13 The project team form. of organization confers both advantages and disadvantages. Disadvantages of the project form. include:A. Conflict in authority between project manager and functional managersB. Dual allegiance on part of team members "C. Complex

题目

13 The project team form. of organization confers both advantages and disadvantages. Disadvantages of the project form. include:

A. Conflict in authority between project manager and functional managers

B. Dual allegiance on part of team members "

C. Complex prioritization of resources

D. Loss of developed procedures on project dissolution

E. All of the above


相似考题
更多“13 The project team form. of organization confers both advantages and disadvantages. Disadvantages of the project form. include:A. Conflict in authority between project manager and functional managersB. Dual allegiance on part of team members "C. Complex ”相关问题
  • 第1题:

    Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?

    A . Matrix

    B . Pure project

    C . Project coordinator

    D . Project expediter

    E . Classical/traditional


    正确答案:B

  • 第2题:

    Expectancy theory as applied to project management implies that:

    A The team will work the hardest on those goals that are clearly explained by the project manager

    B The more rewards that the project manager provides, the better the performance of the team

    C Team members will work hardest for those project goals that also bring satisfaction to personal goals

    D Employees will work hardest for those project goals which are accompanied by high levels of authority for the individual team members

    E None of the above


    正确答案:C

  • 第3题:

    When a majority of team members must agree before a decision is reached _____.

    A some team members may become alienated

    B future group effectiveness may become damaged.

    C the PM may lose credibility

    D the project manager will most likely have to utilize a conflict resolution technique

    E All of the above.


    正确答案:E

  • 第4题:

    128 The project manager must be concerned with building a closely knit team. During the project kickoff meeting, the project manager can get a good start at team building by providing the team with:

    A. Proposed salary increases if the project is successful

    B. Bonuses for early completion date

    C. A promise of future assignments

    D. Well-defined project objectives

    E. Linear responsibility charts


    正确答案:D

  • 第5题:

    4 Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?

    A. Matrix

    B Pure project

    C. Project coordinator

    D. Project expediter

    E. Classical/traditional


    正确答案:B

  • 第6题:

    131 The project team form. of organization confers both advantages and disadvantages. Disadvantages of the project form. include:

    A. Conflict in authority between project manager and functional managers

    B. Dual allegiance on part of team members

    C. Complex prioritization of resources

    D. Loss of developed procedures on project dissolution

    E. All of the above


    正确答案:E

  • 第7题:

    38 Expectancy theory as applied to project management implies that:

    A. The team will work the hardest on those goals that are clearly explained by the project manager

    B. The more rewards that the project manager provides, the better the performance of the team

    C. Team members will work hardest for those project goals that also bring satisfaction to personal goals

    D. Employees will work hardest for those project goals which are accompanied by high levels of authority for the individual team members

    E. None of the above


    正确答案:C

  • 第8题:

    64 An effective Project Manager does not share project _____ with the team members.

    A. Vision

    B. responsibility

    C. solution to problems

    D. accountability

    E. status


    正确答案:D

  • 第9题:

    ● The scope baseline/project charter is prepared by the:

    A Project manager

    B Project manager and project office

    C Project manager, project office and functional team

    D Project manager, project office, functional team and project sponsor

    E Project manager, project sponsor and customer/user


    正确答案:E

  • 第10题:

    Your project is behind schedule due to conflict between team members. Having resolved the conflict, to get the project back on schedule, you should consider __(74)__.

    A.crashing the schedule

    B.performing resource leveling

    C.conducting reverse resource allocation scheduling

    D.utilizing the critical chair resources


    正确答案:D
    你的项目由于团队成员之间的冲突而导致进度滞后了,为了解决这种冲突,让项目回到计划进度上来,你应该考虑的是利用临界(应急)资源。

  • 第11题:

    Your project is behind schedule due to conflict between team members. Having resolved the conflict,to get the project back on schedule,you should consider ( ) .

    A.crashing the schedule
    B.performing resource leveling
    C.conducting reverse resource allocation scheduling
    D.utilizing the critical chair resources

    答案:B
    解析:
    由于团队成员之间的冲突,造成了项目进度落后于计划,为了解决冲突以使得项目如期完成你应该考虑。A.重新安排时间表 B.执行资源调配C.进行反向资源分配调度 D.利用关键的主要资源

  • 第12题:

    Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().

    • A、crashing the schedule
    • B、performing resource leveling
    • C、conducting reverse resource allocation scheduling
    • D、utilizing the critical chain resources

    正确答案:A

  • 第13题:

    The project manager must be concerned with building a closely knit team. During the project kickoff meeting, the project manager can get a good start at team building by providing the team with:

    A . Proposed salary increases if the project is successful

    B . Bonuses for early completion date

    C . A promise of future assignments

    D . Well-defined project objectives

    E . Linear responsibility charts


    正确答案:D

  • 第14题:

    An effective Project Manager does not share project _____ with the team members.

    A Vision

    B responsibility

    C solution to problems

    D accountability

    E status


    正确答案:D

  • 第15题:

    156 Expectancy theory as applied to project management implies that:

    A. The team will work the hardest on those goals that are clearly explained by the project manager

    B. The more rewards that the project manager provides, the better the performance of the team

    C. Team members will work hardest for those project goals that also bring satisfaction to personal goals

    D. Employees will work hardest for those project goals which are accompanied by high levels of authority for the individual team members E. None of the above


    正确答案:C

  • 第16题:

    145 Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:

    A. The project manager and project office personnel.

    B. The project team and functional managers.

    C. The project sponsor.

    D. All of the above.

    E. A and B only


    正确答案:E

  • 第17题:

    123 The scope baseline/project charter is prepared by the:

    A. Project manager

    B. Project manager and project office

    C. Project manager, project office and functional team

    D. Project manager, project office, functional team and project sponsor

    E. Project manager, project sponsor and customer/user


    正确答案:E

  • 第18题:

    86 Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?

    A. Matrix

    B. Pure project

    C. Project coordinator

    D. Project expediter

    E. Classical/traditional


    正确答案:B

  • 第19题:

    22 When a majority of team members must agree before a decision is reached _____.

    A. some team members may become alienated

    B. future group effectiveness may become damaged.

    C. the PM may lose credibility

    D. the project manager will most likely have to utilize a conflict resolution technique

    E. All of the above


    正确答案:E

  • 第20题:

    104 When a majority of team members must agree before a decision is reached _____.

    A. some team members may become alienated

    B. future group effectiveness may become damaged.

    C. the PM may lose credibility

    D. the project manager will most likely have to utilize a conflict resolution technique

    E. All of the above.


    正确答案:E

  • 第21题:

    ● Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:

    A The project manager and project office personnel.

    B The project team and functional managers.

    C The project sponsor.

    D All of the above.

    E A and B only.


    正确答案:E

  • 第22题:

    The project manager must maintain an effective communication link with the customer'ssatisfaction with the progress of the project.The project manager maintains this link through( ).

    A.periodic project reports,periodic visits to the customer,and telephonic exchanges
    B.subordinates,project team members,and the project sponsor
    C.one-time reports,weekly reports,and monthly reports
    D.the telephone,facsimile,and data transmission

    答案:A
    解析:
    项目经理必须保持一个有效的沟通,项目经理保持这个环节,通过与客户的项目定期报告,定期走访客户和电话交流。

  • 第23题:

    Within Information Technology projects, communications between the project manager and the project team members should take place:()

    • A、by written and oral communication.
    • B、via a weekly status report.
    • C、through the formal chain of command.
    • D、with approved template forms.

    正确答案:A