You have summarized the project and note that , hours have been scheduled, , hours have been earned and , hours paid. The correct conclusion is:A.The project is operating at a favorable cost efficiency ratio.B.the project is spending more than plannedC.th

题目

You have summarized the project and note that , hours have been scheduled, , hours have been earned and , hours paid. The correct conclusion is:

A.The project is operating at a favorable cost efficiency ratio.

B.the project is spending more than planned

C.the project is behind schedule

D.the project is ahead of schedule

E.B and C


相似考题
更多“You have summarized the project and note that , hours have been scheduled, , hours have been earned and , hours paid. The correct conclusion is:A.The project is operating at a favorable cost efficiency ratio.B.the project is spending more than plannedC.th”相关问题
  • 第1题:

    159 The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:

    A. Multiplying the actual hours worked on the project by the budgeted labor rate.

    B. Multiplying the budgeted hours to complete the task by the budgeted labor rate.

    C. Dividing the actual hours required to complete the task by the budgeted labor rate.

    D. Cannot be determined.

    E. None of the above


    正确答案:B

  • 第2题:

    ● The financial closeout of a project dictates that:

    A All project funds have been spent.

    B No charge numbers have been overrun.

    C No follow-on work from this client is possible.

    D No further charges can be made against the project.

    E All of the above.


    正确答案:D

  • 第3题:

    You can have days with more or fewer than twenty-four hours, and ______ with more or fewer than seven days.

    A、years

    B、months

    C、seasons

    D、weeks


    标准答案:D

  • 第4题:

    If it has been over 12 hours since you missed a dose, you should .

    A. change the amount of your next dose

    B, eat more when taking your next dose

    C. have a dose as soon as you remember

    D. take the next dose at your regular time


    正确答案:D

  • 第5题:

    Working hours in the United States ____________over the past 20 years.

    A. have increased

    B. increased

    C. were increasing

    D. have been increased


    参考答案:A

  • 第6题:

    The project requires more labor than ____ because it is extremely difficult.

    A.has been put

    B.have been put

    C.being put in

    D.to.be put in


    答案:A

  • 第7题:

    What does a CPI of 80% mean? ( ) .

    A.As of now we expect the total pr gject cost of 80% more than planned

    B.When the project is completed, we will have spent 80% more

    C.Your project is only progressing at 80% of that planned

    D.Your project is only getting 80 cents out of every RMB invested


    正确答案:D
    CPI等于80%,意味你的项目只获得80美分的每元投资

  • 第8题:

    The project requires more labor than ________.

    [A] has been put in

    [B] have been put in

    [C] being put in

    [D] to be put in


    正确答案:A

  • 第9题:

    The Project Management Triangle is a model of the constraints of projectmanagement.These constraints have been listed scope(or quality),(73),and cost.

    A.resource
    B.time
    C.plan
    D.tool

    答案:B
    解析:
    项目管理三角形是一个项目管理约束模型。这些约束有范围(或质量),时间,和成本。

  • 第10题:

    They()for hours.

    • A、have been driving
    • B、have been driven
    • C、drove
    • D、drive

    正确答案:A

  • 第11题:

    Why is it important to have a final meeting on a project that has been cancelled?()

    • A、Document lessons learned
    • B、Assign responsibility
    • C、Close budget
    • D、Begin new project

    正确答案:A

  • 第12题:

    填空题
    ____(complete) the project as planned, we have to work two more hours a day.

    正确答案: To complete
    解析:
    句意:为了按计划完成这个项目,我们每天不得不多工作两个小时。本题考查动词不定式。通过句中的“planned”可知,该项目还没有完成,只是计划过,表示“将要完成”用动词不定式表达。故划线处填To complete。

  • 第13题:

    39 You have summarized the project and note that 28,000 hours have been scheduled, 25,000 hours have been earned and 26,000 hours paid. The correct conclusion is:

    A. The project is operating at a favorable cost efficiency ratio.

    B. the project is spending more than planned

    C. the project is behind schedule

    D. the project is ahead of schedule

    E. B and C


    正确答案:C

  • 第14题:

    They're very angry. They ____to see you for the last two or three hours.

    A.are managing

    B.will promise

    C.had made up their minds

    D.have been trying


    正确答案:D

  • 第15题:

    You can have days ______ more or fewer than twenty-four hours,

    A、between

    B、with

    C、for

    D、at


    标准答案:B

  • 第16题:

    The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned


    正确答案:C
    挣值管理(EVM)是一种常用的绩效测量方法。它综合考虑项目范围、进度与成本指标,帮助项目管理团队评估项目绩效。如果某个项目的成本绩效指数(CPI=EV/AC)值小于1.0,则说明已完成的工作的成本超支(the cost overrun for work completed)。

  • 第17题:

    We ( ) on it for many hours but we have not yet reached any conclusion.

    A、have had worked

    B、have been working

    C、are working

    D、work


    参考答案:B

  • 第18题:

    The earned value technique is a commonlyused method of performance measurement. It integrates project scope, cost, andschedule measures to help the project management team assess projectperformance.If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, itmeans that (74).

    A.the project is ahead of its planned schedule

    B.less work was completed than was planned

    C.the cost overrun for work completed

    D.the cost under-run of performance to date


    正确答案:B
    此题主要考查挣值分析法的相关概念,它综合了范围、时间和成本数据,主要用于实际成本的绩效测量。基本思想是通过测量和计算已完成工作的预算费用与已完成工作的实际费用,将其与计划工作预算费用相比较得到项目的费用偏差,从而达到判断项目成本和进度计划执行情况,来帮助项目管理团队分析项目的完成情况,衡量项目的成本效率,为成本控制提供依据。挣值分析法主要涉及到3个参数,4个指标。其中3个参数如下:?计划工作量的预算成本(PV),已完成工作量的预算成本(EV),已完成工作量的实际成本(AC)?4个指标是指CV,SV,CPI,SPI:进度偏差(SV)是项目进度绩效的一种指标。成本偏差(CV)是项目成本绩效的一种指标。进度绩效指数(SPI)是比较项目已完成进度与计划进度的一种指标。当SPI小于1.0时,说明已完成的工作量未达到计划要求;当SPI大于1.0时,则说明已完成的工作量超过计划。SPI等于EV与PV的比值。公式:SPI=EV/PV。成本绩效指数(CPI)是比较已完成工作的价值与实际成本的一种指标。它考核已完成工作的成本效率。当CPI小于1.0时,说明已完成工作的成本超支;当CPI大于1.0时,则说明到目前为止成本有结余。CPI等于EV与AC的比值。公式:CPI=EV/AC。

  • 第19题:

    The Project Management Triangle is a model of the constraints of project management. These constraints have been listed scope (or quality),(), and cost.

    A.resource

    B.time

    C.plan

    D.tool


    正确答案:B

  • 第20题:

    The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than1.0, it means that_().

    A.the project is a head of its planned schedule
    B.less work was completed than was planned
    C.the cost overrun for work completed
    D.the cost under-run of performance to date

    答案:B
    解析:
    挣值技术是一种综合了范围、成本、进度指标的绩效测量方法,帮助项目团队评价项目绩效。如果一个项目的进度绩效指数SPI值小于1,意味着:(74)A.项目滞后B.项目超前C.项目超支D.成本有结余

  • 第21题:

    What does A.CPI of 80%mean?( ).

    A.As of now we expect the total project cost of 80%more than planned
    B.When the project is completed,we will have spent 80%more
    C.Your project is only progressing at 80%of that planned
    D.Your project is only getting 80 cents out of every RMB invested

    答案:D
    解析:
    翻译:
    CPI等于80%,意味着?(74)
    A.目前我们预计比原计划多出80%的项目总成本
    B.当项目完成后,我们会多花费80%
    C.项目进度是只在80%的计划进度
    D.项目只获得80美分每支出人民币1元。

  • 第22题:

    他们工作四小时,休息八小时。()

    • A、They work four hours and have four hours for rest.
    • B、They work eight hours and have four hours for rest.
    • C、They work four hours and have eight hours for rest.
    • D、They work eight hours and have eight hours for rest.

    正确答案:C

  • 第23题:

    单选题
    You are really incompetent! It ______ hours ago.
    A

    finished  

    B

    should be finished

    C

    must be finished  

    D

    should have been finished


    正确答案: D
    解析:
    你真是不称职。这项工作应该在几小时以前就完成了。这里采用与过去相反的虚拟语气,即should have done的形式,故D项正确。