Project management provides organizations with a methodology to:ABecome more efficient and effective in accomplishing goals that cannot be handled well by the traditional structureBManage high risk repetitive workCProvide clients with multiple points of c

题目

Project management provides organizations with a methodology to:

ABecome more efficient and effective in accomplishing goals that cannot be handled well by the traditional structure

BManage high risk repetitive work

CProvide clients with multiple points of contact

DProvide guidance in accomplishing repetitive activities

EAll of the above


相似考题
更多“Project management provides organizations with a methodology to:ABecome more efficient and ”相关问题
  • 第1题:

    Provides 3 properties that make an OS, a RTOS?


    正确答案:
     

  • 第2题:

    Refer to Topic TestKing.com in iPAD document.What happens to the network when TestKingX is reconnected and a trunk exists between the two switches?()

    A. All VLANs except the default VLAN will be removed from all switches.

    B. All existing switches will have the students, admin, faculty, Servers, Management,Production, and no-where VLANs.

    C. The VLANs Servers, Management, Production, and no-where will replace the VLANs on SwX.

    D. The VLANs Servers, Management, Production, and no-where will be removed from existing switches.


    参考答案:D

  • 第3题:

    ()is a document?generated by the?creating?WBS?process?that?support the WBS,which provides?more?detailed?descriptions?of the components in the?WBS.

    A.The project?charter
    B.The?project?scope statement
    C.The?WBS dictionary
    D.The?activity list

    答案:C
    解析:
    本题翻译:()是由支持WBS的创建WBS过程生成的文档,它提供了WBS中组件的更详细描述。
    A.项目章程B.项目范围说明书C.WBS词典D.活动列表
    本题考查的是范围管理中的WBS词典,正确选项为C:WBS词典。
    在制作WBS的过程中,要给WBS的每个部分赋予一个账户编码标志符,它们是成本、进度和资源使用信息汇总的层次结构。需要生成一些配套的文件,这些文件需要和WBS配套使用,称为WBS词典。所以说WBS词典是创建WBS过程生成的支持WBS的文档,它提供了WBS中组件的更详细描述。

  • 第4题:

    Project (75).Management:includes the processes required to ensure that the project includes au the word required, and only the work required, to complete the project successfully.

    A.Integration

    B.Configuration

    C.Scope

    D.Requirement


    正确答案:C

  • 第5题:

    In?project?net work?diagram,the?number?of?critical?path?is()。

    A.none
    B.only?one
    C.only?two
    D.one?or?more

    答案:D
    解析:
    本题翻译:在项目网络工作图中,关键路径的数目是()。
    A.没有B.只有一个C.只有两个D.一个或更多
    本题考查的是进度管理中的关键路径,正确选项为D一个或更多。
    在一个网络图中关键路径有一条或多条,关键路径是项目中时间最长的活动顺序,决定着可能的项目最短工期。

  • 第6题:

    methodology
    Methodology is the principle and techniques of teaching with no necessary reference to linguistics.