185 Life Cycle Costing:A. is the concept of including all costs within the total life of a project.B. is an activity devoted to optimizing cost/performanceC. is an activity of appraising the cost and technical performance of a completed project.D. is a pr

题目

185 Life Cycle Costing:

A. is the concept of including all costs within the total life of a project.

B. is an activity devoted to optimizing cost/performance

C. is an activity of appraising the cost and technical performance of a completed project.

D. is a process of predicting the life of a project.

E. None of the above


相似考题
参考答案和解析
正确答案:A