  • 第1题:

    92 The main player in project communication is the

    A. sponsor

    B. project manager

    C. functional manager

    D. functional team

    E. All of the above


    正确答案:B

  • 第2题:

    121 The quality objectives are approved in the conceptual stage of the project by the:

    A. Project Engineer

    B. Project Manager

    C. Functional Manager

    D. Quality Assurance Manager

    E. Project Owner


    正确答案:E

  • 第3题:

    18 Interfacing with the customer after project go-ahead is the responsibility of:

    A. Project sponsor

    B. Project team

    C. Project manager

    D. Functional manager

    E. All of the above are possible, based upon the size and complexity of the project


    正确答案:C

  • 第4题:

    ● The scope baseline/project charter is prepared by the:

    A Project manager

    B Project manager and project office

    C Project manager, project office and functional team

    D Project manager, project office, functional team and project sponsor

    E Project manager, project sponsor and customer/user


    正确答案:E

  • 第5题:

    ● The project life-cycle can be described as(72).

    (72)

    A.project concept, project planning, project execution, and project close-out

    B.project planning, work authorization, and project reporting

    C.project planning, project control, project definition, WBS development, and project termination

    D.project concept, project execution, and project reporting


    正确答案:A

    试题(72)分析
      关于项目周期划分正确的是  (72)  。
      A.启动、计划、执行、收尾
      B.计划、授权、报告
      C.计划、控制、方案设计、WBS的发展、终止
      D.启动、执行、报告
    参考答案
      (72)A

  • 第6题:

    In project management,a ( ) is a list of a project’s milestones,activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource allocation,budget and duration, linked by dependencies and scheduled events.

    A.schedule

    B.WBS

    C.SOW

    D.charter


    正确答案:A
    在项目管理中,进度管理的里程碑清单、活动和可交付物,通常都有明确的开始和结束日期,这些条目通常在资源分配中已经进行估算,在预算和持续时间上依赖于事件的调度。

  • 第7题:

    在Project2003中,以下关于总览项目的叙述错误的是( )。

    A.总览项目可以使用户对报表体情况有所了解

    B.Project 2003 提供了很多任务视图、资源视图和组合图视图

    C.Project2003 提供了多个可以进行简单选择、预览和打印的内置报表

    D.Project 2003 提供的报表汇集了最常用的信息集


    正确答案:A

  • 第8题:

    The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) .

    A.Chang control board
    B.Project management office
    C.Project manager
    D.Configuration management officer

    答案:C
    解析:
    实施整体变更控制过程是从项目开始到项目结束并且是项目经理的最终责任。

  • 第9题:

    A schedule is commonly used in project planning and project portfolio management.( ) on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work, or a contract data requirements list.

    A.Essences
    B.Elements
    C.Purposes
    D.Issues

    答案:B
    解析:
    时间表常用于项目规划和项目组合管理。时间表的元素与工作分解结构(WBS)的最终元素,工作说明书,或合同数据需求清单密切相关。

  • 第10题:

    在Project 2003中,以下关于总览项目的叙述错误的是()。

    • A、总览项目可以使用户对报表体情况有所了解
    • B、Project 2003提供了很多任务视图、资源视图和组合图视图
    • C、Project 2003提供了多个可以进行简单选择、预览和打印的内置报表
    • D、Project 2003提供的报表汇集了最常用的信息集

    正确答案:A

  • 第11题:

    You create a Visual Studio 2010 solution that includes a WCF service project and an ASP.NET project. The service includes a method named GetPeople that takes no arguments and returns an array of Person objects. The ASP.NET application uses a proxy class to access the service. You use the Add Service Reference wizard to generate the class. After you create the proxy, you move the service endpoint to a different port. You need to configure the client to use the new service address. In addition, you must change the implementation so that calls to the client proxy will return a List instead of an array. Which two actions should you perform?()

    • A、In the context menu for the service reference in the ASP.NET project, select the Configure Service Reference commSystem.Collections.Generic.List
    • B、In the context menu for the service reference in the ASP.NET project, select the Update Service Reference comma
    • C、Change the service interface and implementation to return a List
    • D、Edit the address property of the endpoint element in the web.config file to use the new service address

    正确答案:A,D

  • 第12题:

    单选题
    以下哪种不是Project Menu提供的项目导出方法?()
    A

    Extract

    B

    AAF

    C

    Project Manager

    D

    Batch List


    正确答案: A
    解析: 暂无解析

  • 第13题:

    112 Of the following, who has the ultimate responsibility for meeting project quality objectives?

    A. Project Engineer

    B. Project Manager

    C. Functional Manager

    D. Quality Assurance Manager

    E. Project Owner


    正确答案:B

  • 第14题:

    10 The project charter is developed by:

    A. senior management

    B the customer

    C. the project manager

    D. both A and C

    E. None of the above


    正确答案:D

  • 第15题:

    ● Interfacing with the customer after project go-ahead is the responsibility of:

    A Project sponsor

    B Project team

    C Project manager

    D Functional manager

    E All of the above are possible, based upon the size and complexity of the project


    正确答案:C

  • 第16题:

    ● The project charter is developed by:

    A senior management

    B the customer

    C the project manager

    D both A and C

    E None of the above.


    正确答案:D

  • 第17题:

    The perform. Integrated Change Contorl process is the ultimate responsibility of the(①).Although changes may be initiated verbally,they should be recorded in writtern form. and entered into the (②)system.

    ①A.resource manager

    B.division manager

    C.functional manager

    D.project manager

    ②.A.quality management

    B.configuration management

    C.project manager

    D.scope management


    参考答案:D,D

  • 第18题:

    以下关于总揽项目的叙述错误的是()。

    A.Project 2003提供了多个可以进行简单选择、预览和打印的内置报表

    B.Project 2003提供了很多任务视图、资源视图和组合图视图,它们可以用不同格式显示在Project中输入的项目信息

    C.Project 2003提供的报表汇集了最常用的信息集,可以用来管理项目、调整资源、控制成本、分析潜在问题以及交流进度情况

    D.总揽项目可以使用户对视图的整体情况有所了解


    正确答案:D


  • 第19题:

    The Perform. Integrated Change Control process is conducted from project lnception through completion and is the ultimate responsibility of the(75)

    A.change control board

    B. project management office

    C.project manager

    D.configuration management officer


    正确答案:C
    本题目翻译:实施整体变更控制过程是从项目开始到完成进行,是项目经理的摄终责任。考察的是整体变更管理。

  • 第20题:

    The project life-cycle can be described as().

    A.project concept, project planning, project execution, and project close-out
    B.project planning, work authorization, and project reporting
    C.project planning, project control, project definition, WBS development, and project termination
    D.project concept, project execution, and project reporting

    答案:A
    解析:
    关于项目周期划分正确的是(72)。

    A. 启动、计划、执行、收尾

    B. 计划、授权、报告

    C. 计划、控制、方案设计、WBS的发展、终止

    D. 启动、执行、报告

  • 第21题:

    ( )is a document generated by the creating WBS process that support the WBS, which provides more detailed descriptions of the components in the WBS.

    A.The project charter
    B.The project scope statement
    C.The WBS dictionary
    D.The activity list

    答案:C
    解析:
    参考译文WBS词典是在分解WBS过程中产生的文档,用于支撑WBS,它更加详细的描述了WBS中组件。A.项目章程 B.范围说明书C. WBS词典 D.活动清单

  • 第22题:

    哪种加工类型更适合多品种生产?()

    • A、装配线(AssEmBly)
    • B、单件小批生产(joB-shop)
    • C、批量生产(BAtCh)
    • D、连续生产(Continuous)
    • E、项目(ProjECt)

    正确答案:B

  • 第23题:

    单选题
    哪种加工类型更适合多品种生产?()
    A

    装配线(AssEmBly)

    B

    单件小批生产(joB-shop)

    C

    批量生产(BAtCh)

    D

    连续生产(Continuous)

    E

    项目(ProjECt)


    正确答案: B
    解析: 暂无解析