10 The project manager must be concerned with building a closely knit team. During the project kickoff meeting, the project manager can get a good start at team building by providing the team with: A. Proposed salary increases if the project is successful

题目

10 The project manager must be concerned with building a closely knit team. During the project kickoff meeting, the project manager can get a good start at team building by providing the team with: A. Proposed salary increases if the project is successful

B. Bonuses for early completion date

C. A promise of future assignments

D. Well-defined project objectives

E. Linear responsibility charts


相似考题
更多“10 The project manager must be concerned with building a closely knit team. During the project kickoff meeting, the project manager can get a good start at team building by providing the team with: A. Proposed salary increases if the project is successful”相关问题
  • 第1题:

    Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?

    A . Matrix

    B . Pure project

    C . Project coordinator

    D . Project expediter

    E . Classical/traditional


    正确答案:B

  • 第2题:

    A project manager recently rewarded an individual with a promotion that carried with it a very small salary increase but substantially more responsibility. The project manager appears to be appealing to the employee's _____ need.

    A Monetary

    B Physiological

    C Esteem

    D Self-actualization

    E Team-building


    正确答案:C

  • 第3题:

    A project manager can exchange information with the project team using which media?

    A tactile

    B audio

    C olfactory

    D visual

    E All of the above.


    正确答案:E

  • 第4题:

    84 Risk management allows the project manager and the project team to:

    A. eliminate most risks during the planning phase of the project

    B. identify project risks

    C. identify impacts of various risks

    D. plan suitable responses

    E. B, C and D only


    正确答案:E

  • 第5题:

    128 The project manager must be concerned with building a closely knit team. During the project kickoff meeting, the project manager can get a good start at team building by providing the team with:

    A. Proposed salary increases if the project is successful

    B. Bonuses for early completion date

    C. A promise of future assignments

    D. Well-defined project objectives

    E. Linear responsibility charts


    正确答案:D

  • 第6题:

    155 A project manager can exchange information with the project team using which media?

    A. tactile

    B. audio

    C. olfactory

    D. visual

    E. All of the above


    正确答案:E

  • 第7题:

    108 In which type of organization is team building likely to be most difficult?

    A. Functional

    B. Projectized

    C. Matrixed

    D. Project expediter

    E. Project coordinator


    正确答案:C

  • 第8题:

    86 Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?

    A. Matrix

    B. Pure project

    C. Project coordinator

    D. Project expediter

    E. Classical/traditional


    正确答案:B

  • 第9题:

    ● The scope baseline/project charter is prepared by the:

    A Project manager

    B Project manager and project office

    C Project manager, project office and functional team

    D Project manager, project office, functional team and project sponsor

    E Project manager, project sponsor and customer/user


    正确答案:E

  • 第10题:

    Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses


    正确答案:A
    风险管理并不能使得项目经理及其团队在项目的规划过程中避免大多数的风险。

  • 第11题:

    Risk management allows the project manager and the project team not to (71).

    A.eliminate most risks during the planning phase of the project

    B.identify project risks

    C.identify impacts of various risks

    D.plan suitable responses


    正确答案:A

  • 第12题:

    The project manager must maintain an effective communication link with the customer'ssatisfaction with the progress of the project.The project manager maintains this link through( ).

    A.periodic project reports,periodic visits to the customer,and telephonic exchanges
    B.subordinates,project team members,and the project sponsor
    C.one-time reports,weekly reports,and monthly reports
    D.the telephone,facsimile,and data transmission

    答案:A
    解析:
    项目经理必须保持一个有效的沟通,项目经理保持这个环节,通过与客户的项目定期报告,定期走访客户和电话交流。

  • 第13题:

    The project manager must be concerned with building a closely knit team. During the project kickoff meeting, the project manager can get a good start at team building by providing the team with:

    A . Proposed salary increases if the project is successful

    B . Bonuses for early completion date

    C . A promise of future assignments

    D . Well-defined project objectives

    E . Linear responsibility charts


    正确答案:D

  • 第14题:

    An effective Project Manager does not share project _____ with the team members.

    A Vision

    B responsibility

    C solution to problems

    D accountability

    E status


    正确答案:D

  • 第15题:

    A project manager trying to communicate accurately to the team should use:

    A the language of the team members

    B the language of the project manager

    C non-verbal methods

    D written memos

    E All of the above.


    正确答案:A

  • 第16题:

    126 A project manager recently rewarded an individual with a promotion that carried with it a very small salary increase but substantially more responsibility. The project manager appears to be appealing to the employee's _____ need.

    A. Monetary

    B. Physiological

    C. Esteem

    D. Self-actualization

    E. Team-building


    正确答案:C

  • 第17题:

    145 Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:

    A. The project manager and project office personnel.

    B. The project team and functional managers.

    C. The project sponsor.

    D. All of the above.

    E. A and B only


    正确答案:E

  • 第18题:

    4 Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?

    A. Matrix

    B Pure project

    C. Project coordinator

    D. Project expediter

    E. Classical/traditional


    正确答案:B

  • 第19题:

    123 The scope baseline/project charter is prepared by the:

    A. Project manager

    B. Project manager and project office

    C. Project manager, project office and functional team

    D. Project manager, project office, functional team and project sponsor

    E. Project manager, project sponsor and customer/user


    正确答案:E

  • 第20题:

    78 Which of the following can the project manager use as a means of measuring project team effectiveness?

    A. Absenteeism

    B. Sponsor-approved salary increases

    C. Efficiency of the team

    D. Turnover of personnel

    E. Grievances


    正确答案:C

  • 第21题:

    ● Risk management allows the project manager and the project team not to(71).

    (71)

    A.eliminate most risks during the planning phase of the project

    B.identify project risks

    C.identify impacts of various risks

    D.plan suitable responses


    正确答案:A

    试题(71)分析
      下面不属于风险管理中项目经理和项目团队职责的是  (71)  。
      A.排除大部分项目执行中的风险        B.风险识别
      C.风险分析                          D.妥善处理
    参考答案
    (71)A

  • 第22题:

    ●The project manager must maintain an effective communication link with the customer's satisfaction with the progress of the project. The project manager maintains this link through (71).

    (71)

    A.periodic project reports, periodic visits to the customer, and telephonic exchanges

    B.subordinates, project team members, and the project sponsor

    C.one-time reports, weekly reports, and monthly reports

    D.the telephone, facsimile, and data transmission


    正确答案:A

  • 第23题:

    Risk management allows the project manager and the project team not to()

    A.eliminate most risks during the planning phase of the project
    B.identify project risks
    C.identify impacts of various risks
    D.plan suitable responses

    答案:A
    解析:
    下面不属于风险管理中项目经理和项目团队职责的是(71)。A.排除大部分项目执行中的风险B.风险识别C.风险分析D.妥善处理