40 For every situation, several methods usually exist for effective communication to take place. Which of the following is least likely to be used for explaining to the team project planning guidelines?A. project office memoB. project office directiveC. p

题目

40 For every situation, several methods usually exist for effective communication to take place. Which of the following is least likely to be used for explaining to the team project planning guidelines?

A. project office memo

B. project office directive

C. project team meeting

D. formal report

E.counseling sessions


相似考题
更多“40 For every situation, several methods usually exist for effective communication to take place. Which of the following is least likely to be used for explaining to the team project planning guidelines?A. project office memoB. project office directiveC. p”相关问题
  • 第1题:

    Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?

    A . Matrix

    B . Pure project

    C . Project coordinator

    D . Project expediter

    E . Classical/traditional


    正确答案:B

  • 第2题:

    Which of the following is least likely to be used in explaining to a team member why you consider his/her performance substandard?

    A Project office memo

    B counseling session

    C project team meeting

    D formal letter

    E individual conversation


    正确答案:C

  • 第3题:

    50 Which of the following is least likely to be used in explaining to a team member why you consider his/her performance substandard?

    A. Project office memo

    B. counseling session

    C. project team meeting

    D. formal letter

    E. individual conversation


    正确答案:C

  • 第4题:

    145 Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:

    A. The project manager and project office personnel.

    B. The project team and functional managers.

    C. The project sponsor.

    D. All of the above.

    E. A and B only


    正确答案:E

  • 第5题:

    108 In which type of organization is team building likely to be most difficult?

    A. Functional

    B. Projectized

    C. Matrixed

    D. Project expediter

    E. Project coordinator


    正确答案:C

  • 第6题:

    123 The scope baseline/project charter is prepared by the:

    A. Project manager

    B. Project manager and project office

    C. Project manager, project office and functional team

    D. Project manager, project office, functional team and project sponsor

    E. Project manager, project sponsor and customer/user


    正确答案:E

  • 第7题:

    122 For every situation, several methods usually exist for effective communication to take place. Which of the following is least likely to be used for explaining to the team project planning guidelines?

    A. project office memo

    B. project office directive

    C. project team meeting

    D. formal report

    E. counseling sessions


    正确答案:D

  • 第8题:

    ● Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:

    A The project manager and project office personnel.

    B The project team and functional managers.

    C The project sponsor.

    D All of the above.

    E A and B only.


    正确答案:E

  • 第9题:

    ●The project manager must maintain an effective communication link with the customer's satisfaction with the progress of the project. The project manager maintains this link through (71).

    (71)

    A.periodic project reports, periodic visits to the customer, and telephonic exchanges

    B.subordinates, project team members, and the project sponsor

    C.one-time reports, weekly reports, and monthly reports

    D.the telephone, facsimile, and data transmission


    正确答案:A

  • 第10题:

    The project manager must maintain an effective communication link with the customer'ssatisfaction with the progress of the project.The project manager maintains this link through( ).

    A.periodic project reports,periodic visits to the customer,and telephonic exchanges
    B.subordinates,project team members,and the project sponsor
    C.one-time reports,weekly reports,and monthly reports
    D.the telephone,facsimile,and data transmission

    答案:A
    解析:
    项目经理必须保持一个有效的沟通,项目经理保持这个环节,通过与客户的项目定期报告,定期走访客户和电话交流。

  • 第11题:

    The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false.

    • A、The communication management plan is contained in or is a subsidiary plan of, the project management plan.
    • B、The  communication  management  plan  can  be  formal  or informal, highly detailed or broadly framed, and based on the needs of the project.
    • C、The  communication  manamgement  plan  organize  and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.
    • D、The communication management plan can include guidelines project status meetings,project team meetings,e-meetines,and e-mail

    正确答案:C

  • 第12题:

    单选题
    The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false.
    A

    The communication management plan is contained in or is a subsidiary plan of, the project management plan.

    B

    The  communication  management  plan  can  be  formal  or informal, highly detailed or broadly framed, and based on the needs of the project.

    C

    The  communication  manamgement  plan  organize  and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.

    D

    The communication management plan can include guidelines project status meetings,project team meetings,e-meetines,and e-mail


    正确答案: A
    解析: 沟通管理计划用于确定项目千系人的信息需求和沟通方法,以下关于沟通管理计划的叙述中,错误的是:沟通管理计划定期收集、对比和分析基准与实际数据,以便了解和沟通项目进展与绩效情况。 A:沟通管理计划是项目管理计划的一部分或子计划 B:沟通管理计划可以根据项目需求是正式或非正式的、非常详细或高度概括的。 C://沟通管理计划定期收集、对比和分析基准与实际数据,以便了解和沟通项目进展与绩效情况。 D://沟通管理计划可包括关于状态会议、项目团队回忆、网络会议和电子邮件等的指南。

  • 第13题:

    Which of the following time robbers end up creating additional work for the project manager and the project office?

    A . Failure to delegate

    B . Changes without notification or direction

    C . Unreasonable time constraints

    D . Over directing people

    E . All of the above


    正确答案:E

  • 第14题:

    For every situation, several methods usually exist for effective communication to take place. Which of the following is least likely to be used for explaining to the team project planning guidelines?

    A project office memo

    B project office directive

    C project team meeting

    D formal report

    E counseling sessions


    正确答案:D

  • 第15题:

    116 Which of the following time robbers end up creating additional work for the project manager and the project office?

    A. Failure to delegate

    B. Changes without notification or direction

    C. Unreasonable time constraints

    D. Over directing people

    E. All of the above


    正确答案:E

  • 第16题:

    4 Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?

    A. Matrix

    B Pure project

    C. Project coordinator

    D. Project expediter

    E. Classical/traditional


    正确答案:B

  • 第17题:

    118 Which of the following would most likely not be an essential objective of a project team kick-off meeting

    A. Create a project technology master plan

    B. Get team members to know one another

    C. Identify project problem areas

    D. Obtain individual and group commitments

    E. Identify the project coordinator


    正确答案:A

  • 第18题:

    86 Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?

    A. Matrix

    B. Pure project

    C. Project coordinator

    D. Project expediter

    E. Classical/traditional


    正确答案:B

  • 第19题:

    ● The scope baseline/project charter is prepared by the:

    A Project manager

    B Project manager and project office

    C Project manager, project office and functional team

    D Project manager, project office, functional team and project sponsor

    E Project manager, project sponsor and customer/user


    正确答案:E

  • 第20题:

    The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false.

    A. The communication management plan is contained in or is a subsidiary plan of, the project management plan.

    B. The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the project.

    C. The communication manamgement plan organize and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.

    D. The communication management plan can include guidelines project status meetings,project team meetings,e-meetines,and e-mail


    参考答案:C
    沟通管理计划用于确定项目千系人的信息需求和沟通方法,以下关于沟通管理计划的叙述中,错误的是:沟通管理计划定期收集、对比和分析基准与实际数据,以便了解和沟通项目进展与绩效情况。 A:沟通管理计划是项目管理计划的一部分或子计划 B:沟通管理计划可以根据项目需求是正式或非正式的、非常详细或高度概括的。 C:沟通管理计划定期收集、对比和分析基准与实际数据,以便了解和沟通项目进展与绩效情况。 D:沟通管理计划可包括关于状态会议、项目团队回忆、网络会议和电子邮件等的指南。

  • 第21题:

    In order to facilitate configuration and change management, manual or automated tools maybe used. Tools selection should be based on the needs of the( ).

    A. Project manager
    B.CCB.members
    C.Project stakeholders
    D. Project Management Office(PMO)

    答案:C
    解析:
    翻译:为了便于实施配置和变更管理,会使用到一些手工或者自动工具,工具的选择取决于项目干系人的需要。A.项目经理 B.变更委员会成员 C.项目干系人 D.项目管理办公室

  • 第22题:

    The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false.

    A.The communication management plan is contained in or is A.subsidiary plan of, the project management plan.
    B.The communication management plan can be formal or informal, highly detaileD.or broadly framed, and based on the needs of the project.
    C.The communication manamgement plan organize and summarize the information gathered, and present the results of any analysis as comparedthe performance measurement baseline.
    D.The communication management plan can include guidelines project status meetings, project team meetings, e-meetines, and e-mail.


    答案:C
    解析:
    沟通管理计划用于确定项目干系人的信息需求和沟通方法,以下关于沟通管理计划的叙述中,错误的是:沟通管理计划定期收集、对比和分析基准与实际数据,以便了解和沟通项目进展与绩效情况。A.沟通管理计划是项目管理计划的一部分或子计划 B.沟通管理计划可以根据项目需求是正式或非正式的、非常详细或高度概括的C.沟通管理计划定期收集、对比和分析基准与实际数据,以便了解和沟通项目进展与绩效情况。D.沟通管理计划可包括关于状态会议、项目团队回忆、网络会议和电子邮件等的指南。

  • 第23题:

    Which is the MOST effective method for generating support for your project plan?()

    • A、Requiring stakeholders to sign-off on project plan components
    • B、Requesting input from all stakeholders during the planning process
    • C、Providing an open line of communication regarding the project
    • D、Clearly illustrating how the project relates to the company’s objectives

    正确答案:B