  • 第1题:

    100 The auditing function that provides feedback about the quality of output is referred to as:

    A. quality control.

    B. quality planning.

    C. quality assurance.

    D. quality improvement

    E. All of the above


    正确答案:C

  • 第2题:

    59 Quality Improvement Programs are normally associated with which two of the following?

    A. Juran and Crosby

    B. Juran and Deming

    C. Crosby and Deming

    D. Deming and the Japanese

    E. Crosby and the Japanese


    正确答案:D

  • 第3题:

    42 Which of the following is not an input to quality planning?

    A. scope statement.

    B. regulations.

    C. work results.

    D. standards.

    E. quality policy.


    正确答案:C

  • 第4题:

    Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.

    A.Benchmarking

    B.Quality metric

    C.Quality checklist

    D.Brainstornung


    参考答案:A

  • 第5题:

    ● (75)is one of the quality planning outputs.

    (75)

    A. Scope base line

    B. Cost of quality

    C. Product specification

    D. Quality checklist


    正确答案:D

  • 第6题:

    Quality management ensures that an organization , It has foor main components; quality planning,quality assurance. Quality control and quality ( )

    A.improvement

    B.change

    C.spiral

    D.evolution


    正确答案:A

  • 第7题:

    ()is one of the quality planning outputs.

    A.Scope base line
    B.Cost of quality
    C.Product specification
    D.Quality checklist

    答案:D
    解析:
    质量计划输出之一的是()A.范围基线 B.质量成本 C.产品规范 D.质量检查表

  • 第8题:

    Quality planning tools are often used to help plan effective quality management activities. ( ) is one of such tools,which involves comparing actual or planned project practices to other projects to generate ideas for improvement and to provide a basis by which to measure performance.

    A.Benchmarking
    B.Quality metric
    C.Quality checklist
    D.Brainstorming

    答案:A
    解析:
    质量规划工具通常用来帮助计划有效的质量管理活动。(71)是一个这样的工具,它通过与别的项目比较实际的或计划的项目活动,产生改进的建议,并且提供一个基准用来衡量业绩的依据。A.基准 B.质量度量 C.质量检查表 D.头脑风暴

  • 第9题:

    () is one of the quality planning outputs.

    • A、Scope base line
    • B、Cost of quality
    • C、Product specification
    • D、Quality checklist

    正确答案:D

  • 第10题:

    Which of the following statements best describes a Pre-sales Solution Assurance Review?()

    • A、An account team proposal review
    • B、An installation planning meeting
    • C、A solution design development methodology
    • D、A technical inspection of a completed solution design

    正确答案:D

  • 第11题:

    单选题
    Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.
    A

    Benchmarking

    B

    Quality metric

    C

    Quality checklist

    D

    Brainstornung


    正确答案: A
    解析: 暂无解析

  • 第12题:

    单选题
    Which of the following statements best describes a Pre-sales Solution Assurance Review?()
    A

    An account team proposal review

    B

    An installation planning meeting

    C

    A solution design development methodology

    D

    A technical inspection of a completed solution design


    正确答案: B
    解析: 暂无解析

  • 第13题:

    160 Which of the following is not an input to quality planning?

    A. scope statement.

    B. regulations.

    C. work results.

    D. standards.

    E. quality policy


    正确答案:C

  • 第14题:

    5 Which of the following constitute Juran's "quality trilogy":

    A. planning, inspection, control.

    B. planning, improvement, control.

    C. planning, organization, control.

    D. product, price, customer.

    E. design, build, deliver.


    正确答案:B

  • 第15题:

    82 Which of the following are included in the Acquisition phase(s) of the project life cycle.

    A. concept and development

    B. development and planning

    C. execution and phase-out

    D. planning and implementation

    E. concept and planning


    正确答案:C

  • 第16题:

    ●Which of the following is not an input to quality planning? (73) .

    (73) A. scope statement

    B. regulations

    C. work results

    D. standards


    正确答案:C

  • 第17题:

    ●Quality planning tools are often used to help plan effective quality management activities.(71) is one of such tools, which involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance.

    (71)A. Benchmarking

    B. Quality metric

    C. Quality checklist

    D. Brainstorming


    正确答案:A

  • 第18题:

    Quality management ensures that an organization,product or service is (1).It has four main components:quality planning,quality assurance,quality control and quality (2).

    A.guaranteed

    B.sustain

    C.good

    D.consistent@@@SXB@@@A.improvement

    B.change

    C.spiral

    D.evolution


    正确答案:D,A

  • 第19题:

    Quality management has four main components:quality planning .,quality assurance.,quality control and quality( ).

    A.improvement
    B.change
    C.spiral
    D.evolution

    答案:A
    解析:
    包括四个主要环节:质量计划、质量保证、质量控制和过程改进。A. 改进 B.变更 C.升级 D.进化

  • 第20题:

    ()is one of the quality planning outputs.

    A.Scope base line
    B.Cost of quality
    C.Product specification
    D.Quality checklist

    答案:D
    解析:
    是制定项目质量管理计划过程的成果之一。
    A.范围基线 B.质量成本
    C.产品规范 D.质量检查表

  • 第21题:

    Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.

    • A、Benchmarking
    • B、Quality metric
    • C、Quality checklist
    • D、Brainstornung

    正确答案:A

  • 第22题:

    Which of these is an accurate list of Cisco Lifecycle Services phases? Select exactly 1 answer(s) from the following:()。

    • A、initiation planning analysis design development implementation operations and maintenance
    • B、project planning, site assessment risk assessment solution selection and acquisition, testing, and operations
    • C、prepare, plan, design, implement operate, and optimize
    • D、analysis, design, deployment testing, implementation, and production
    • E、presales, project planning, development implementation, operations testing, and operations sign- off

    正确答案:C

  • 第23题:

    单选题
    Which of these is an accurate list of Cisco Lifecycle Services phases? Select exactly 1 answer(s) from the following:()。
    A

    initiation planning analysis design development implementation operations and maintenance

    B

    project planning, site assessment risk assessment solution selection and acquisition, testing, and operations

    C

    prepare, plan, design, implement operate, and optimize

    D

    analysis, design, deployment testing, implementation, and production

    E

    presales, project planning, development implementation, operations testing, and operations sign- off


    正确答案: D
    解析: 暂无解析