38 A calendar that identifies when a project may be performed on an activity is called a:A. Project calendar.B. Resource calendar.C. Milestone point.D. Key point.E. Work unit

题目

38 A calendar that identifies when a project may be performed on an activity is called a:

A. Project calendar.

B. Resource calendar.

C. Milestone point.

D. Key point.

E. Work unit


相似考题
更多“38 A calendar that identifies when a project may be performed on an activity is called a:A. Project calendar.B. Resource calendar.C. Milestone point.D. Key point.E. Work unit”相关问题
  • 第1题:

    118 A project element which lies between two events is called:

    A. An activity.

    B. A critical path method.

    C. A slack milestone.

    D. A timing slot.

    E. A calendar completion point


    正确答案:A

  • 第2题:

    171 Documented work authorization provide:

    A. a means of effective internal coordination of the project's activities.

    B. an audit trail of all work authorized from project initiation to completion

    C.a means for communication of work activity between the project manager and the performing activities.

    D. All of the above

    E. A and B only


    正确答案:D

  • 第3题:

    120 A calendar that identifies when a project may be performed on an activity is called a:

    A. Project calendar.

    B. Resource calendar.

    C. Milestone point.

    D. Key point.

    E. Work unit


    正确答案:A

  • 第4题:

    ● Increasing resources on the critical path activities may not always shorten the length of the project because:

    A Certain activities are time-dependent rather than resource-dependent (i.e., using three ovens rather than one to bake a cake).

    B Safety, OSHA and EPA may have placed restrictions on the number of people used on certain activities or in the physical location of the project.

    C The skill level of the added resources might not be appropriate for the activities to be performed.

    D Adding more resources may create additional work and produce inefficiencies (i.e., additional people may need training and supervision.)

    E All of the above.


    正确答案:E

  • 第5题:

    Define Activities is the process of identifying the specific actions to be performed to produce the (71).

    A.project elements

    B.work drafts

    C.work package

    D.project deliverables


    正确答案:D
    解析:活动定义过程识别是为了生产项目的可交付物而必须执行的具体活动。

  • 第6题:

    ● Define Activities is the process of identifying the specific actions tobe performed to produce the (71).

    (71)

    A. project elements

    B. work drafts

    C. work package

    D. project deliverables


    正确答案:D

  • 第7题:

    A key activity in closing out a project is to(47).

    A.Disseminate status reports and risk assessment.

    B.Disseminate information to formalize project completion.

    C.Monitor the specific project results to determine if they comply with relevant quality standards.

    D.Transfer all the project records to the project owners.


    正确答案:B
    解析:项目收尾时的一个关键活动是发布消息以正式确认项目完工。

  • 第8题:

    In project time management, activity definition is the process of identifying and documenting the specific action to be performed to produce the project deliverables. ()are not output of activity definition.

    A.Activity list

    B.Work Breakdown Structures

    C.Activity Attributes

    D.Milestone Lists


    正确答案:B

  • 第9题:

    In project time management,activity definition is the process of identifying and documenting the specification to be performed to produce the project deliverables.( )are not output of activity definition.

    A.Activity list
    B.Work Break down Structures
    C.Activity Attributes
    D.Mile stone Lists

    答案:B
    解析:
    翻译:在项目管理中,活动定义是识别和记录项目可交付物而采取的具体行动的过程。( )不是活动定义的输出。A.活动清单 B.工作分解结构 C.活动属性 D.里程碑清单

  • 第10题:

    Define Activities is the process of identifying the specific actions to be performed to produce the ( ) .

    A.project elements
    B.work drafts
    C.work package
    D.project deliverables

    答案:D
    解析:

  • 第11题:

    Estimating activity
    durations uses information on activity scope of ( ) , required resource types, estimated
    resource quantities, and resource calendars.

    A.milestone
    B. baseline
    C.quality
    D. work

    答案:D
    解析:

  • 第12题:

    Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

    • A、activity duration estimating, schedule developing, activity resource estimating
    • B、activity resource estimating, activity duration estimating, schedule development
    • C、schedule developing, activity resource estimating, activity duration estimating
    • D、activity resource estimating, schedule developing, activity duration estimating

    正确答案:B

  • 第13题:

    135 Increasing resources on the critical path activities may not always shorten the length of the project because:

    A. Certain activities are time-dependent rather than resource-dependent (i.e., using three ovens rather than one to bake a cake).

    B. Safety, OSHA and EPA may have placed restrictions on the number of people used on certain activities or in the physical location of the project.

    C. The skill level of the added resources might not be appropriate for the activities to be performed. D. Adding more resources may create additional work and produce inefficiencies (i.e., additional people may need training and supervision.)

    E. All of the above


    正确答案:E

  • 第14题:

    53 Documented work authorization provide:

    A. a means of effective internal coordination of the project's activities.

    B. an audit trail of all work authorized from project initiation to completion.

    C. a means for communication of work activity between the project manager and the performing activities.

    D. All of the above

    E. A and B only


    正确答案:D

  • 第15题:

    ● Documented work authorization provide:

    A a means of effective internal coordination of the project's activities.

    B an audit trail of all work authorized from project initiation to completion.

    C a means for communication of work activity between the project manager and the performing activities.

    D All of the above

    E A and B only.


    正确答案:D

  • 第16题:

    ● A calendar that identifies when a project may be performed on an activity is called a:

    A Project calendar.

    B Resource calendar.

    C Milestone point.

    D Key point.

    E Work unit.


    正确答案:A

  • 第17题:

    Project work packages are typically decomposed into smaller components called activities to provide a basis for (72) ,scheduling, executing, and monitoring and controlling the project work.

    A.reviewing

    B.estimating

    C.auditing

    D.expecting


    正确答案:B
    解析:把项目工作包分解成更小的结构称为活动的单元,为估算、进度安排、项目执行、项目监控提供了基础。

  • 第18题:

    ● Project work packages are typically decomposed into smaller components called activities to provide a basis for (72), scheduling, executing, and monitoring and controlling the project work.

    (72)

    A. reviewing

    B. estimating

    C. auditing

    D. expecting


    正确答案:B

  • 第19题:

    On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and (71) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

    A.project planning

    B.time estimating

    C.cost estimating

    D.schedule development


    正确答案:D

  • 第20题:

    On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and(70)are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

    A.time estimating

    B.cost estimating

    C.project planning

    D.schedule development


    正确答案:D
    解析:在某些项目,特别是在范围较小的项目中,活动排序、活动资源估算、活动历时估算和进度制定连接得如此紧密,以至于它们被视为可以由一个人在相对较短的时间内执行的单独过程。

  • 第21题:

    In project management and systems engineering,( )is a deliverable-oriented breakdown of a project into smaller components.It is a key project deliverable that organizes the team's work into manageable sections.

    A.RBS
    B.PBS
    C.GBS
    D.WBS

    答案:D
    解析:
    在项目管理和系统工程中,WBS是将项目分解为更小的组件的可交付成果。这是一个重要的项目交付成果,将团队的工作组织到可管理的部分。

  • 第22题:

    Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level.

    A.independent resource
    B.individual work loaD.
    C.work milestone
    D.work package

    答案:D
    解析:
    WBS(工作分解结构)是面向可交付物的层次性分析结构,是对完成项目目标、创造可交付物所需执行的项目工作的分解。WBS把项目工作细分为更小、更易管理的工作单元,随着WBS层次的降低,意味着项目工作也越来越详细,直到工作包(work package)的层次。
    (75) A.独立资源 B.个人工作负荷 C.工作里程碑 D.工作包

  • 第23题:

    On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

    • A、time estimating
    • B、cost estimating
    • C、project planning
    • D、schedule development

    正确答案:C