38 A calendar that identifies when a project may be performed on an activity is called a:
A. Project calendar.
B. Resource calendar.
C. Milestone point.
D. Key point.
E. Work unit
第1题:
118 A project element which lies between two events is called:
A. An activity.
B. A critical path method.
C. A slack milestone.
D. A timing slot.
E. A calendar completion point
第2题:
171 Documented work authorization provide:
A. a means of effective internal coordination of the project's activities.
B. an audit trail of all work authorized from project initiation to completion
C.a means for communication of work activity between the project manager and the performing activities.
D. All of the above
E. A and B only
第3题:
120 A calendar that identifies when a project may be performed on an activity is called a:
A. Project calendar.
B. Resource calendar.
C. Milestone point.
D. Key point.
E. Work unit
第4题:
● Increasing resources on the critical path activities may not always shorten the length of the project because:
A Certain activities are time-dependent rather than resource-dependent (i.e., using three ovens rather than one to bake a cake).
B Safety, OSHA and EPA may have placed restrictions on the number of people used on certain activities or in the physical location of the project.
C The skill level of the added resources might not be appropriate for the activities to be performed.
D Adding more resources may create additional work and produce inefficiencies (i.e., additional people may need training and supervision.)
E All of the above.
第5题:
Define Activities is the process of identifying the specific actions to be performed to produce the (71).
A.project elements
B.work drafts
C.work package
D.project deliverables
第6题:
● Define Activities is the process of identifying the specific actions tobe performed to produce the (71).
(71)
A. project elements
B. work drafts
C. work package
D. project deliverables
第7题:
A key activity in closing out a project is to(47).
A.Disseminate status reports and risk assessment.
B.Disseminate information to formalize project completion.
C.Monitor the specific project results to determine if they comply with relevant quality standards.
D.Transfer all the project records to the project owners.
第8题:
In project time management, activity definition is the process of identifying and documenting the specific action to be performed to produce the project deliverables. ()are not output of activity definition.
A.Activity list
B.Work Breakdown Structures
C.Activity Attributes
D.Milestone Lists
第9题:
第10题:
第11题:
第12题:
Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.
第13题:
135 Increasing resources on the critical path activities may not always shorten the length of the project because:
A. Certain activities are time-dependent rather than resource-dependent (i.e., using three ovens rather than one to bake a cake).
B. Safety, OSHA and EPA may have placed restrictions on the number of people used on certain activities or in the physical location of the project.
C. The skill level of the added resources might not be appropriate for the activities to be performed. D. Adding more resources may create additional work and produce inefficiencies (i.e., additional people may need training and supervision.)
E. All of the above
第14题:
53 Documented work authorization provide:
A. a means of effective internal coordination of the project's activities.
B. an audit trail of all work authorized from project initiation to completion.
C. a means for communication of work activity between the project manager and the performing activities.
D. All of the above
E. A and B only
第15题:
● Documented work authorization provide:
A a means of effective internal coordination of the project's activities.
B an audit trail of all work authorized from project initiation to completion.
C a means for communication of work activity between the project manager and the performing activities.
D All of the above
E A and B only.
第16题:
● A calendar that identifies when a project may be performed on an activity is called a:
A Project calendar.
B Resource calendar.
C Milestone point.
D Key point.
E Work unit.
第17题:
Project work packages are typically decomposed into smaller components called activities to provide a basis for (72) ,scheduling, executing, and monitoring and controlling the project work.
A.reviewing
B.estimating
C.auditing
D.expecting
第18题:
● Project work packages are typically decomposed into smaller components called activities to provide a basis for (72), scheduling, executing, and monitoring and controlling the project work.
(72)
A. reviewing
B. estimating
C. auditing
D. expecting
第19题:
On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and (71) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.project planning
B.time estimating
C.cost estimating
D.schedule development
第20题:
On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and(70)are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.time estimating
B.cost estimating
C.project planning
D.schedule development
第21题:
第22题:
第23题:
On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.