171 Resource leveling _____.
A. Allocates resources to activities to find shortest schedule within fixed resource limits.
B. Smoothes out resource requirements by rescheduling activities within their float time.
C. Smooths out resource requirements by substituting activities with unassigned resources.
D. Attempts to reduce resource requirements within a constraint on project duration
E. B or D
第1题:
172 Smoothing out resource requirements from period to period is called resource _____.
A. Allocation.
B. Partitioning
C. Leveling.
D. Quantification
E. None of above
第2题:
2 The Work Breakdown Structure (WBS) is the basis for communicating:
A. Project scope, cost control, schedule, quality
B. Project objectives, dependencies, plan, cost control
C. Project scope, schedule, staffing, cost control
D. Project scope, quality, schedule, dependencies
E. Project budget, schedule, risk factors, work assignments
第3题:
195 The basic terminology for networks includes:
A. Activities, events, manpower, skill levels and slack.
B. Activities, documentation, events, manpower and skill levels.
C. Slack, activities, events, and time estimates.
D. Time estimates, slack, sponsorship involvement, and activities.
E. Time estimates, slack time, report writing, life cycle phases, and crashing times
第4题:
120 The Work Breakdown Structure (WBS) is the basis for communicating:
A. Project scope, cost control, schedule, quality
B. Project objectives, dependencies, plan, cost control
C. Project scope, schedule, staffing, cost control
D. Project scope, quality, schedule, dependencies
E. Project budget, schedule, risk factors, work assignments
第5题:
54 Smoothing out resource requirements from period to period is called resource _____.
A. Allocation.
B. Partitioning
C. Leveling.
D. Quantification
E. None of above
第6题:
● The Work Breakdown Structure (WBS) is the basis for communicating:
A Project scope, cost control, schedule, quality
B Project objectives, dependencies, plan, cost control
C Project scope, schedule, staffing, cost control
D Project scope, quality, schedule, dependencies
E Project budget, schedule, risk factors, work assignments.