  • 第2题:

    PDM includes four types of dependencies or precedence relationships: ...(18). The completion of the successor activity depends upon the initiation of the predecessor activity.

    A.Finish-to-Start

    B.Finish-to-Finish

    C.Start-to-Start

    D.Start-to-Finish


    正确答案:D
    解析:PDM包括四种活动依赖或前导关系:...开始一结束。后续活动的结束依赖于前置活动的开始。

  • 第3题:

    ● Precedence Diagramming Method (PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called __(75)__.

    (75)

    A.Finish-to-Start

    B.Finish-to-Finish

    C.Start-to-Start

    D.Start-to-Finish


    正确答案:A

  • 第4题:

    PDM includes four types of dependencies or precedence relationships…(73),the initiation of the successor activity,depends upon the initiation of the predecessor activity.

    A.Finish-to-Start

    B.Finish-to-Finish

    C.Start-to-Start

    D.Start-to-Finish


    正确答案:C

  • 第5题:

    CMM(Capability Maturity Model)是由美国国防部DOD指定CMU的软件工程研究所SEI研究出来的一套过程规范,它将软件过程的成熟度分为(62)。

    A.Initial, Defined, Managed, Repeatable, Optimizing

    B.Initial, Repeatable, Managed, Defined, Optimizing

    C.Initial, Repeatable, Defined, Managed, Optimizing

    D.Initial, Managed, Defined, Repeatable, Optimizing


    正确答案:C
    解析:CMM将软件过程的成熟度分为:初始级(Initial),可重复级(Repeatable),定义级(Defined),管理级(Managed),优化级(Optimizing)。

  • 第6题:

    Precedence Diagramming Method(PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called ( ).

    A.Finish-to-Start
    B.Finish-to-Finish
    C.Start-to-Start
    D.Start-to-Finish

    答案:A
    解析:
    前导图法是用于活动排序的技术。前导图法包括四种活动依赖关系。先行活动结束后续活动才能开展的关系是结束—开始关系。