186 Methods and techniques used to examine cost and technical data are called feasibility studies. The economic aspects of a feasibility study include interest rates, present worth factors, operating costs, depreciation and _____.A. Capitalization costs.B

题目

186 Methods and techniques used to examine cost and technical data are called feasibility studies. The economic aspects of a feasibility study include interest rates, present worth factors, operating costs, depreciation and _____.

A. Capitalization costs.

B. Technical skill requirements.

C. Technology forecasting.

D. Strategic marketing intelligence.

E. All of the above


相似考题
更多“186Methods and techniques used to examine cost and technical data are called feasibility s ”相关问题
  • 第1题:

    Project ______is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.

    A.risk

    B.problem

    C.result

    D.data


    正确答案:A
    解析:风险是一个不确定因素或条件,如果它一旦发生,可能对至少一个项目目标,如项目进度、项目成本、项目范围或项目质量产生负面或正面的影响。选项A是风险,选项B是问题,选项C是结果,选项D是数据。根据项目风险定义,风险包括两方面含义:一是未实现目标;二是不确定性。因此应选择A。

  • 第2题:

    Project(71)is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.

    A.risk

    B.problem

    C.result

    D.data


    正确答案:A
    风险是一个不确定因素或条件,如果它一旦发生,可能对至少一个项目目标,如项目进度、项目成本、项目范围或项目质量产生负面或正面的影响。选项A是风险,选项B是问题,选项C是结果,选项D是数据。根据项目风险定义,风险包括两方面含义:一是未实现目标;二是不确定性。因此应选择A。

  • 第3题:

    Project( )is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.

    A.risk
    B.problem
    C.result
    D.data

    答案:A
    解析:
    风险不是一个不确定因素或条件,如果它一旦发生,可能对至少一个项目目标,如项目进度、项目成本、项目范围或项目质量产生负面或正面的影响。选项A是风险,选项B是问题,选项C是结果,选项D是数据。根据项目风险定义,风险包括两方面含义:一是未实现目标;二是不确定性。因此应选择A。

  • 第4题:

    ● Project()is an uncertain event or condition that ,if it occurs ,has a positive or a negative effect on at least one project objective ,such as time ,cost ,scope or quality()A. risk B. problem C. result D. data


    正确答案:A
    项目风险是一种不确定的事件或条年,一旦发生,至少会对一个项目目标,比如时间、成本、范围或质量造成正面或负面的影响。

  • 第5题:

    Project()is an uncertain event or condition that,if it occurs,has a positiveor a negative effect on at least one project objective,such as time,cost,scope, or quality.

    A.risk
    B.problem
    C.result
    D.data

    答案:A
    解析:
    风险是一个不确定因素或条件,如果它一旦发生,可能对至少一个项目目标,如项目进度、项目成本、项目范围或项目质量产生负面或正面的影响。选项A 是风险,选项B 是问题,选项 C 是结果,选项 D 是数据。根据项目风险定义,风险包括两方面含义:一是未实现目标;二是不确定性。因此应选择 A

  • 第6题:

    7、一个顺序栈S,其栈顶指针为top,则将元素e入栈的操作是()。

    A.S.data[top]=e;S.top++;

    B.S.top++;S.data[top]=e;

    C.S.data[top]=e;

    D.S.top=e;


    *S->top=e;S->top++;