114 The cost of corrective action taken by the purchaser and chargeable to the supplier under the terms of the contract is:A. Payment authorizationB. Bid cost considerationsC. Release paymentD. Back chargeE. None of the above

题目

114 The cost of corrective action taken by the purchaser and chargeable to the supplier under the terms of the contract is:

A. Payment authorization

B. Bid cost considerations

C. Release payment

D. Back charge

E. None of the above


相似考题
更多“114 The cost of corrective action taken by the purchaser and chargeable to the supplier under the terms of the contract is:A. Payment authorizationB. Bid cost considerationsC. Release paymentD. Back chargeE. None of the above”相关问题
  • 第1题:

    The difference between the BCWS and the BCWP is referred to as the:

    A . Schedule variance

    B . Cost variance.

    C . Estimate of completion

    D . Actual cost of the work performed

    E . None of the above


    正确答案:A

  • 第2题:

    The cost of corrective action taken by the purchaser and chargeable to the supplier under the terms of the contract is:

    A Payment authorization

    B Bid cost considerations

    C Release payment

    D Back charge

    E None of the above.


    正确答案:D

  • 第3题:

    By which process may an unsuccessful supplier seek remedy for unjust awards?

    A Contract dispute

    B Stop work order

    C Bid protest

    D Coffective action

    E None of the above.


    正确答案:C

  • 第4题:

    Back charges refers to:

    A transferring charges from sub-contractors to the owner

    B adjusting payments to reflect late invoices consequence

    C the cost of corrective action taken by the owner and charged to the contractor for non-conformance

    D gaining restitution from the owner for non payment

    E C and D only


    正确答案:C

  • 第5题:

    125 Which of the following types of contracts is equivalent to a cost plus contract:

    A. Fixed firm price

    B. Cost reimbursable

    C. Fixed price plus incentive fee

    D. progress payments

    E. All of the above


    正确答案:B

  • 第6题:

    33 In which of the following contract types is it easier to change the scope of the contract:

    A. firm fixed price

    B. fixed price plus incentive fee

    C. cost plus percentage of cost

    D. letter contract

    E. None of the above


    正确答案:C

  • 第7题:

    106 Cost Reimbursable contracts are equivalent to:

    A. Cost plus contracts

    B. Fixed plus contracts

    C. Progress payment contracts

    D. Back charge contracts

    E. None of the above


    正确答案:A

  • 第8题:

    153 Which is not a consideration in a make or buy decision?

    A. Cost factors (least cost alternatives)

    B. Competitors' method of sourcing

    C. Existence of sufficient administration/technical personnel

    D. Political and social factors

    E. None of the above


    正确答案:B

  • 第9题:

    72 Which of the following is referred to as payback period:

    A. the number of periods required to recover the initial investment

    B. the rate of return on the investment

    C. the number of periods required to bring project cost back to the original budget, based on current performance

    D. loan payment schedule

    E. None of the above


    正确答案:A

  • 第10题:

    100 The difference between the BCWS and the BCWP is referred to as the:

    A. Schedule variance

    B. Cost variance.

    C. Estimate of completion

    D. Actual cost of the work performed

    E. None of the above


    正确答案:A

  • 第11题:

    196 The cost of corrective action taken by the purchaser and chargeable to the supplier under the terms of the contract is:

    A. Payment authorization

    B. Bid cost considerations

    C. Release payment

    D. Back charge

    E. None of the above


    正确答案:D

  • 第12题:

    72 Project trade-offs vary between

    A. risk, cost and schedule.

    B. direct cost, indirect cost, and resource availability

    C. quality, schedule and time

    D. cost, quality and schedule

    E. contract terms, scope and budget


    正确答案:D

  • 第13题:

    _____ is a method of procurement where a contract results from a bid which may be changed through bargaining.

    A Acquisition

    B Contract negotiation

    C Procurement

    D Purchase negotiation

    E None of the above.


    正确答案:B

  • 第14题:

    Cost Reimbursable contracts are equivalent to:

    A Cost plus contracts

    B Fixed plus contracts

    C Progress payment contracts

    D Back charge contracts

    E None of the above.


    正确答案:A

  • 第15题:

    In which of the following contract types is it easier to change the scope of the contract:

    A firm fixed price

    B fixed price plus incentive fee

    C cost plus percentage of cost

    D letter contract

    E None of the above.


    正确答案:C

  • 第16题:

    Which of the following types of contracts is equivalent to a cost plus contract:

    A Fixed firm price

    B Cost reimbursable

    C Fixed price plus incentive fee

    D progress payments

    E All of the above.


    正确答案:B

  • 第17题:

    9 Back charges refers to:

    A. transferring charges from sub-contractors to the owner

    B. adjusting payments to reflect late invoices consequence

    C. the cost of corrective action taken by the owner and charged to the contractor for non-conformance D. gaining restitution from the owner for non payment

    E. C and D only


    正确答案:C

  • 第18题:

    75 By which process may an unsuccessful supplier seek remedy for unjust awards?

    A. Contract dispute

    B. Stop work order

    C. Bid protest

    D. Coffective action

    E. None of the above


    正确答案:C

  • 第19题:

    131 _____ is a method of procurement where a contract results from a bid which may be changed through bargaining.

    A. Acquisition

    B. Contract negotiation

    C. Procurement

    D. Purchase negotiation

    E. None of the above


    正确答案:B

  • 第20题:

    18 The difference between the BCWS and the BCWP is referred to as the:

    A. Schedule variance

    B Cost variance.

    C. Estimate of completion

    D. Actual cost of the work performed

    E. None of the above


    正确答案:A

  • 第21题:

    79 Under the terms of 2/10 net 30, the buyer may:

    A. deduct 10% of the invoice amount for payment within 30 days

    B. deduct 2% of the invoice for payment within 10 days

    C. incurs a penalty on 10% for payments more than 30 days late

    D. settle the invoice with 2 equal payments; one within 10 days and the other within 30 days

    E. None of the above


    正确答案:B

  • 第22题:

    115 In which of the following contract types is it easier to change the scope of the contract:

    A. firm fixed price

    B. fixed price plus incentive fee

    C. cost plus percentage of cost

    D. letter contract

    E. None of the above.


    正确答案:C

  • 第23题:

    44 The estimated cost to complete (ETC) is _____.

    A. BCWP/ACWP

    B. the forecasted and final cost - cost to date

    C. (ACWP-BCWP)/BCWP * 100

    D. Total estimate - ACWP

    E. None of the above


    正确答案:B