171 Resource leveling _____.A. Allocates resources to activities to find shortest schedule within fixed resource limits.B. Smoothes out resource requirements by rescheduling activities within their float time.C. Smooths out resource requirements by substi

题目

171 Resource leveling _____.

A. Allocates resources to activities to find shortest schedule within fixed resource limits.

B. Smoothes out resource requirements by rescheduling activities within their float time.

C. Smooths out resource requirements by substituting activities with unassigned resources.

D. Attempts to reduce resource requirements within a constraint on project duration

E. B or D


相似考题
参考答案和解析
正确答案:E
更多“171Resource leveling _____. A.Allocates resources to activities to find shortest schedule ”相关问题
  • 第1题:

    172 Smoothing out resource requirements from period to period is called resource _____.

    A. Allocation.

    B. Partitioning

    C. Leveling.

    D. Quantification

    E. None of above


    正确答案:C

  • 第2题:

    2 The Work Breakdown Structure (WBS) is the basis for communicating:

    A. Project scope, cost control, schedule, quality

    B. Project objectives, dependencies, plan, cost control

    C. Project scope, schedule, staffing, cost control

    D. Project scope, quality, schedule, dependencies

    E. Project budget, schedule, risk factors, work assignments


    正确答案:A

  • 第3题:

    195 The basic terminology for networks includes:

    A. Activities, events, manpower, skill levels and slack.

    B. Activities, documentation, events, manpower and skill levels.

    C. Slack, activities, events, and time estimates.

    D. Time estimates, slack, sponsorship involvement, and activities.

    E. Time estimates, slack time, report writing, life cycle phases, and crashing times


    正确答案:C

  • 第4题:

    120 The Work Breakdown Structure (WBS) is the basis for communicating:

    A. Project scope, cost control, schedule, quality

    B. Project objectives, dependencies, plan, cost control

    C. Project scope, schedule, staffing, cost control

    D. Project scope, quality, schedule, dependencies

    E. Project budget, schedule, risk factors, work assignments


    正确答案:A

  • 第5题:

    54 Smoothing out resource requirements from period to period is called resource _____.

    A. Allocation.

    B. Partitioning

    C. Leveling.

    D. Quantification

    E. None of above


    正确答案:C

  • 第6题:

    ● The Work Breakdown Structure (WBS) is the basis for communicating:

    A Project scope, cost control, schedule, quality

    B Project objectives, dependencies, plan, cost control

    C Project scope, schedule, staffing, cost control

    D Project scope, quality, schedule, dependencies

    E Project budget, schedule, risk factors, work assignments.


    正确答案:A