During the planning phase of a project, you realize that more than one functional department possesses the skill and technical know-how to perform. a given task. The best way for the project manager to handle this would be to:A.Make the decision, document

题目

During the planning phase of a project, you realize that more than one functional department possesses the skill and technical know-how to perform. a given task. The best way for the project manager to handle this would be to:

A.Make the decision, document it in the linear responsibility chart, and distribute the chart to all departments.

B.Let the affected line groups decide among themselves who will perform. the work

C.Ask the executive sponsor to make the decision

D.Allow each line group to perform. part of the task

E.All of the above


相似考题
更多“During the planning phase of a project, you realize that more than one functional departme ”相关问题
  • 第1题:

    148 Network schedules are prepared during the _____ phase and updated during the _____ phase. A. Conceptual, execution.

    B. Development, implementation.

    C. Development, close-out.

    D. Implementation, close-out.

    E. Planning, finishing


    正确答案:B

  • 第2题:

    125 Middle (functional) managers have the greatest influence in the direction of the project in which type of organizational structure?

    A. Project.

    B. Strong matrix.

    C. Weak matrix.

    D. Project coordinator.

    E. Project expeditor


    正确答案:C

  • 第3题:

    7. If you were in Sahara,you ________ the value of fresh water.

    A. will realize

    B. realized

    C. would realize

    D. realize


    正确答案:C
    7.C【解析】虚拟语气。

  • 第4题:

    30 Network schedules are prepared during the _____ phase and updated during the _____ phase. A. Conceptual, execution.

    B. Development, implementation.

    C. Development, close-out.

    D. Implementation, close-out.

    E. Planning, finishing


    正确答案:B

  • 第5题:

    In his composition there are ________errors _______a few misspellings.

    A: no other ... than

    B: some other ... than

    C: more ... than

    D: other ... than


    参考答案: A

  • 第6题:

    In?project?net work?diagram,the?number?of?critical?path?is()。

    A.none
    B.only?one
    C.only?two
    D.one?or?more

    答案:D
    解析:
    本题翻译:在项目网络工作图中,关键路径的数目是()。
    A.没有B.只有一个C.只有两个D.一个或更多
    本题考查的是进度管理中的关键路径,正确选项为D一个或更多。
    在一个网络图中关键路径有一条或多条,关键路径是项目中时间最长的活动顺序,决定着可能的项目最短工期。