112 Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?A. PB. QC. RD. SE. T

题目

112 Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?

A. P

B. Q

C. R

D. S

E. T


相似考题
参考答案和解析
正确答案:A
更多“112 Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?A. PB. QC. RD. SE. T”相关问题
  • 第1题:

    Activities with zero time duration are referred to as:

    A.Critical path activites.

    B.Noncritical path activities.

    C.Slack time activities.

    D.Dummies

    E.None of above.


    正确答案:D
    D

  • 第2题:

    The schedule risk is the _____ .

    A the accumulated "expected' durations which maintain project completion.

    B Critical Path adjusted by "high-risk" activity float.

    C highest risk path that maintains quality.

    D Critical Path when calculated with "most likely" duration.

    E highest risk path that contributes the most risk toward the project completion.


    正确答案:B

  • 第3题:

    82 Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. This will provide information on the _____ and identification of the _____ . A. Slack for each activity, critical path.

    B. Slack for each activity, high risk activities.

    C. Manpower shortages, high risk activities.

    D. High risk activities, non-critical paths.

    E. Manpower availability, contingency plans


    正确答案:A

  • 第4题:

    96 Bar charts are most appropriate for:

    A. Comparing actual to planned performance to each activity.

    B. Showing slack time.

    C. Showing critical path dependencies.

    D. Showing which activities can be rearranged in parallel.

    E. All of the above


    正确答案:A

  • 第5题:

    135 Increasing resources on the critical path activities may not always shorten the length of the project because:

    A. Certain activities are time-dependent rather than resource-dependent (i.e., using three ovens rather than one to bake a cake).

    B. Safety, OSHA and EPA may have placed restrictions on the number of people used on certain activities or in the physical location of the project.

    C. The skill level of the added resources might not be appropriate for the activities to be performed. D. Adding more resources may create additional work and produce inefficiencies (i.e., additional people may need training and supervision.)

    E. All of the above


    正确答案:E

  • 第6题:

    112 The schedule risk is the _____ .

    A. the accumulated "expected' durations which maintain project completion.

    B. Critical Path adjusted by "high-risk" activity float.

    C. highest risk path that maintains quality.

    D. Critical Path when calculated with "most likely" duration.

    E. highest risk path that contributes the most risk toward the project completion


    正确答案:B

  • 第7题:

    101 Using the situation stated in the Special window, which WBS element is behind schedule but under budget?

    A. Element P

    B. Element Q

    C. Element R

    D. Element S

    E. None of the above


    正确答案:D

  • 第8题:

    139 Using the scenario in the special window, the project manager:

    A. will probably spend the weekend reviewing the data.

    B. Won't ask for the report again.

    C. Has a preference for written communication.

    D. Has chosen an inappropriate medium.

    E. Is experiencing communication overload


    正确答案:E

  • 第9题:

    ● Increasing resources on the critical path activities may not always shorten the length of the project because:

    A Certain activities are time-dependent rather than resource-dependent (i.e., using three ovens rather than one to bake a cake).

    B Safety, OSHA and EPA may have placed restrictions on the number of people used on certain activities or in the physical location of the project.

    C The skill level of the added resources might not be appropriate for the activities to be performed.

    D Adding more resources may create additional work and produce inefficiencies (i.e., additional people may need training and supervision.)

    E All of the above.


    正确答案:E

  • 第10题:

    ● A non-critical path activity is completed in half the time. Then,

    A The critical path is also reduced.

    B The slack in the path containing this activity will increase.

    C The total cost for this activity has decreased.

    D Manpower from this activity can be assigned to other activities.

    E All of the above.


    正确答案:B

  • 第11题:

    ( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.

    A.Parametric

    B.Analogous

    C.Three-point

    D.Expert judgment


    正确答案:B

  • 第12题:

    ( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.

    A.Parametric
    B.Analogous
    C.Three-point
    D.Expert judgment

    答案:B
    解析:
    类比估计是一项使用类似的活动或项目的历史数据,来估计活动的时间或成本的技术。 (73) A.参数 B.类比 C.三点 D.专家判断

  • 第13题:

    Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?

    A . P

    B . Q

    C . R

    D . S

    E . T


    正确答案:A

  • 第14题:

    142 Activities with zero time duration are referred to as:

    A. Critical path activites.

    B. Noncritical path activities.

    C. Slack time activities.

    D. Dummies

    E. None of above


    正确答案:D

  • 第15题:

    88 A non-critical path activity is completed in half the time. Then,

    A. The critical path is also reduced.

    B. The slack in the path containing this activity will increase.

    C. The total cost for this activity has decreased.

    D. Manpower from this activity can be assigned to other activities.

    E. All of the above


    正确答案:B

  • 第16题:

    111 Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:

    A. All activities.

    B. Only those activities with the longest time durations.

    C. Those activities on the critical path begining with the longest time duration activities.

    D. Those activities with the greatest degree of risk.

    E. None of the above


    正确答案:C

  • 第17题:

    170 Assume that you have a network where an activity on the critical path can be crashed by two weeks. If the activity is actually crashed by two weeks, then:

    A. The project's schedule will be reduced by 2 weeks.

    B. The available slack on the noncritical paths will increase.

    C. A new critical path may appear after the crash.

    D. All of the above.

    E. A and B only


    正确答案:C

  • 第18题:

    194 The schedule risk is the _____ .

    A. the accumulated "expected' durations which maintain project completion.

    B. Critical Path adjusted by "high-risk" activity float.

    C. highest risk path that maintains quality.

    D. Critical Path when calculated with "most likely" duration.

    E. highest risk path that contributes the most risk toward the project completion


    正确答案:B

  • 第19题:

    102 Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?

    A. Element P

    B. Element Q

    C. Element R

    D. Element S

    E. None of the above


    正确答案:C

  • 第20题:

    194 Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?

    A. P

    B. Q

    C. R

    D. S

    E. T


    正确答案:A

  • 第21题:

    ● Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:

    A All activities.

    B Only those activities with the longest time durations.

    C Those activities on the critical path begining with the longest time duration activities.

    D Those activities with the greatest degree of risk.

    E None of the above.


    正确答案:C

  • 第22题:

    You are the administrator of a SQL Server computer. Users report that the database times out when they attempt to modify data. You use the Current Activity window to examine locks held in the database as shown in the following screenshot.

    You need to discover why users cannot modify data in the database, but you do not want to disrupt normal database activities. What should you do?

    A.Use the spid 52 icon in the Current Activity window to discover which SQL statement is being executed

    B.Use the sp_who stored procedure to discover who is logged in as spid 52

    C.Use SQL Profiler to capture the activity of the user who is logged in as spid 52

    D.Use System Monitor to log the locks that are granted in the database


    正确答案:A
    解析:Explanation: The current activity window in SQL Server Enterprise Manager can be used to perform. ad hoc monitoring of an instance of SQL Server. This allows for the quick analysis of the volume and general types of activity on the system and can indicate current blocked and blocking transactions, currently connected users on an instance of SQL Server and the last statement executed and locks that are in effect on the database.

    In the screen shot of current activity window the icon, labeled spid 51, indicates that a database lock is in place; the second icon, labeled spid 52, can be used to identify the process that is blocking one or more connections; and the third icon, labeled spid 53, can be used to identify the process that is being blocked by another connection

    Incorrect Answers:
    B: The system stored procedure sp_lock can be used to return a result set that contains information about resources that are locked and the sp_who stored procedure provides information about current SQL Server 2000 users and processes. The information returned by the sp_who procedure can be filtered to return only current non-idle processes. This makes it possible to identify which resources are being locked and which processes are responsible for creating those locks. These stored procedures require more resources and more administrative effort than the Current Activity window. It is therefore not the best answer.

    C: The SQL profiler is not the best tool to immediately solve the locking problem. It could be used at a later moment if a long-term solution to the problem is required. SQL profiler would require more system resources and might impact normal database activities.

    Note: SQL Profiler is a graphical tool that allows system administrators to monitor events in an instance of SQL Server. Data pertaining to an event can be captured and saved to a file or SQL Server table to be analyzed at a later date. It can be is used to step through problem queries to find the cause of the problem; to find and diagnose slow-running queries; to capture the series of SQL statements that led to a problem; and to monitor the performance of SQL Server to tune workloads.

    D: SQL Server provides objects and counters that can be used by System Monitor in a Windows 2000 or by Performance Monitor in Windows NT 4.0 to monitor the system performance of computers running an instance of SQL Server. However, these counters are used for statistics and alerts and they cannot, in a direct way, be used to track down the cause of the locking problem.

  • 第23题:

    A critical path for a project is the series of activities that determine( )by which the project can be completed.

    A.the earliest time
    B.the latest time
    C.the total time
    D.the free time

    答案:A
    解析:
    翻译:关键路径通常由一系列决定项目工期的活动组成,它们决定了整个项目的( )。A.最早完成时间 B.最迟完成时间 C.总时间 D.自由时间