111 Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:
A. All activities.
B. Only those activities with the longest time durations.
C. Those activities on the critical path begining with the longest time duration activities.
D. Those activities with the greatest degree of risk.
E. None of the above