更多“Using the situation stated in the Special window, what is the cost performance index for Case #9?A . 1.1B . 1.91C . 0.83D . 1.2E . None of the above”相关问题
  • 第1题:

    Using the situation stated in the Special window, what is the total variable costs for producing one widget?

    A . ¥1,020

    B . ¥1,010

    C . ¥1,015

    D . ¥20

    E . None of the above.


    正确答案:E

  • 第2题:

    Using the situation stated in the Special window, the labor rate cost variance is:

    A . ¥66,927

    B . ¥68,329

    C . ¥386

    D . ¥-0

    E . ¥18.36


    正确答案:D

  • 第3题:

    Using the situation stated in the Special window, WBS Element Q is _____ budget by _____ percent.

    A . Over, 16.66

    B . Under, 16.66

    C . Over, 10.0

    D . Under, 10.0

    E . None of the above.


    正确答案:A

  • 第4题:

    Using the situation stated in the Special window, the cost performance index (CPI) for WBS Element R is:

    A . 0.875

    B . 1.14

    C . 0.952

    D . 0.833

    E . 1.2


    正确答案:B

  • 第5题:

    Using the situation stated in the Special window, which WBS element is behind schedule but under budget?

    A . Element P

    B . Element Q

    C . Element R

    D . Element S

    E None of the above.


    正确答案:D

  • 第6题:

    101 Using the situation stated in the Special window, which WBS element is behind schedule but under budget?

    A. Element P

    B. Element Q

    C. Element R

    D. Element S

    E. None of the above


    正确答案:D

  • 第7题:

    103 Using the situation stated in the Special window, the cost performance index (CPI) for WBS Element R is:

    A. 0.875

    B. 1.14

    C. 0.952

    D. 0.833

    E. 1.20


    正确答案:B

  • 第8题:

    106 Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.

    A. Become worse, become worse

    B. Become worse, improved

    C. Improved, increased

    D. Improved, become worse

    E. None of the above are correct


    正确答案:E

  • 第9题:

    124 Using the situation stated in the Special window, what is the total variable costs for producing one widget?

    A. $1,020

    B. $1,010

    C. $1,015

    D. $20.00

    E. None of the above


    正确答案:E

  • 第10题:

    128 Using the situation stated in the Special window, what is present value of $1000 at 12% at the end of 5 years?

    A. $3605.00

    B. $0.57

    C. $567.00

    D. $892.86

    E. $3.61


    正确答案:C

  • 第11题:

    130 Using the situation stated in the Special window, what is the schedule variance for Case #8? A. 1000

    B. 2000

    C. -1000

    D. -2000

    E. 0


    正确答案:C

  • 第12题:

    9 Using the situation stated in the Special window, what is net present value of an annual income flow of $1600 at 14% over the next three years?

    A. $3713.60

    B. $0.68

    C. $1080.00

    D. $476.19

    E. $2.32


    正确答案:A

  • 第13题:

    Using the situation stated in the Special window, what is the total fixed costs for manufacturing the widgets?

    A . ¥3,000

    B . ¥27,000

    C . ¥27,270

    D . ¥1,335

    E . ¥1,000


    正确答案:E

  • 第14题:

    Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.

    A . Become worse, become worse

    B . Become worse, improved

    C . Improved, increased

    D . Improved, become worse

    E . None of the above are correct


    正确答案:E

  • 第15题:

    Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:

    A . 1.1

    B . 0.9

    C . 0.956

    D . 1.15

    E . 0.869


    正确答案:A

  • 第16题:

    Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?

    A . Element P

    B . Element Q

    C . Element R

    D . Element S

    E . None of the above.


    正确答案:C

  • 第17题:

    Using the diagram in the Special window, what is the probability that Alternative I will be adopted and completed below budget:

    A 1.4

    B 0.8

    C 0.2

    D 0.12

    E None of the above


    正确答案:D

  • 第18题:

    102 Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?

    A. Element P

    B. Element Q

    C. Element R

    D. Element S

    E. None of the above


    正确答案:C

  • 第19题:

    104 Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:

    A. 1.10

    B. 0.90

    C. 0.956

    D. 1.15

    E. 0.869


    正确答案:A

  • 第20题:

    108 Using the situation stated in the Special window, the labor rate cost variance is:

    A. $66,927

    B. $68,329

    C. $386

    D. -$0.22

    E. $18.36


    正确答案:D

  • 第21题:

    126 Using the situation stated in the Special window, what is the labor rate cost variance?

    A. $5500.00

    B. $1500.00

    C. -$100.00

    D. -$0.10

    E. $5600.00


    正确答案:D

  • 第22题:

    129 Using the situation stated in the Special window, what is the cost variance for Case #9?

    A. -$1000

    B. 1000

    C. -2000

    D. 2000

    E. 0


    正确答案:B

  • 第23题:

    132 Using the situation stated in the Special window, what is the cost performance index for Case #9?

    A. 1.10

    B. 1.91

    C. 0.83

    D. 1.20

    E. None of the above


    正确答案:A