更多“113 Screening of risk events for potential risk is known as _____ .A. problem structuring.B. risk identificationC. risk quantificationD. risk modelingE. risk mitigation”相关问题
  • 第1题:

    Which of the following actions is an example of risk response:

    A adjust project parameters (scope, time, quality ...)

    B reduce the probability of potential project risk events

    C reduce the consequences of potential project risk events

    D wait until a problem actually happens, then deal with it in the most effective and efficient manner.

    E A, B and C only


    正确答案:E

  • 第2题:

    15 Total project risk can be defined as:

    A. the sum of the probabilities of project risks events times the sum of consequences of those risks

    B. the sum of the products of each project risk event times its consequences

    C. the sum of the consequences of all project risk events

    D. the sum of the probabilities of all project risk events

    E. 1 - the sum of the probabilities of all project risk events


    正确答案:B

  • 第3题:

    125 In Project Risk Management, Risk Response may include actions to:

    A. reduce the probability of risk events

    B. change the scope, budget, schedule or quality specifications of the project

    C. reduce the consequences or severity of impacts of a potential risk event

    D. A and C

    E. All of the above


    正确答案:E

  • 第4题:

    170 Project Risk _____ .

    A. should not be calculated for small projects.

    B. is the probability of each risk event minus the sum of the consequences of potential risk events.

    C. is the cumulative effect of uncertain occurrences which will adversely affect project objectives.

    D. cannot be quantified for first time projects.

    E. B or D


    正确答案:C

  • 第5题:

    195 Screening of risk events for potential risk is known as _____ .

    A. problem structuring.

    B. risk identification

    C. risk quantification

    D. risk modeling

    E. risk mitigation


    正确答案:B

  • 第6题:

    26 Risk mitigation is the process of _____ .

    A. transferring risk to another party.

    B. reducing uncertainty on the project

    C. identifying all possible risk events

    D. monitoring status and making adjustments

    E. All of the above.


    正确答案:B

  • 第7题:

    A situation in which one of two or more risk events will follow an act, but the precise nature of these events may

    not be known and the probabilities of their occurring cannot be objectively assigned, is the definition of:

    a. Certainty

    b. Uncertainty

    c. Risk

    d. Risk adversity

    e. None of the above


    正确答案:B
        b [见学习手册,确定因素、风险、不确定因素的定义章节。]

  • 第8题:

    The______process ascertains which risks have the potential Of affecting the proect and documenting the risks' characteristics.

    A.Risk Identification

    B.Quantitative Risk Analysis

    C.Qualitative Risk Analysis

    D.Risk Monitoring and Control


    正确答案:A
    解析:项目风险管理主要包括风险管理计划编制、风险识别、定性风险分析、定量风险分析、风险应对计划编制和风险监控。其中,风险识别过程是确定哪些风险可能会对项目产生影响,并将这些风险的特征形成文档。选项A是风险识别,选项B是定量风险分析,选项C是定性风险分析,选项D是风险监控。

  • 第9题:

    () can be considered as part of risk mitigation.

    A.Risk identification
    B.Purchasing insurance
    C.Assessment of outcomes
    D.Assessment of probabilities

    答案:D
    解析:
    ()可以被认为是风险缓解的一部分。A、风险识别B、购买保险C、成果评估D、概率评估注意题干中:as part of.

  • 第10题:

    The ( ) process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.

    A.Risk Identification
    B.Quantitative Risk Analysis
    C.Qualitative Risk Analysis
    D.Risk Monitoring anD.Control

    答案:A
    解析:
    项目风险管理主要包括风险管理计划编制、风险识别、定性风险分析、定量风险分析、风险应对计划编制和风险监控。其中,风险识别过程是确定哪些风险可能会对项目产生影响,并将这些风险的特征形成文档。
    A.风险识别 B.定量风险分析 C.定性风险分析 D.风险检测与控制

  • 第11题:

    The()process analyzes the effect of risk events and assigns a numerical rating to those risks.

    • A、Risk Identification
    • B、Quantitative Risk Analysis
    • C、Qualitative Risk Analysis
    • D、Risk Monitoring and Control

    正确答案:B

  • 第12题:

    单选题
    The()process analyzes the effect of risk events and assigns a numerical rating to those risks.
    A

    Risk Identification

    B

    Quantitative Risk Analysis

    C

    Qualitative Risk Analysis

    D

    Risk Monitoring and Control


    正确答案: C
    解析: 暂无解析

  • 第13题:

    Total project risk can be defined as:

    A the sum of the probabilities of project risks events times the sum of consequences of those risks

    B the sum of the products of each project risk event times its consequences

    C the sum of the consequences of all project risk events

    D the sum of the probabilities of all project risk events

    E 1 - the sum of the probabilities of all project risk events.


    正确答案:B

  • 第14题:

    23 Which of the following actions is an example of risk response:

    A. adjust project parameters (scope, time, quality ...)

    B. reduce the probability of potential project risk events C. reduce the consequences of potential project risk events

    D. wait until a problem actually happens, then deal with it in the most effective and efficient manner.

    E. A, B and C only


    正确答案:E

  • 第15题:

    144 Risk event probability is defined as:

    A. the total number of possible events divided into the expectations or frequency of the risk event

    B. the number of times the risk event may occur

    C. the fraction of the total project tasks which may be affected by the risk event

    D. the total number of possible events divided into the consequences of the risk event.

    E. A and B


    正确答案:A

  • 第16题:

    In Project Risk Management, Risk Response may include actions to:

    A. reduce the probability of risk events

    B. change the scope, budget, schedule or quality specifications of the project

    C. reduce the consequences or severity of impacts of a potential risk event

    D. A and C

    E. All of the above


    正确答案:E

  • 第17题:

    105 Which of the following actions is an example of risk response:

    A. adjust project parameters (scope, time, quality ...)

    B. reduce the probability of potential project risk events

    C. reduce the consequences of potential project risk events

    D. wait until a problem actually happens, then deal with it in the most effective and efficient manner.

    E. A, B and C only


    正确答案:E

  • 第18题:

    108 Risk mitigation is the process of _____ .

    A. transferring risk to another party.

    B. reducing uncertainty on the project

    C. identifying all possible risk events

    D. monitoring status and making adjustments

    E. All of the above


    正确答案:B

  • 第19题:

    The()process analyzes the effect of risk events and assigns a numerical rating to those risks.()A.Risk Identification B.Quantitative Risk AnalysisC.Qualitative Risk Analysis D.Risk Monitoring and Control


    正确答案:B
    定量风险分析过程分析风险事件的影响并对这些影响赋予一个数值化的评价。

  • 第20题:

    The(75)process analyzes the effect of risk events and assigns a numerical rating to those risks.

    A.Risk Identification

    B.Quantitative Risk Analysis

    C.Qualitative Risk Analysis

    D.Risk Monitoring and Control


    正确答案:B
    解析:定量风险分析过程分析风险事件的影响并对这些风险赋予一个数值化的评价。

  • 第21题:

    setting redundant components in subsystem to handle with the risks brought by the defaults of original components,what kind of risk response strategy is this? ( ) .

    A.risk avoidance
    B.risk acceptance
    C.risk mitigation
    D.contingency plan

    答案:C
    解析:
    翻译:为子系统设置冗余组件处理原系统带来的风险,是一种什么样的风险应对策略?A.风险规避 B.风险接受C.风险减轻 D.应急计划冗余减少了风险发生概率,属于风险减轻。

  • 第22题:

    The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.

    • A、Riskldentification
    • B、Quantitative Risk Analysis
    • C、Qualitative Risk Analysis
    • D、Risk Monitoring and Control

    正确答案:A

  • 第23题:

    ( )can be considered as part of risk mitigation.

    • A、Risk identification
    • B、Purchasing insurance
    • C、Assessment of outcomes
    • D、Assessment of probabilities

    正确答案:D