Which of the following would most likely increase the accuracy of estimating the project cost?A . Pricing out the work at lower levels in the work breakdown structure.B . Using historical data.C . Talking to people who have worked on similar projects.D .

题目

Which of the following would most likely increase the accuracy of estimating the project cost?

A . Pricing out the work at lower levels in the work breakdown structure.

B . Using historical data.

C . Talking to people who have worked on similar projects.

D . All of the above.

E . A and C only.