Parametric cost estimating involves
A.using the WBS to do bottom up estimates
B.defining the perimeters of the life-cycle
C.calculating the individual estimates of work packages
D.using a statistical model to estimate costs
E.A and C
第1题:
22 The three most common types of project cost estimates are:
A. Order of magnitude, parametric, and budget.
B. Parametric, definitive and top down.
C. Order of magnitude, definitive and bottom up.
D. Order of magnitude, budget and definitive.
E. Analogy, parametric and top down