● Project life cycles are very useful for _____ and _____ .A Configuration management, terminationB Objective setting, information gatheringC Standardization, controlD Configuration management, weekly status updatesE Approval, termination

题目

● Project life cycles are very useful for _____ and _____ .

A Configuration management, termination

B Objective setting, information gathering

C Standardization, control

D Configuration management, weekly status updates

E Approval, termination


相似考题
更多“● Project life cycles are very useful for _____ and _____ .A Configuration management, terminationB Objective setting, information gatheringC Standardization, controlD Configuration management, weekly status updatesE Approval, termination”相关问题
  • 第1题:

    126 Researching, organizing and recording pertinent information is called:

    A. Alternative analysis

    B. Information gathering

    C. Configuration management

    D. Post project analysis

    E. All of the above


    正确答案:B

  • 第2题:

    147 Project life cycles are very useful for _____ and _____ .

    A. Configuration management, termination

    B. Objective setting, information gathering

    C. Standardization, control

    D. Configuration management, weekly status updates

    E. Approval, termination


    正确答案:C

  • 第3题:

    ● Researching, organizing and recording pertinent information is called:

    A Alternative analysis

    B Information gathering

    C Configuration management

    D Post project analysis

    E All of the above


    正确答案:B

  • 第4题:

    The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false.

    A. The communication management plan is contained in or is a subsidiary plan of, the project management plan.

    B. The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the project.

    C. The communication manamgement plan organize and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.

    D. The communication management plan can include guidelines project status meetings,project team meetings,e-meetines,and e-mail


    参考答案:C
    沟通管理计划用于确定项目千系人的信息需求和沟通方法,以下关于沟通管理计划的叙述中,错误的是:沟通管理计划定期收集、对比和分析基准与实际数据,以便了解和沟通项目进展与绩效情况。 A:沟通管理计划是项目管理计划的一部分或子计划 B:沟通管理计划可以根据项目需求是正式或非正式的、非常详细或高度概括的。 C:沟通管理计划定期收集、对比和分析基准与实际数据,以便了解和沟通项目进展与绩效情况。 D:沟通管理计划可包括关于状态会议、项目团队回忆、网络会议和电子邮件等的指南。

  • 第5题:

    The communication management plandetermines the information and communications needs of the stakeholders. In thefollowing statements related to communication management plan, (73) is false.

    A.The communication management plan is contained in, or is a subsidiary plan of, the project management plan

    B.The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the project

    C.The communication management plan organize and summarize the information gathered, and present the results of any analysis as compared to the performance measurement baseline

    D.The communication management plan can include guidelines for project status meetings, project team meetings, e-meetings, and e-mails


    正确答案:C
    沟通管理计划确定的利益相关者的信息和通信需求。在下列相关沟通管理计划的描述中,(73)是错误的。沟通管理计划包于项目管理计划的子计划。沟通管理计划根据项目的需要可以是正式的或非正式的,非常详细的,或大致框架。沟通管理计划组织并概括收集到的信息,并提交任何可供分析的结果作为绩效测量基准。沟通管理计划可以包括项目状态会议,项目小组会议,电子会议,电子邮件的指引。

  • 第6题:

    The Perform. Integrated Change Control process is conducted from project lnception through completion and is the ultimate responsibility of the(75)

    A.change control board

    B. project management office

    C.project manager

    D.configuration management officer


    正确答案:C
    本题目翻译:实施整体变更控制过程是从项目开始到完成进行,是项目经理的摄终责任。考察的是整体变更管理。

  • 第7题:

    The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) .

    A.Chang control board
    B.Project management office
    C.Project manager
    D.Configuration management officer

    答案:C
    解析:
    实施整体变更控制过程是从项目开始到项目结束并且是项目经理的最终责任。

  • 第8题:

    ()describes the configurable items of the project and identifies itcms that will be recorded and updated so that the product of the project tins consistent and operable
    A.The configuration management plan
    B.The change management plan
    C.The requirements traceability matrix
    D.The change baseline


    答案:A
    解析:
    配置管理计划描述了项目的可配置项,并确定了将被记录和更新的项,以便项目的产品保持一致性和可操作性。

  • 第9题:

    Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes. ( ) is not a project configuration management tool

    A.Rational Clearcase
    B.Quality Function Deployment
    C.Visual SourceSafe
    D.Concurrent Versions System

    答案:B
    解析:
    配置管理的目的在于运用配置标识、配置控制、配置状态统计和配置审计,建立和维护工作产品的完整性。常用的配置管理工具有Visual SourceSafe、Rational Clearcase,以及Concurrent Versions System等。

  • 第10题:

    Software configuration management(SCM)is the task of tracking and controlling changes in the software. Configuration management practices include configuration identification,change control, ( ) and configuration audit.

    A.milestones marking
    B.status reporting
    C.stakeholder management
    D.quality audit

    答案:B
    解析:
    软件配置管理(SCM)是一种跟踪和控制软件的变化的技术。配置管理包括配置标识、变更控制、状态报告和配置审计。

  • 第11题:

    The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false.

    • A、The communication management plan is contained in or is a subsidiary plan of, the project management plan.
    • B、The  communication  management  plan  can  be  formal  or informal, highly detailed or broadly framed, and based on the needs of the project.
    • C、The  communication  manamgement  plan  organize  and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.
    • D、The communication management plan can include guidelines project status meetings,project team meetings,e-meetines,and e-mail

    正确答案:C

  • 第12题:

    Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.

    • A、RationalClearcase
    • B、QualityFunctionDeployment
    • C、VisualSourceSafe
    • D、ConcurrentVersions System

    正确答案:B

  • 第13题:

    Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.

    A.RationalClearcase

    B.QualityFunctionDeployment

    C.VisualSourceSafe

    D.ConcurrentVersions System


    参考答案:B

  • 第14题:

    ● The initial document that formally recognizes the existence of a project is the _____ .

    A Scope baseline

    B Management plan

    C Project charter

    D Configuration control report

    E None of the above


    正确答案:C

  • 第15题:

    ● A comprehensive definition of scope management would be:

    A Managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.

    B Approval of the scope baseline.

    C Approval of the detailed project charter.

    D Configuration control.

    E Approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.


    正确答案:A

  • 第16题:

    Software configuration management(SCM) is the task oftracking and controlling changes in the software. Configuration managementpractices include configuration identification,change control ,(74)and configuration audit.

    A.milstones marking

    B.status reporting

    C.stakeholder management

    D.quality audit


    正确答案:B
    软件配置管理(SCM)的任务是跟踪和控制软件的变化。配置管理实践包括配置标识,变更控制,状态报告和配置审计。

  • 第17题:

    Software configuration management(SCM),is the task of tracking and controiling changes in the software,configuration management practicesconfiguration identirication change control ()and configuration audit

    A.ailestones marking

    B.status reporting

    C.stakeholder management

    D.quality audit


    正确答案:B

  • 第18题:

    In order to facilitate configuration and change management, manual or automated tools maybe used. Tools selection should be based on the needs of the( ).

    A. Project manager
    B.CCB.members
    C.Project stakeholders
    D. Project Management Office(PMO)

    答案:C
    解析:
    翻译:为了便于实施配置和变更管理,会使用到一些手工或者自动工具,工具的选择取决于项目干系人的需要。A.项目经理 B.变更委员会成员 C.项目干系人 D.项目管理办公室

  • 第19题:

    Configuration management is focused on the specification of both the deliverables and the processes;while( )is focused on identifying,documenting,and approving or rejecting changes to the project documents,deliverables,or baselines.

    A.cost management
    B.change management
    C.configuration management
    D.capacity management

    答案:B
    解析:

  • 第20题:

    The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false.

    A.The communication management plan is contained in or is A.subsidiary plan of, the project management plan.
    B.The communication management plan can be formal or informal, highly detaileD.or broadly framed, and based on the needs of the project.
    C.The communication manamgement plan organize and summarize the information gathered, and present the results of any analysis as comparedthe performance measurement baseline.
    D.The communication management plan can include guidelines project status meetings, project team meetings, e-meetines, and e-mail.


    答案:C
    解析:
    沟通管理计划用于确定项目干系人的信息需求和沟通方法,以下关于沟通管理计划的叙述中,错误的是:沟通管理计划定期收集、对比和分析基准与实际数据,以便了解和沟通项目进展与绩效情况。A.沟通管理计划是项目管理计划的一部分或子计划 B.沟通管理计划可以根据项目需求是正式或非正式的、非常详细或高度概括的C.沟通管理计划定期收集、对比和分析基准与实际数据,以便了解和沟通项目进展与绩效情况。D.沟通管理计划可包括关于状态会议、项目团队回忆、网络会议和电子邮件等的指南。

  • 第21题:

    Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes. ( ) is not a project configuration management tool.

    A.Rational Clearcase
    B.Quality Function Deployment
    C.Visual SourceSafe
    D.Concurrent Versions System

    答案:B
    解析:
    配置管理的目的在于运用配置标识、配置控制、配置状态统计和配置审计,建立和维护工作产品的完整性。常用的配置管理工具有Visual SourceSafe、Rational Clearcase,以及Concurrent Versions System等。

  • 第22题:

    ( ) is the process of documenting. Analyzing,tracing,prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders. It is a continuous process throughout a project.

    A.Integrated management
    B.Configuration management
    C.Scope management
    D.Requirements management

    答案:D
    解析:
    需求管理是一个记录的过程。对需求进行分析、描绘、划分优先顺序,达成需求并控制其变化、并传达给利益相关者,它在项目中是一个持续的过程。

  • 第23题:

    Software configuration management (SCM) is the task of tracking and controlling changes in the software. Configuration management practices include configuration identification, change control, ( ) and configuration audit.

    • A、milestones marking
    • B、status reporting
    • C、stakeholder management
    • D、quality audit

    正确答案:B