Companycom has seven days of vmstat data on a p5 590. The server has a total of four test/dev LPARs and 4 production LPARs of one processor each. On the four test/dev LPARs, the data shows 90-95% peak utilizations with a duration of from 5 to 10 minutes. The average utilizations of all LPARs were between 15-30%. All of the applications have different times when they peak. What is the best configuration to fully utilize the processor resource?()
第1题:
Companycom has a p5 590 that has their production LPAR, their Tivoli Storage Manager (TSM) LPAR, and several other LPARs. What method would provide connectivity between the production LPAR, and the TSM LPAR, but be isolated from the other LPARs in the system without utilizing a Virtual IO Server or physical adapter resources?()
第2题:
Companycom is about to purchase a POWER5 Enterprise server which requires two Ethernet ports and two disks for each of the four LPARs. It has been configured and validated using the IBM eConfig tool. Which of the following is very important to verify in addition to the eConfig validation?()
第3题:
A customer has defined their server needs as a four-LPAR 16-way p570 with 64GB of memory, four 10/100/1000 TX LAN adapters, and six fibre channel adapters to external storage in an IBM ESS (Shark). They like the idea of being able to do SAN maintenance while not incurring downtime. If all LPARs are production related and similar, which question is most appropriate for the pSeries technical specialist to ask?()
第4题:
Companycom wants to deploy WebSphere in an HACMP environment, running on two servers in LPARs. These servers will also host the test and dev LPARs. The customer would like to use the test and dev resources to support an HACMP failover. What is the best way to accomplish this task?()
第5题:
The pSeries technical specialist is designing a two LPAR p5-570 with eight total processors. The system is a test system to run AIX 5.2. The customer has stated a preference for internal disks for the boot devices. The customer has said they may later need to run three or four LPARs without increasing the number of processors. What should the pSeries technical specialist tell the customer about the ability of the p5-570 to meet their requirements?()
第6题:
A customer is looking for a reliable well-performing, cost-effective solution to a growing commercial workload. Initially, they want to run 12 UDB partitions, each of which would need two processors and 8GB of memory. They are looking at the p655 and want to start with three LPARS on each p655 node using a total of four nodes. Each LPAR would need at least 4 x 6239 fibre cards and 2 x 5706 2-port 10/100/1000 Ethernet cards. At a later date, they want to add an additional LPAR to each node to expand to a total of 16 UDB partitions. Which of the following major limitations of this solution should be mentioned to the customer?()
第7题:
Companycom is planning a p5 595 running AIX 5L 5.3 LPARs. They would like to design the system using physical resources with maximum resource efficiency. One LPAR requires a peak load of 30 processors during the week with a low of 1 processor required on the weekend. The other LPAR requires only a single processor most of the time, but needs at least 24 processors at the beginning of the weekend to finish its weekly processing in the window allocated. Which of the following solutions is most appropriate to continuously maximize resource use for these two LPARs?()
第8题:
Companycom has a p5 595 running 12 LPARs. They are interested in high bandwidth, secure communication between two of the LPARs within the p5 595 server. They do not have any unused Ethernet adapters. Which of the following recommendations will best meet this requirement?()
第9题:
A shared pool with four capped LPARs
A shared pool with four uncapped LPARs
Four dedicated LPARs and use DLPAR to manage resources effectively
The server in SMP mode and use WLM to manage resources effectively
第10题:
The p655 supports only two LPARs.
The p655 supports only four LPARs.
There are not enough available slots for three LPARs.
There are not enough available slots for four LPARs.
第11题:
LPARs 1 and 2, capped, SMT on, Weights between 25-30, min CPU 0.1, max CPU 1.0 LPARs 3 and 4, uncapped, SMT on, Weights between 100-130, min CPU 2.7, max CPU 3.0
LPARs 1 and 2, capped, SMT on, Weights between 100-130, min CPU 0.1, max CPU 1.0 LPARs 3 and 4, uncapped, SMT on, Weights between 25-30, min CPU 2.7, max CPU 3.0
LPARs 1 and 2, uncapped, SMT on, Weights between 25-30, min CPU 0.1, max CPU 1.0 LPARs 3 and 4, capped, SMT on, Weights between 100-130, min CPU 2.7, max CPU 3.0
LPARs 1 and 2, uncapped, SMT off, Weights between 25-30, min CPU 0.1, max CPU 1.0 LPARs 3 and 4, capped, SMT on, Weights between 100-130, min CPU 2.7, max CPU 3.0
第12题:
It will require additional SCSI adapters and I/O drawers or external disks to support more than two LPARs.
It has sufficient built-in SCSI controllers and disk enclosures to support four total LPARs by only adding the necessary additional disks.
It is unable to use internal disks for LPARs and therefore additional adapters I/O drawers or external disks must be used to support all LPARs.
It can support six LPARs with internal disks but will require special features, cables and an adapter to support the additional LPARs with internal disks.
第13题:
Companycom has the following: 8 x 1.65GHz CPUs 16GB Memory 4 LPARs LPAR 1: Test/Dev 1 CPU, 2GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 2: QA 1 CPU, 2GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 3: Prod 3 CPUs, 6GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 4: Web App 3 CPUs, 6GB Memory, 1 Fibre Channel HBA, SUSE Linux Utilization over a 30 day period LPAR 1: Average utilization was 15%, Peak utilization was 100% LPAR 2: Average utilization was 25%, Peak utilization was 100% LPAR 3: Average utilization was 50%, Peak utilization was 90% LPAR 4: Average utilization was 35%, Peak utilization was 100% If the customer has a requirement for all four LPARs moved to a p5 590 and to have dedicated CPU resources. Which of the following would best describe the profile requirements?()
第14题:
Companycom has just purchased a p5 570 with AIX 5.3. The customer would like to add a training LPAR to the system, but no processors are available. All of the partitions are using dedicated resources. The test LPAR is using one processor and has a 90% CPU idle rate. What can be done to setup this training LPAR quickly without disabling their current environment?()
第15题:
Companycom is planning to do server consolidation on POWER5. The customer has a test environment, a QA environment and a production environment for two applications. Both the test and QA environments are very small and are only utilized when new releases are being developed and tested. They require less than 1 CPU each. Both production applications require 2 CPUs for day-to-day operation and can require up to an additional 2 CPUs each during abrupt peak requirements. What is the best design for the LPARs?()
第16题:
Companycom has five LPARs, but only one CD drive. How should the CD drive be shared among all the users without system administrator action?()
第17题:
Companycom has just installed a p5 595 with four uncapped LPARs in a shared processor pool. The system and profile settings are still in their default states. One of the LPARs has an application that is consuming all of the available shared processor resources. Users of this application are complaining about response time. Which of the following changes to the slow LPAR would improve response time?()
第18题:
Companycom is using shared processor LPARs exclusively, including the Virtual IO Server. The users are complaining about response time. The application LPARs can be heavy processor users. The Virtual IO Server has been measured to be processor constrained. How should the Virtual IO Server's shared processor LPAR be configured?()
第19题:
Companycom has the following: 8 x 1.65GHz CPUs 16GB Memory 4 LPARs LPAR 1: Test/Dev 1 CPU, 2GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 2: QA 1 CPU, 2GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 3: Prod 3 CPUs, 6GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 4: Web App 3 CPUs, 6GB Memory, 1 Fibre Channel HBA, SUSE Linux Utilization over a 30 day period LPAR 1: Average utilization was 15%, Peak utilization was 100% LPAR 2: Average utilization was 25%, Peak utilization was 100% LPAR 3: Average utilization was 50%, Peak utilization was 90% LPAR 4: Average utilization was 35%, Peak utilization was 100% If the customer has a requirement for all four LPARs to be moved to a p5 590 and assigned to a shared pool. Which of the following would best describe the profile requirements?()
第20题:
Total number of SCSI adapters
Total number of Ethernet adapters
Total number of Ethernet adapters and number of SCSI paths per LPAR
Total number of SCSI paths available and total number of SCSI adapters
第21题:
A
B
C
D
第22题:
One single port Ethernet adapter
Four dual port Ethernet adapters
Two single port Ethernet adapters
Eight single port Ethernet adapters
第23题:
LPARs 1 and 2, SMT on, min CPU 1.0, max CPU 1.0, desired CPU 1.0 LPARs 3 and 4, SMT on, min CPU 1.0, max CPU 3.0, desired CPU 2.0
LPARs 1 and 2, SMT on, min CPU 1.0, max CPU 1.0, desired CPU 1.0 LPARs 3 and 4, SMT on, min CPU 2.0, max CPU 3.0, desired CPU 3.0
LPARs 1 and 2, SMT on, min CPU 1.0, max CPU 3.0, desired CPU 3.0 LPARs 3 and 4, SMT on, min CPU 1.0, max CPU 3.0, desired CPU 2.0
LPARs 1 and 2, SMT off, min CPU 1.0, max CPU 1.0, desired CPU 1.0 LPARs 3 and 4, SMT off, min CPU 1.0, max CPU 3.0, desired CPU 3.0