60 "Fast-tracked" projects awarded and begun before all planning and risk assessment information is complete and available may _____ .

A. be completed in reduced overall time than other projects.

B. be in a higher risk category than other projects.

C. not be compatible with project risk and assessment

D. A and B

E. All of the above