One single port Ethernet adapter
Four dual port Ethernet adapters
Two single port Ethernet adapters
Eight single port Ethernet adapters
第1题:
Companycom is about to purchase a POWER5 Enterprise server which requires two Ethernet ports and two disks for each of the four LPARs. It has been configured and validated using the IBM eConfig tool. Which of the following is very important to verify in addition to the eConfig validation?()
第2题:
Companycom is installing a p5 595 with AIX 5.3. The DLPAR option for the resources cannot be selected on the HMC menus. However, the daemons are running on both the HMC and LPARs. Which of the following is a prerequisite for DLPAR functionality?()
第3题:
A p5 570 customer is currently running AIX 5.3. The customer now wants to add Virtual Ethernet to two of the LPARs. This will enable the application tier can communicate to the database tier without using an external Ethernet card. What is the best way to accomplish this task?()
第4题:
Companycom has just installed a p5 595 with four uncapped LPARs in a shared processor pool. The system and profile settings are still in their default states. One of the LPARs has an application that is consuming all of the available shared processor resources. Users of this application are complaining about response time. Which of the following changes to the slow LPAR would improve response time?()
第5题:
Companycom is considering a partitioned solution with one of the LPARs utilizing 12 CPUs. Multiple applications will be loaded on this large LPAR. However, the customer wants to ensure some tasks will have higher priority access to the CPU and memory resources. Which of the following solutions would best satisfy the requirement?()
第6题:
Total number of SCSI adapters
Total number of Ethernet adapters
Total number of Ethernet adapters and number of SCSI paths per LPAR
Total number of SCSI paths available and total number of SCSI adapters
第7题:
Utilize the integrated 10/100/1000 network interface
Implement Virtual Ethernet to enable inter-partition communication
Implement shared Ethernet with the Ethernet adapters utilized in the other LPARs
Implement a Point to Point protocol serial communication between the p5 595 serial ports
第8题:
The resources must be unallocated in an LPAR
The microcode on the pSeries must be current
All network adapters on the LPAR must be defined
Network connectivity and name resolution capability between HMC and LPARs
第9题:
The application server,firewall,and database server on the same VLAN
The application server and firewall on one VLAN,and the database server on a second VLAN
The application server on one VLAN,and the database server and firewall on a second VLAN
The application server and firewall on one VLAN,and the firewall and database server on a second VLAN
第10题:
One single port Ethernet adapter
Four dual port Ethernet adapters
Two single port Ethernet adapters
Eight single port Ethernet adapters
第11题:
A 24 way p5 595 with 3 LPARs
A 24 way p5 595 with 2 LPARs
One p5 570s 16 way and one p5 570 8 way
One p5 595 12 way active and 12 way inactive, and one p5 570 8 way
第12题:
Enable SMT
Reduce the weight
Renice the process
Increase the weight
第13题:
Companycom has just purchased a p5 570 with AIX 5.3. The customer would like to add a training LPAR to the system, but no processors are available. All of the partitions are using dedicated resources. The test LPAR is using one processor and has a 90% CPU idle rate. What can be done to setup this training LPAR quickly without disabling their current environment?()
第14题:
A customer has an 8-way p5-570 with eight internal disk drives and AIX 5.2. Which of the following must be added, if anything, to the configuration to support four LPARs, assuming each LPAR requires twodisk drives?()
第15题:
A customer is planning to buy a two enclosure Power 770, and will implement 4 LPARs with the following requirements:Each LPAR must have a private, dedicated connection to the network.The adapter for this network connection must be hot-swappable.The customer wants to minimize the number of I/O slots used. Which of the following fulfills the customer requirements?()
第16题:
Companycom wants the application server LPAR to communicate with the database LPAR on a p5 590 without using network adapters. What does the customer need to install?()
第17题:
Companycom is planning a p5 595 running AIX 5L 5.3 LPARs. They would like to design the system using physical resources with maximum resource efficiency. One LPAR requires a peak load of 30 processors during the week with a low of 1 processor required on the weekend. The other LPAR requires only a single processor most of the time, but needs at least 24 processors at the beginning of the weekend to finish its weekly processing in the window allocated. Which of the following solutions is most appropriate to continuously maximize resource use for these two LPARs?()
第18题:
Create a VIO server
Modify the LPAR profiles to add a Virtual Ethernet adapter
Buy the Advanced Power Virtualization feature and enter a authorization code at the HMC
Buy the Advanced Power Virtualization feature and enter a authorization code at the service processor menu
第19题:
The resources must be unallocated in an LPAR
The microcode on the pSeries must be current
All network adapters on the LPAR must be defined
Network connectivity and name resolution capability between HMC and LPARs
第20题:
7311-D20 drawer with four disks
Upgrade to AIX 5.3
Fiber adapters to attach to SAN
Nothing
第21题:
VIO Server
AIX 5.2 ML4
Shared Ethernet Adapter
AIX 5.3 with Advanced Power Virtualization
第22题:
Use shared memory and semaphores to transfer the data to the TSM LPAR
Provide gigabit Ethernet adapters in each LPAR and run a crossover cable
Create a Virtual Ethernet between the production server and the TSM LPARs
Create a Virtual Ethernet between the TSM server LPAR and the non-production LPARs
第23题:
Dynamic LPAR
Workload Manager
Partition Load Manager
Shared Processor Pools
第24题:
Use AIX 5.3 which supports micro-partitioning for both the test and training LPARS
Use DLPAR to move resources from the test LPAR to training when training is active
Install Partition Load Manager to share resources between the test and training environments
Install Advanced Power Virtualization and then use micro-partitioning for both the test and training LPARs