Micro-Partitioning support and the L3 controller is now between L2 and main memory.
Dynamic partitioning support and the L3 controller is now between L2 and main memory.
Micro-Partitioning support and the L3 controller is no longer between L2 and main memory.
Dynamic partitioning support and the L3 controller is no longer between L2 and main memory.
第1题:
A bank is interested in technology that will enhance competitiveness and flexibility in the financial trading market by harnessing the typically unused power of idle machines. The pSeries technical specialist should make the customer aware of which IBM offering?()
第2题:
A customer wants to take advantage of IBM’s Micro-Partitioning capabilities for their new AIX applications. The pSeries technical specialist should recommend purchasing which of the following?()
第3题:
The account executive is asking about post-sales support for a new p5 HMC. They need the pSeries technical specialist to configure an HMC with software support for the customer. Which of the following should the specialist include in the configuration?()
第4题:
A company has recently placed an order for a POWER4+ p650 server. Their facilities manager has approached the pSeries technical specialist to gather information on the correct power receptacle for thenew server. They have requested a picture of the power cord plug to show to their electrician. Where would the pSeries technical specialist find the required information?()
第5题:
A new p5 customer has just installed a partitioned p5-550 alongside some older POWER4 servers. The pSeries technical specialist has received a call to say that the existing HMC (7315) cannot connect to the new server. How can the specialist help the customer?()
第6题:
Is there a need for a PKI Management System?
Is there a need for end-to-end encryption?
Do they currently have a Kerberos domain in place?
Which clients are installed on their desktops -- SSH, Telnet or both?
第7题:
Sales Manual
Announcement Letter
POWER4+ p650 Specification Sheet
Site and Hardware Planning Information Manual
第8题:
Supportline
ServiceSuite
Software Maintenance Agreement (SWMA)
Machine Control Program Remote Support Agreement (MCPRSA)
第9题:
Direct the customer to the Installation Guide for each system to identify the power requirements.
Direct the customer to engage their site personnel to ensure the proper power connectors are provided to support the systems.
Direct the customer to the Site and Hardware Planning Information and review the system requirements for each new pSeries system.
Direct the customer to the Site and Hardware Planning Information to confirm that enough space is available in the rack to allow for proper airflow.
第10题:
Use eConfig to configure and validate each pSeries and p5 system.
Engage Advanced Technical Support to review any outstanding technical issues.
Confirm with the customer that the solution design meets their requirements.
Perform a Pre-Install Solution Assurance Review to validate required power requirements.
第11题:
p5 hardware, AIX 5.2, Virtual I/O Server
POWER4 hardware, AIX 5.3, Virtual I/O Server,
p5 hardware, AIX 5.3, Advanced POWER Virtualization feature
POWER4 hardware, AIX 5.2, Advanced POWER Virtualization feature
第12题:
Create a POWER5 technical presentation for the account executive’s use.
Mentor the account executive with the most important POWER5 features and benefits.
Attend the meeting instead of the account executive to present the POWER5 features and benefits.
Join the meeting via teleconference at a prescheduled time to present the POWER5 features and benefits.
第13题:
A customer has requested the most cost-effective p5 solution allowing for growth. Which of the following should the pSeries technical specialist consider doing when configuring each p5 system using eConfig?()
第14题:
A customer has two locations that host their pSeries servers. Traffic is being routed through the public Internet. The customer needs to exchange confidential financial data between the servers. Which of the following solutions should the pSeries technical specialist propose to the customer to secure the data?()
第15题:
A customer currently has five partitioned POWER4 systems and is adding new systems. When the pSeries technical specialist introduces the first p5 system with CoD into this environment, how should the HMC be handled?()
第16题:
A customer’s data center has all POWER4+ systems, and they plan to add three new p5-570 systems. They will be purchasing a new 7310-CR2 HMC to support the POWER5 systems. What is a key requirement that they need to plan for with the new HMC?()
第17题:
The account team is putting together a very complex solution for the customer. During the solution design phase, many of the customer’s requirements have changed and additional requirements are being identified. What should the pSeries technical specialist do to ensure the greatest possible customer satisfaction?()
第18题:
Implementing CoD
Using Express Configurations with processor upgrades
Meeting the minimum Value Pak rules
Engaging the pSeries representative to identify appropriate discounts
第19题:
Micro-Partitioning support and the L3 controller is now between L2 and main memory.
Dynamic partitioning support and the L3 controller is now between L2 and main memory.
Micro-Partitioning support and the L3 controller is no longer between L2 and main memory.
Dynamic partitioning support and the L3 controller is no longer between L2 and main memory.
第20题:
Explain to the customer that they need an additional HMC for the POWER5 system.
Obtain a PO from the customer to purchase additional serial connections to the HMC.
Obtain a PO from the customer to purchase additional Ethernet connections to the HMC.
Explain to the customer that they need a firmware update on the HMC to support both POWER4 and POWER5.
第21题:
A DCE domain
A Kerberos domain
A PPP tunnel between the servers
An IPSEC tunnel between the servers
第22题:
IBM Grid Toolbox
IBM Capacity on Demand
IBM Cluster Systems Management
IBM Global Solutions Directory
第23题:
Order a new HMC to support the p5 system.
Attach the new p5 system to the existing HMC.
Upgrade the existing HMC to accommodate both the POWER4 and p5 systems.
Do nothing. This system does not require an HMC.
第24题:
p650
p5-570
Two p630s