Using the WBS in the Special window, an instance of a work package is:
A.Build house
B.Excavate
C.Prepare Foundation
D.B and C
E.None of the above
第1题:
Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:
A . 1.1
B . 0.9
C . 0.956
D . 1.15
E . 0.869
第2题:
Using the situation stated in the Special window, which WBS element is behind schedule but under budget?
A . Element P
B . Element Q
C . Element R
D . Element S
E None of the above.
第3题:
Using the situation stated in the Special window, what is the cost performance index for Case #9?
A . 1.1
B . 1.91
C . 0.83
D . 1.2
E . None of the above
第4题:
Using the possible loss outcomes shown in the Special window, find the expected (loss)
A ¥0
B ¥-1,300
C ¥-2,000
D ¥-3,000
E None of the above
第5题:
102 Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?
A. Element P
B. Element Q
C. Element R
D. Element S
E. None of the above
第6题:
106 Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.
A. Become worse, become worse
B. Become worse, improved
C. Improved, increased
D. Improved, become worse
E. None of the above are correct
第7题:
121 Using the WBS in the Special window, an instance of a work package is:
A. Build house
B. Excavate
C. Prepare Foundation
D. B and C
E. None of the above
第8题:
133 Using the WBS shown in the Special window, a typical work package would be:
A. Software development
B. Systems design
C. Coding
D. A, B, and C
E. None of the above
第9题:
● When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the
A task
B level of effort
C sub-task
D project
E work package
第10题:
● Using the WBS shown in the Special window, a typical work package would be:
A Software development
B Systems design
C Coding
D A, B, and C
E None of the above.
第11题:
● Using the WBS in the Special window, an instance of a work package is:
A Build house
B Excavate
C Prepare Foundation
D B and C
E None of the above
第12题:
第13题:
Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?
A . Element P
B . Element Q
C . Element R
D . Element S
E . None of the above.
第14题:
Using the situation shown in the Special window and assuming continues efficiency for work-in-progress and fixed price contract for task four. The estimate at completion is:
A . $19K
B . $21K
C . $26K
D . $29K
E . indeterminate
第15题:
Using the diagram in the Special window, what is the probability that Alternative I will be adopted and completed below budget:
A 1.4
B 0.8
C 0.2
D 0.12
E None of the above
第16题:
101 Using the situation stated in the Special window, which WBS element is behind schedule but under budget?
A. Element P
B. Element Q
C. Element R
D. Element S
E. None of the above
第17题:
103 Using the situation stated in the Special window, the cost performance index (CPI) for WBS Element R is:
A. 0.875
B. 1.14
C. 0.952
D. 0.833
E. 1.20
第18题:
113 Using the possible profit and loss outcomes shown in the Special window, find the expected profit (loss)
A. ($1000)
B. $1000
C. $2000
D. $1200
E. None of the above
第19题:
124 Using the situation stated in the Special window, what is the total variable costs for producing one widget?
A. $1,020
B. $1,010
C. $1,015
D. $20.00
E. None of the above
第20题:
137 Using the situation shown in the Special window and assuming continues efficiency for work-in-progress and fixed price contract for task four. The estimate at completion is:
A. $19K
B. $21K
C. $26K
D. $29K
E. indeterminate
第21题:
● Which of the following can be tracked using the WBS?
A time
B cost
C performance
D scope
E None of the above.
第22题:
● Which of the following can result in misinterpretation of the statement of work?
A Using imprecise language (i.e. nearly, approximately)
B Mixing tasks, specifications, special instructions and approvals
C No pattern, structure or chronological order
D Wide variation in the size of tasks or details of work
E All of the above
第23题:
● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.
(75)
A.independent resource
B.individual work load
C.work milestone
D.work package