Guidelines for estimating time durations include:
A.Assuming a normal level of labor and equipment.
B.Assuming a normal work week.
C.Using consistent time units
D.Using past actual durations as guides.
E.All or part of each of the above.
第1题:
79 Time management is the allocation of time in a project's life cycle through the process of:
A. Planning
B. Estimating.
C. Scheduling.
D. Controlling
E. All of the above.
第2题:
● A Work Breakdown Structure:
A assures all work is identified
B subdivides the project into manageable segments
C provides the project sponsor with a time-phase task summary
D both A and B
E All of the above.
第3题:
● Bar charts are most appropriate for:
A Comparing actual to planned performance to each activity.
B Showing slack time.
C Showing critical path dependencies.
D Showing which activities can be rearranged in parallel.
E All of the above.
第4题:
● Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is following the process- Estimate Activity Durations.
(74)
A.Develop Schedule
B.Estimate Activity Resources
C.Define Activities
D.Sequence Activities
第5题:
Estimate activity durations is the processof estimating the number of work periods to complete indivities with estimatedresources . the tools and technques is not including().
A.expert judgment
B.analogous estimating
C.requiremen tstraceability matrix
D.three-point estimating
第6题:
Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.
A.Develop Schedule
B.Estimate Activity Resources
C.Define Activities
D.Sequence Activities
第7题:
A、having fun
B、studying late at night
C、finding a job
D、doing a part-time job
第8题:
[A] actual
[B] common
[C] special
[D] normal
第9题:
第10题:
第11题:
Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.
第12题:
attended
presented
joined
took part in
第13题:
166 Guidelines for estimating time durations include:
A. Assuming a normal level of labor and equipment.
B. Assuming a normal work week.
C. Using consistent time units
D. Using past actual durations as guides.
E. All or part of each of the above
第14题:
● Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:
A All activities.
B Only those activities with the longest time durations.
C Those activities on the critical path begining with the longest time duration activities.
D Those activities with the greatest degree of risk.
E None of the above.
第15题:
● (73) is one of the techniques used for estimating activity durations.
(73)
A.Analogous Estimating
B.Precedence Diagramming Method (PDM)
C.Dependency Determination
D.Schedule network Templates
第16题:
Estimating activity durations uses information on activity scope of(74) , required resource types, estimated resource quantities, and resource calendars.
A.milestone
B.baseline
C.quality
D.work
第17题:
______is one of the techniques used for estimating activity durations.
A.Analogous Estimating
B.Precedence Diagramming Method(PDM)
C.Dependency Determination
D.Schedule network Templates
第18题:
This passage is intended to __________.
A. discuss part-time jobs for students in general
B. encourage students to take up part-time jobs
C. show the benefits of part-time jobs to students' studies
D. praise boys and girls who work part time
第19题:
The carrying vessel chartered by the Seller shall sail and arrive at the port of departure within the normal and reasonable period of time.()
第20题:
Estimating activity durations uses information on activity scope of (74), required resource types, estimated resource quantities, and resource calendars.
(74)
A. milestone
B. baseline
C. quality
D. work
第21题:
第22题:
第23题:
milestone
baseline
quality
work