第1题:
67 In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs.
A. Increase, decrease.
B. Increase, increase
C. Increase, increase or decrease.
D. Decrease, decrease.
E. Decrease, increase
第2题:
45______
A. steps
B. control
C. charge
D. risks
第3题:
There are two extremes in music, both of which can ________ risks.
A leadin
B bringin
C contributein
D resultin
第4题:
88 Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.
A. Increase, increase.
B. Increase, decrease.
C. Decrease, decrease.
D. Decrease, increase.
E. Remain the same, return to customer
第5题:
______(increase),new technology is making it easier for us to find alternative methods of testing.
第6题:
The word "exposures" in this paragraph can be understood as "risks".
A.Right
B.Wrong
C.Doesn't say