is installing a p5 595 with AIX 5.3. The DLPAR option for the resources cannot be selected on the HMC menus. However, the daemons are running on both the HMC and LPARs. Which of the following is a prerequisite for DLPAR functionality?()
    A

    The resources must be unallocated in an LPAR

    B

    The microcode on the pSeries must be current

    C

    All network adapters on the LPAR must be defined

    D

    Network connectivity and name resolution capability between HMC and LPARs


    正确答案: D
    解析: 暂无解析

  • 第20题:

    单选题
    A customer has an 8-way p5-570 with eight internal disk drives and AIX 5.2.  Which of the following must be added, if anything, to the configuration to support four LPARs, assuming each LPAR requires twodisk drives?()
    A

    7311-D20 drawer with four disks

    B

    Upgrade to AIX 5.3

    C

    Fiber adapters to attach to SAN

    D

    Nothing


    正确答案: D
    解析: 暂无解析

  • 第21题:

    单选题
    Companycom wants the application server LPAR to communicate with the database LPAR on a p5 590 without using network adapters. What does the customer need to install?()
    A

    VIO Server

    B

    AIX 5.2 ML4

    C

    Shared Ethernet Adapter

    D

    AIX 5.3 with Advanced Power Virtualization


    正确答案: B
    解析: 暂无解析

  • 第22题:

    单选题
    Companycom has a p5 590 that has their production LPAR, their Tivoli Storage Manager (TSM) LPAR, and several other LPARs. What method would provide connectivity between the production LPAR, and the TSM LPAR, but be isolated from the other LPARs in the system without utilizing a Virtual IO Server or physical adapter resources?()
    A

    Use shared memory and semaphores to transfer the data to the TSM LPAR

    B

    Provide gigabit Ethernet adapters in each LPAR and run a crossover cable

    C

    Create a Virtual Ethernet between the production server and the TSM LPARs

    D

    Create a Virtual Ethernet between the TSM server LPAR and the non-production LPARs


    正确答案: D
    解析: 暂无解析

  • 第23题:

    单选题
    Companycom is planning a p5 595 running AIX 5L 5.3 LPARs. They would like to design the system using physical resources with maximum resource efficiency. One LPAR requires a peak load of 30 processors during the week with a low of 1 processor required on the weekend. The other LPAR requires only a single processor most of the time, but needs at least 24 processors at the beginning of the weekend to finish its weekly processing in the window allocated. Which of the following solutions is most appropriate to continuously maximize resource use for these two LPARs?()
    A

    Dynamic LPAR

    B

    Workload Manager

    C

    Partition Load Manager

    D

    Shared Processor Pools


    正确答案: C
    解析: 暂无解析

  • 第24题:

    单选题
    Companycom has just purchased a p5 570 with AIX 5.3. The customer would like to add a training LPAR to the system, but no processors are available. All of the partitions are using dedicated resources. The test LPAR is using one processor and has a 90% CPU idle rate. What can be done to setup this training LPAR quickly without disabling their current environment?()
    A

    Use AIX 5.3 which supports micro-partitioning for both the test and training LPARS

    B

    Use DLPAR to move resources from the test LPAR to training when training is active

    C

    Install Partition Load Manager to share resources between the test and training environments

    D

    Install Advanced Power Virtualization and then use micro-partitioning for both the test and  training LPARs


    正确答案: D
    解析: 暂无解析