单选题They will not start the project until the board chairman _____ back from South Africa.A will comeB is comingC cameD comes

题目
单选题
They will not start the project until the board chairman _____ back from South Africa.
A

will come

B

is coming

C

came

D

comes


相似考题
参考答案和解析
正确答案: A
解析:
句意:等董事会主席从南非回来,他们才会运作这个项目。not until经常连用,意思是“直到……才……”。使用not until时要注意前后句子的时态,until表示的是一个时间点,主句用的是一般将来时,从句要用现在时,选D。A项、B项和C项在时态上均不符本题意思。
更多“They will not start the project until the board chairman ___”相关问题
  • 第1题:

    ● A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:

    A Change the scope baseline

    B Prepare a variance report

    C Call a meeting of the configuration control board

    D Change the project's objectives

    E Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline


    正确答案:E

  • 第2题:

    The chairman of the board _______ on me the unpleasant job of dismissing good workers the firm can no longer afford to employ.

    A compelled B posed C pressed D tempted


    正确答案:C
    选[C]。[B]posed:提出,陈述;[D]tempted:引诱可以很快排除;[A][C]互为强干扰项,都表示"强迫"的意思,但只有press才可以用press sth on sb 这样的结构,意思是把…强加于人。本句大意是:董事会主席把解散公司雇佣不起的优秀职员这样讨厌的工作强加于我。

  • 第3题:

    MONTHLY MEETING MINUTES OF BOARD OF DIRECTORS Time: 2:30 p.m., March 5, 2015 Place: Conference room, second floor of 3T Co. Ltd. Participants: All the directors Chairman: Chairman of the board, Mr. William Forest Minutes keeper: Linda The main activities at the meeting are as follows: Firstly, Mr. William Forest, chairman of the board, made a report on the work and total sales of the company this season. Then the report was followed by a heated discussion. Secondly, all the directors agreed to hold a press conference for the company next month. Thirdly, the meeting suggested inviting experts from Canada to give a five-day training course to staff in the Sales Department. The meeting finished at 3:30 p.m.

    1. Who are the meeting participants().

    A. The executive assistants.

    B. The directors.

    C. The interviewees.

    2. How many activities does the meeting have().

    A. The executive assistants.

    B. The directors.

    C. The interviewees.

    3. Mr. William Forest made a report ()this season.

    A. on training course to staff in the Sales Department

    B. on the advertisement policies of the company

    C. on the work and total sales of the company

    4. What did all the directors agree to do ()

    A. To carry out a training project in the company next year.

    B. To have another board meeting of all directors next season.

    C. Tohave a press conference for the company next month.

    5. How long did the meeting last ()

    A.1.5 hours.

    B.1 hour.

    C.2 hour.


    参考答案:子问题 1:B; 子问题 2:C; 子问题 3:C; 子问题 4:C; 子问题 5:B

  • 第4题:

    The Chairman and the remaining 16 board directors of the Representatives' Commission are elected by its shareholding employees.()

    此题为判断题(对,错)。


    参考答案:错

  • 第5题:

    A()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.

    A.gantt chart

    B.project histogram

    C.milestone chart

    D.project flowchart


    正确答案:A

  • 第6题:

    It is recommended that the project _____ until 选择

    It is recommended that the project _____ until all the preparations have been made.

    (A) is not started                          (C) not be started

    (B) will not be started                   (D) is not to be started

     


    C.虚拟语气 recommended +that should+原形should可省        此题为被动

  • 第7题:

    A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( )

    A.assign change tasks to project members
    B.call a meeting of the configuration control board
    C.change the scope baseline
    D. postpone the modification until a separate enhancement project is fundedafter this project is completed according to the original baseline

    答案:D
    解析:
    项目经理认为调整项目范围可以给客户提供增值的服务,项目经理应该怎么做。
    选项A是安排任务变更到项目成员,选项B是召集变更控制委员会会议,选项C是变更项目基线,选项D是按照原先的基线,在确定完成一项改进项目会得到客户的相应资金前,暂缓修改。
    由于是在原内容基础上增加增值服务内容,超出原先范围,应先确定客户认可和增加新资金。因此应选择D。

  • 第8题:

    There are four phases in the life cycle of a project:start,plan,execute and( ).

    A.implement
    B.performance
    C.end
    D.excute

    答案:C
    解析:
    项目的生命周期有四个阶段为启动、计划、执行与结束。A执行B执行C结束D执行

  • 第9题:

    Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by ( ) .

    A.executive IT manager
    B.project manger
    C.change control board
    D.project sponsor

    答案:C
    解析:
    项目变更可以由执行经理(executive IT manager)、项目管理者(project manager)、项目发起人(project sponsor)等任意项目干系人发起,但只能由变更控制委员会(change control board)授权通过。(73) A.执行经理 B.项目经理 C.变更控制委员会 D.项目发起人

  • 第10题:

    The researcher has to start looking for a company()

    A which I would like you to have.

    B that values his new ideas.

    C which is the Mark 2 project.

    D that the process can be made simpler.


    B

  • 第11题:

    ()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.

    • A、gantt chart
    • B、project histogram
    • C、milestone chart
    • D、project flowchart

    正确答案:A

  • 第12题:

    单选题
    Two boards are being cut for a construction project. If the total length of the boards is 100 inches and the shorter board is 5 inches less than half the length of the longer board, what is the length of the shorter board?
    A

    25 inches

    B

    30 inches

    C

    35 inches

    D

    65 inches

    E

    70 inches


    正确答案: B
    解析:
    设长板的长度为x,短板的长度为y,故x+y=100,y=0.5x-5,故y=30,所以本题选B项。

  • 第13题:

    ● Free float is the amount of time that an activity may be delayed with out affecting the _____.

    A Early start of the succeeding activities.

    B Late start of the succeeding activities.

    C Project finish.

    D Cost of the project.

    E None of the above.


    正确答案:A

  • 第14题:

    A project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should______.

    A.assign change tasks to project members

    B.call a meeting of the configuration control board

    C.change the scope baseline

    D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline


    正确答案:D
    解析:项目经理认为调整项目范围可以给客户提供增值的服务,项曰经理应该怎么做。
      选项A是安排任务变更到项目成员,选项B是召集变更控制委员会会议,选项C是变更项目基线,选项D是按照原先的基线,在确定完成一项改进项目会得到客户的相应资金前,暂缓修改。
      由于是在原内容基础上增加增值服务内容,超出原先范围,应先确定客户认可和增加新资金,因此应选择D。

  • 第15题:

    The board will decide whether to approve or disapprove Bob’s plan on the Nanjing project.()

    此题为判断题(对,错)。


    参考答案:正确

  • 第16题:

    There may be an ____ for you to see the chairman of the board tomorrow.

    A.ability

    B.future

    C.possibility

    D.opportunity


    参考答案:D

  • 第17题:

    A__(74)__is a type of bar chart that illustrates a project schedul

    A.It illustrates the start and finish dates of the terminal elements and summary elements of a project.

    B.Gantt chart

    C.project histogram

    D.milestone chart

    E.project flowchart


    正确答案:A
    甘特图是一种用来描述项目计划的条形图,它描述了项目的各个底层工作单元以及概括性工作单元的开始日期与结束日期。

  • 第18题:

    Regulations require certain records to be retained on board for at least 3 months after a ship is involved in a casualty or until advised that they are no longer needed on board by the ______.

    A.owner

    B.Master

    C.person in charge

    D.Officer in Charge,Marine Inspection


    正确答案:D

  • 第19题:

    In project management, a ( ) is a listing of a project’s milestones ,activities, and deliverables, usually with intended start and finish dates。

    A.schedule
    B.activity
    C.Plan
    D.contractor

    答案:A
    解析:
    在项目管理中,( )是项目的里程碑、活动和交付物的列表,通常包括开始和完成日期。

  • 第20题:

    ( ) is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.

    A.gantt chart
    B.project histogram
    C.milestone chart
    D.project flowchart

    答案:A
    解析:
    甘特图是一类描述项目进度的图表。它说明了一个项目的开始和结束时间。A.甘特图 B.项目直方图C.里程碑图 D.项目流程图

  • 第21题:

    A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( ) .

    A.assign change tasks to project members
    B.call A.meeting of the configuration control board
    C.change the scope baseline
    D.postpone the modification until A.separate enhancement project is fundeD.after this project is completeD.according to the original baseline

    答案:D
    解析:
    项目经理认为调整项目范围可以给客户提供增值的服务,项目经理应该怎么做。

    选项A是安排任务变更到项目成员,选项B是召集变更控制委员会会议,选项C是变更项目基线,选项D是按照原先的基线,在确定完成一项改进项目会得到客户的相应资金前,暂缓修改。

    由于是在原内容基础上增加增值服务内容,超出原先范围,应先确定客户认可和增加新资金。因此应选择D。

  • 第22题:

    The () will have a rotating honorary chairman.

    • A、Board of Directors
    • B、Boards of Director
    • C、boards of director
    • D、Board Directors

    正确答案:A

  • 第23题:

    单选题
    Regulations require certain records to be retained on board for at least 3 months after a ship is involved in a casualty or until advised that they are no longer needed on board by the ().
    A

    owner

    B

    Master

    C

    person in charge

    D

    Officer in Charge,Marine Inspection


    正确答案: D
    解析: 暂无解析

  • 第24题:

    单选题
    They will not start the project until the board chairman _____ back from South Africa.
    A

    will come

    B

    is coming

    C

    came

    D

    comes


    正确答案: D
    解析:
    本题考查句式结构。句意:等董事会主席从南非回来,他们才会运作这个项目。not...until...在使用时,要注意前后句子的时态,until表示的是一个时间点,主句用的是一般将来时,从句要用现在时,选D。