更多“Using the figure in the Special Window, what is the probability of success for Project B?A 0.3B 0.2C 0.35D 0.15E 0.12”相关问题
  • 第1题:

    Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.

    A . 2

    B . 3

    C . 4

    D . 5

    E . 7


    正确答案:C

  • 第2题:

    Using the figure in the Special window, The Critical path is _____ weeks.

    A . 21

    B . 22

    C . 23

    D . 24

    E . 25


    正确答案:D

  • 第3题:

    Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?

    A . 0

    B . 1

    C . 2

    D . 3

    E . 4


    正确答案:D

  • 第4题:

    Using the situation stated in the Special window, what is the cost performance index for Case #9?

    A . 1.1

    B . 1.91

    C . 0.83

    D . 1.2

    E . None of the above


    正确答案:A

  • 第5题:

    Using the scenario in the special window, the project manager:

    A will probably spend the weekend reviewing the data.

    B Won't ask for the report again.

    C Has a preference for written communication.

    D Has chosen an inappropriate medium.

    E Is experiencing communication overload.


    正确答案:E

  • 第6题:

    110 Using the figure in the Special window, The critical path is:

    A. A-B-G

    B. C-G

    C. C-D

    D. E-F

    E. A-B-G and C-D


    正确答案:B

  • 第7题:

    112 Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?

    A. P

    B. Q

    C. R

    D. S

    E. T


    正确答案:A

  • 第8题:

    117 Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.

    A. 11, 13

    B. 12, 14

    C. 13, 15

    D. 14, 16

    E. 15, 17


    正确答案:E

  • 第9题:

    120 Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.

    A. 2

    B. 3

    C. 4

    D. 5

    E. 7


    正确答案:C

  • 第10题:

    128 Using the situation stated in the Special window, what is present value of $1000 at 12% at the end of 5 years?

    A. $3605.00

    B. $0.57

    C. $567.00

    D. $892.86

    E. $3.61


    正确答案:C

  • 第11题:

    139 Using the scenario in the special window, the project manager:

    A. will probably spend the weekend reviewing the data.

    B. Won't ask for the report again.

    C. Has a preference for written communication.

    D. Has chosen an inappropriate medium.

    E. Is experiencing communication overload


    正确答案:E

  • 第12题:

    20 Using the scenario in the special window, the project manager appears to be a _____ manager.

    A. 1, 9

    B. 9, 1

    C. 1, 1

    D. 9, 9

    E. 5, 5


    正确答案:E

  • 第13题:

    Using the figure in the Special window, Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks.

    A . 2, 10

    B . 4, 12

    C . 6, 14

    D . 7, 15

    E . 9, 17


    正确答案:A

  • 第14题:

    Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?

    A . P

    B . Q

    C . R

    D . S

    E . T


    正确答案:A

  • 第15题:

    Using the figure in the Special window, The critical path is:

    A . A-B-G

    B . C-G

    C . C-D

    D . E-F

    E . A-B-G and C-D


    正确答案:B

  • 第16题:

    Using the scenario in the special window, the project manager appears to be a _____ manager.

    A . 1, 9

    B . 9, 1

    C . 1, 1

    D . 9, 9

    E . 5, 5


    正确答案:E

  • 第17题:

    Using the diagram in the Special window, what is the probability that Alternative I will be adopted and completed below budget:

    A 1.4

    B 0.8

    C 0.2

    D 0.12

    E None of the above


    正确答案:D

  • 第18题:

    111 Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?

    A. 0

    B. 1

    C. 2

    D. 3

    E. 4


    正确答案:D

  • 第19题:

    116 Using the diagram in the Special window, what is the probability that Alternative I will be adopted and completed below budget:

    A. 1.4

    B. 0.8

    C. 0.2

    D. 0.12

    E. None of the above


    正确答案:D

  • 第20题:

    118 Using the figure in the Special Window, what is the probability of success for Project B?

    A. 0.30

    B. 0.20

    C. 0.35

    D. 0.15

    E. 0.12


    正确答案:C

  • 第21题:

    124 Using the situation stated in the Special window, what is the total variable costs for producing one widget?

    A. $1,020

    B. $1,010

    C. $1,015

    D. $20.00

    E. None of the above


    正确答案:E

  • 第22题:

    138 Using the scenario in the special window, the project manager appears to be a _____ manager. A. 1, 9

    B. 9, 1

    C. 1, 1

    D. 9, 9

    E. 5, 5


    正确答案:E

  • 第23题:

    200 Using the figure in the Special Window, what is the probability of success for Project B?

    A. 0.30

    B. 0.20

    C. 0.35

    D.0.15

    E.0.12


    正确答案:C